Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Wuhu power station (华电安徽芜湖发电厂) is an operating power station of at least 2320-megawatts (MW) in Chongjiang Road, Sanshan, Wuhu, Anhui, China with multiple units, some of which are not currently operating.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Wuhu power station | Chongjiang Road, Sanshan, Wuhu, Anhui, China | 31.2374445, 118.1494403 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Phase II Unit 3, Phase II Unit 4: 31.2374445, 118.1494403
- Phase I Unit 1, Phase I Unit 2: 31.2372348, 118.1497184
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Phase I Unit 1 | operating | coal: bituminous | 660 | ultra-supercritical | 2008 |
Phase I Unit 2 | operating | coal: bituminous | 660 | ultra-supercritical | 2008 |
Phase II Unit 3 | operating | coal: bituminous | 1000 | ultra-supercritical | 2018 |
Phase II Unit 4 | cancelled | coal: bituminous | 1000 | ultra-supercritical | – |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Phase I Unit 1 | Anhui Huadian Wuhu Power Co Ltd [100%] | Huadian Power International Co Ltd [65.0%]; Huaihe Energy Holding Group Co Ltd [29.0%]; other [3.1%]; China Cinda Asset Management Co Ltd [2.9%] |
Phase I Unit 2 | Anhui Huadian Wuhu Power Co Ltd [100%] | Huadian Power International Co Ltd [65.0%]; Huaihe Energy Holding Group Co Ltd [29.0%]; other [3.1%]; China Cinda Asset Management Co Ltd [2.9%] |
Phase II Unit 3 | Anhui Huadian Wuhu Power Co Ltd [100%] | Huadian Power International Co Ltd [65.0%]; Huaihe Energy Holding Group Co Ltd [29.0%]; other [3.1%]; China Cinda Asset Management Co Ltd [2.9%] |
Phase II Unit 4 | Anhui Huadian Wuhu Power Co Ltd [100%] | Huadian Power International Co Ltd [65.0%]; Huaihe Energy Holding Group Co Ltd [29.0%]; other [3.1%]; China Cinda Asset Management Co Ltd [2.9%] |
Background
The two existing coal-fired units of Wuhu power station, totaling 1,320 MW, were brought online in May 2008. The plant is owned by China Huadian.[1][2][3]
Description of Expansion
Huadian is planning to build two additional coal-fired units at this plant, with a total planned capacity of 2,000 MW. The project was announced in January 2013.[4] The sponsors applied for environmental clearance in 2015.[5]
Unit 3 received a construction permit from Anhui Provincial DRC in October 2015,[6] and began construction in 2016. It is planned for operation in 2018.[7][8] Construction on unit 4 was reported in 2016,[9] but seems unlikely, since the plant has not been permitted.
Unit 3 was commissioned in December 2018.[10]
As of June 2020 there have been no developments on Unit 4, and it appears to be shelved.
Articles and Resources
References
- ↑ Anhui Huadian Wuhu Coal Power Plant China, Global Energy Observatory, accessed 2014-11.
- ↑ Huadian Wuhu Powerplant, Enipedia, accessed 2014-11.
- ↑ China Huadian's Wuhu Power Plant Begins Operation in Central China's Anhui Province, Industrial Info Resources, 2008-06-03.
- ↑ "安徽华电芜湖发电有限公司二期2×1000MW扩建工程,", 安徽环境信息网, 2014-03-17.
- ↑ "中国电力化工网, 2015-09-06
- ↑ "安徽发改委拟核准华电芜湖电厂二期第一台机组扩建项目"北极星电力网, 2015/9/24
- ↑ "华电芜湖发电公司二期1×1000MW工程项目获批开展前期工作," China Power, 2015年1月9日
- ↑ "华电芜湖电厂二期百万工程正式开工建设"人民网, 2016-4-29
- ↑ "华电芜湖电厂建设2台100万千瓦级火电机组," China 5e, 2016-3-30
- ↑ "芜湖电厂二期2×100万千瓦超超临界燃煤发电工程3号机组投运," 北极星电力网新闻中心, 2018/12/29
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.