Guangdong Xingning power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Guangdong Xingning power station (华润电力兴宁发电厂) is a power station in Heshui Town, Xingning, Meizhou, Guangdong, China with multiple units of varying statuses, none of which are currently operating. It is also known as China Resources Xingning power station.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Guangdong Xingning power station | Heshui Town, Xingning, Meizhou, Guangdong, China | 24.283019, 115.7057154 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Phase I Unit 1, Phase I Unit 2, Phase II Unit 3, Phase II Unit 4: 24.283019, 115.7057154
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year | Retired year |
---|---|---|---|---|---|---|
Phase I Unit 1 | retired | coal: anthracite | 135 | subcritical | 2006 | 2017 |
Phase I Unit 2 | retired | coal: anthracite | 135 | subcritical | 2007 | 2017 |
Phase II Unit 3 | cancelled | coal: waste coal | 350 | subcritical | – | – |
Phase II Unit 4 | cancelled | coal: waste coal | 350 | subcritical | – | – |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Phase I Unit 1 | China Resources POWER (Xingning) Co Ltd [100%] | China Resources Power Holdings Co Ltd [100.0%] |
Phase I Unit 2 | China Resources POWER (Xingning) Co Ltd [100%] | China Resources Power Holdings Co Ltd [100.0%] |
Phase II Unit 3 | China Resources POWER (Xingning) Co Ltd [100%] | China Resources Power Holdings Co Ltd [100.0%] |
Phase II Unit 4 | China Resources POWER (Xingning) Co Ltd [100%] | China Resources Power Holdings Co Ltd [100.0%] |
Background
The two coal-fired units of Guangdong Xingning power station, totaling 270 MW, were brought online in 2006 and 2007; they run on anthracite coal. The plant is owned by China Resources.[1]
Both units were retired in September 2017.[2][3]
Description of Expansion
China Resources were planning to build two additional waste coal-fired units at this plant, with a total planned capacity of 700 MW.[4][1][5]
However, with no developments since 2014, the project appears to be abandoned.
Articles and Resources
References
- ↑ 1.0 1.1 "华润电力投资有限公司华南分公司兴宁项目人才招聘公告,", HDJOB, October 15, 2014
- ↑ "广东推进淘汰煤电落后产能,八电厂入围,鼓励提前关停," Sohu, 2017-09-01
- ↑ "广东省2017年9月关停华润电力(兴宁)电厂2台13.5万千瓦小火电机组公示," 中国电力化工网, 2017-09-22
- ↑ "华润电力(兴宁)有限公司", 华润电力, Aug 27, 2014
- ↑ "华润电力(兴宁)有限公司简介", 北极星火电, 2014-10-15
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.