Aboano power station

From Global Energy Monitor
(Redirected from Ghana Coal power station)
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Aboano power station is a cancelled power station in Otuam, Aboano, Ekumfi District, Central region, Ghana. It is also known as Ekumfi Aboano power station.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Aboano power station Otuam, Aboano, Ekumfi District, Central region, Ghana 5.666667, -1.0 (approximate)

The map below shows the approximate location of the power station.

Loading map...


Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology
Unit 1 cancelled coal: unknown 350 unknown
Unit 2 cancelled coal: unknown 350 unknown
Unit 3 cancelled coal: unknown 1400 unknown

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1 Sunon Asogli Power Ltd [100%] Shenzhen Energy Group Co Ltd [60.0%]; China African Development Fund [40.0%]
Unit 2 Sunon Asogli Power Ltd [100%] Shenzhen Energy Group Co Ltd [60.0%]; China African Development Fund [40.0%]
Unit 3 Sunon Asogli Power Ltd [100%] Shenzhen Energy Group Co Ltd [60.0%]; China African Development Fund [40.0%]

Project-level coal details

  • Coal source(s): Imported - South Africa, Colombia

Financing

  • Source of financing: China-Africa Development Fund (US$1.5 billion)

Background

In July 2013, it was reported that the Ghana Coal power station would cost US$700 million and be built within 2.5 years. Once operating, the plant will burn 2 million tons of coal per year, which will be imported from South Africa. The construction of the plant will also include a new coal port to receive the coal. The project is proposed by Shenzhen Energy Group (SEG), the parent company of Sonon Asogli Power.[1]

The feasibility studies were completed in 2014, and the project was then estimated at US$1.5 billion. The Ghana ministry agreed to coordinate with Shenzhen Energy for the formation of a joint venture to invest and build the coal plant, with construction estimated at 36 months or longer from the commencement stage.[2]

In September 2014, it was reported that Ghana electric utility Volta River Authority (VRA) had signed a memorandum of understanding with Shenzhen Energy Group to develop a 1,200 MW coal-fired power plant in Ghana. Volta River Authority said it will work with locally-based Sunon Asogli Power Ghana to bring the power station online by 2018.[3]

In September 2015, VRA and Shenzhen said the power station would be 2,000 MW, and may be established at Otuam in the Central region. The target date was 2019. Feasibility studies are ongoing.[4]

In December 2015, VRA and Shenzhen released a pre-feasibility environmental and social impact assessment for phase I: 2x350MW supercritical coal plant, including an affiliated coal handling terminal. Phase II would be a 4X350MW or 2X600MW supercritical coal plant. Coal would be imported from South Africa. The project, which is planned for construction in 2017 and commercial operation in 2020, is estimated to cost US$1.5 billion.[5]

In April 2016, the Environmental Protection Agency (EPA), in collaboration with the Volta River Authority (VRA), held a public forum to assess the environmental impact of the plant, reported to be 2,100 MW (Phase I of 700 MW and Phase II of 1,400 MW) and located at Ekumfi Aboano, in the Ekumfi District of the Central Region. Apart from the power plant, another component of the project is a harbour to import the coal from South Africa and Colombia.[6]

As of October 2016, comments by Minister of the Environment Mahama Ayariga indicated that the project had been shelved due to climate change concerns. Speaking at a press conference alongside US EPA Administrator Gina McCarthy, Ayariga asserted that the Aboano plant would not be built. As initially posted in an article in Ghana Business News, Ayariga is quoted as follows: “Ghana is not setting up a coal plant. Somebody has put in an application, which has not been approved. For the rest of my term as the Minister of Environment, I will not be signing a permit for anyone to put up a coal plant when Ghana has just ratified the Climate Change Agreement”.[7]

Later, for unknown reasons, the original definitive quote by Avariga was couched less definitively. As of December 18, 2016, the quote in the October 10 Ghana Business News article was changed to the following: “I don’t think we are setting up a coal plant. Somebody has put in an application to set up a coal power plant, he hasn’t been given permission to set up a coal power plant.”[8]

In May 2017, Shenzhen Energy Group in collaboration with Volta River Authority (VRA) submitted an ESIA for a 2×350MW supercritical coal-fired plant (including an affiliated coal handling terminal) along the coastline of Aboano. According to the ESIA, the first phase of the project is planned to commence in December 2017 and be completed in 2020-2021. The principal source of coal for the project would be imported from South Africa and shipped from the Richards Bay Coal Terminal. The project is estimated to cost US$1.5 billion.[9]

In June 2017, the Ghanaian president announced that new power projects in the country would only be renewable energy-based. In 2020, Ghanaian activist Chibeze Ezekiel was awarded the Goldman environmental prize for his efforts in halting the project as part of 350 Ghana Reducing Our Carbon (350 GROC).[10]

Funding

In March 2016, the China-Africa Development Fund announced it will provide US$1.5 billion to finance the two 350 MW units.[11]

Opposition

Ghana Youth Environmental Movement protest, June 5, 2016

In February 2016, the Ghana Youth Environmental Movement called for a separate Environmental and Social Impact Assessment (ESIA) to be done on the project, saying it came to the “shocking conclusion that a greater section of the public and the media were not adequately aware and informed about the project” and "We therefore call for a number of coordinated public hearings and press conferences to further discuss it." The group also noted the "Scoping Report indicated that children in Ekumfi Aboano are 55.9% of the entire population of 1,900 people. Children are very vulnerable especially to air-borne pollutants such as PM10 and smog."[12]

In response to heavy flooding in Accra and other locations in June 2016, 350 Africa and G-ROC (Ghana Reducing Our Carbon) expressed opposition to a coal-fired power plant in the country and vowed to block it.[13]

Articles and Resources

References

  1. "Asogli To Put Up A 700 Mw Coal-Fired Power Plant" Government of Ghana, July 5, 2013
  2. "Proposed coal plant to cost US$1.5bn," WACEE, March 11, 2014
  3. "Volta River Authority signs MOU for 1,200MW coal power plant," ESI Africa, September 17, 2014
  4. "Ghana targets power from coal - First plant to be completed in 2019," Graphic Online, September 19, 2015
  5. "2x350MW Ghana Supercritical Coal Fired Power Plant - Scoping Report," Volta River Authority and Shenzhen Energy, December 1, 2015
  6. "Ghana to Build a $1.5 Billion Coal Power Plant At Ekumfi Aboano in the Central Region," All Africa, April 7, 2016
  7. "Ghana is not building a coal plant – Minister," Ghana Business News, October 10, 2016
  8. "Ghana Is Not Building a Coal Plant - Minister," Ghana Business News, October 10, 2016
  9. ESIA, Shenzhen Energy Group and Volta River Authority, May 2017
  10. "Chibeze Ezekiel," Goldman Environmental Foundation, accessed December 1, 2020
  11. "China to fund 700MW VRA coal plant," B&FT Online, March 15, 2016
  12. "GYEM to Government: We Reject Coal Power in Ghana," GhanaWeb, February 2, 2016
  13. Lerato Letebele, "More rain, less freshwater: Why the government of Ghana needs to stop coal expansion," 350 Africa, June 22, 2016

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.