Dokouheh power station (نیروگاه سیکل ترکیبی دوکوهه) is an operating power station of at least 307-megawatts (MW) in Andimeshk, Khuzestan, Iran with multiple units, some of which are not currently operating. It is also known as Andimeshk D-Mountain Combined Cycle Power Plant, Dukoheh Andimeshk power plant,.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Dokouheh power station Andimeshk, Khuzestan, Iran 32.52183, 48.22096 (exact)[1][2]

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit GT, Unit ST: 32.52183, 48.22096

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year Retired year
Unit GT operating[3][4] gas[5][3] 307[5][3][4] gas turbine[6][7][3][4] not found 2023[3][8][6][4]
Unit ST construction[3][4] waste heat[5][3] 141[4] steam turbine[6][7][3][4] not found 2024[3][8][6][4]

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit GT Iranian Thermal Power Plants Holding Company (TPPH)[2] Iranian Thermal Power Plants Holding Company (TPPH) [100.0%]
Unit ST Iranian Thermal Power Plants Holding Company (TPPH)[2] Iranian Thermal Power Plants Holding Company (TPPH) [100.0%]

Background

Dokouheh power station is located on the 15th kilometer of Karkheh Dam Road.[9] This is near the Andimeshk-3 power station (at the 10th km), and the two are easily confused given they are both often referred to as the "Andimeshk Combined Cycle Power Plant" and have similar construction timelines.Originally the Dokouheh power station was scheduled by the Ministry of Energy to be commissioned from 2019-2020.[10] Construction was well underway in 2020. The 307 MW gas turbine was scheduled to operate in open cycle mode by the end of 2021, and the steam turbine would be added the year after to convert the plant to combined cycle mode.[11]The gas turbine was connected to the grid in March 2021.[12]

Articles and Resources

References

  1. https://www.google.com/maps/place/%D9%86%DB%8C%D8%B1%D9%88%DA%AF%D8%A7%D9%87+%D8%B3%DB%8C%DA%A9%D9%84+%D8%AA%D8%B1%DA%A9%DB%8C%D8%A8%DB%8C+%D8%AF%D9%88%DA%A9%D9%88%D9%87%D9%87+%D8%A7%D9%86%D8%AF%DB%8C%D9%85%D8%B4%DA%A9%E2%80%AD/@32.521910748.21878921585m/data=!3m1!1e3!4m5!3m4!1s0x0:0x98dc541e65f30d80!8m2!3d32.5216749!4d48.2229602. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 2.2 https://web.archive.org/web/20210623210215/https://www.mapnamd3.com/EN/Projects/Details/44/Dokouhe-CCPP-F-Class. Archived from the original on 23 June 2021. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 https://news.tpph.ir/fa/News/8465. {{cite web}}: Missing or empty |title= (help)
  4. 4.0 4.1 4.2 4.3 4.4 4.5 4.6 4.7 https://mapnagroup.com/18127/mapna-synchronizes-gas-unit-of-dokouheh-power-plant-to-grid/?lang=en. {{cite web}}: Missing or empty |title= (help)
  5. 5.0 5.1 5.2 https://web.archive.org/web/20220709112725/https://en.sabainv.com/second-steam-cycle-of-jahrom-power-plant-synchronized-to-the-grid-2-2-2/. Archived from the original on 09 July 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  6. 6.0 6.1 6.2 6.3 https://web.archive.org/web/20210730234113/https://khabarban.com/a/30466128. Archived from the original on 30 July 2021. {{cite web}}: Missing or empty |title= (help)
  7. 7.0 7.1 https://mapnamd3.com/?p=12352&lang=en. {{cite web}}: Missing or empty |title= (help)
  8. 8.0 8.1 https://web.archive.org/web/20220709082134/https://www.nsenergybusiness.com/projects/andimeshk-iii-combined-cycle-power-project/. Archived from the original on 09 July 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  9. سایت, مدیر (January 1, 2020). "MAPNA Group Dispatches First F-class Turbine to Andimeshk Power Plant". Sabainv Company. Archived from the original on July 9, 2022. Retrieved July 11, 2022.
  10. Iran Electric Power Industry (2017-2018), Islamic Republic of Iran Ministry of Energy & Tavanir Holding Company
  11. "khabarban.com/a/30466128". Archived from the original on July 30, 2021.
  12. اتصال توربین نیروگاه سیکل ترکیبی دوکوهه اندیمشک به شبکه برق سراسری کشور, Khabarban, Apr 9, 2021