Daqing Oil Central power station (中石油大庆油田热电厂) is an operating power station of at least 900-megawatts (MW) in 185 Fengyang Road, Longfeng District, Daqing, Heilongjiang, China. It is also known as 大庆油田热电厂上大压小热电联产项目 (Unit 4).
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Daqing Oil Central power station | 185 Fengyang Road, Longfeng District, Daqing, Heilongjiang, China | 46.5528282, 125.0739301 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2, Unit 3, Unit 4: 46.5528282, 125.0739301
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Unit 1 | operating | coal: bituminous | 200 | subcritical | 1991 |
Unit 2 | operating | coal: bituminous | 200 | subcritical | 1992 |
Unit 3 | operating | coal: bituminous | 200 | subcritical | 1993 |
Unit 4 | operating | coal: lignite | 300 | subcritical | 2013 |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Unit 1 | PetroChina Daqing Petrochemical Co [100%] | PetroChina Co Ltd [100.0%] |
Unit 2 | PetroChina Daqing Petrochemical Co [100%] | PetroChina Co Ltd [100.0%] |
Unit 3 | PetroChina Daqing Petrochemical Co [100%] | PetroChina Co Ltd [100.0%] |
Unit 4 | PetroChina Daqing Petrochemical Co [100%] | PetroChina Co Ltd [100.0%] |
Project-level captive use details
- Captive industry use (heat or power): both
- Captive industry: Oil & Refining
- Non-industry use: heat
Background
Daqing power station began as a three-unit coal-fired power plant with a total capacity of 600 MW. The plant was completed between 1991 and 1993, and is owned by China National Petroleum Corporation.[1]
Expansion
China National Petroleum Corporation planned to build an additional coal-fired unit at this plant, with a capacity of 300 MW.[2][3]
The new unit was completed in 2013.[4]
Pollution
The power station was fined in 2015 for violating pollution limits in Heilongjiang Province.[5]
Articles and Resources
References
- ↑ Daqing Powerplant, Enipedia, accessed Sept. 2015.
- ↑ "大庆油田热电厂“上大压小”扩建工程建设纪实", 北极星电力网首页, 2013-6-4
- ↑ "大庆油田重点工程建设全速推进", 中国石油新闻中心,2012-09-25
- ↑ "大庆油田热电项目完成168小时试运行," China Engineering Group, 2013-10-8
- ↑ "大庆3家热电厂违法排污被“按日计罚”204万元," 经济参考报, 2015年05月18日