Qinhuangdao power station (京能秦皇岛热电) is an operating power station of at least 700-megawatts (MW) in Xiaxvgezhuang, Funing District, Qinhuangdao, Hebei, China with multiple units, some of which are not currently operating. It is also known as 中煤能秦皇岛热电二期.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Qinhuangdao power station Xiaxvgezhuang, Funing District, Qinhuangdao, Hebei, China 39.925144, 119.378781 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Phase I Unit 1, Phase I Unit 2, Phase II Unit 3, Phase II Unit 4: 39.925144, 119.378781

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year
Phase I Unit 1 operating coal: unknown 350 supercritical 2019
Phase I Unit 2 operating coal: unknown 350 supercritical 2020
Phase II Unit 3 permitted coal: unknown 660 ultra-supercritical
Phase II Unit 4 permitted coal: unknown 660 ultra-supercritical

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Phase I Unit 1 Jingneng Qinhuangdao Thermal Power Co Ltd [100%] Beijing Jingneng Power Co Ltd [100.0%]
Phase I Unit 2 Jingneng Qinhuangdao Thermal Power Co Ltd [100%] Beijing Jingneng Power Co Ltd [100.0%]
Phase II Unit 3 Jingneng Qinhuangdao Thermal Power Co Ltd [100%] Beijing Jingneng Power Co Ltd [100.0%]
Phase II Unit 4 Jingneng Qinhuangdao Thermal Power Co Ltd [100%] Beijing Jingneng Power Co Ltd [100.0%]

Project-level coal details

  • Permit(s):

Background on Project

In April 2015 the Hebei Development Commission approved a request by Jingneng Power to begin preparatory work on a 700 MW cogeneration coal plant for the city of Qinhuangdao.[1]

The project was permitted in December 2016.[2] It is started construction in the end of 2017.[3][4]

Satellite photos from Planet show construction progress from July 2017 to April 2018, and from December 2017 to October 2019.

Unit 1 was commissioned in December 2019.[5]

Unit 2 was commissioned in April 2020.[6]

In June 2023, a 2 x 660 MW Phase II expansion was approved at the power station. The units would use ultra-supercritical technology.[7][8]