This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor. |
Sub-articles: |
Krk FSRU (also known as Hrvatska LNG and LNG Croatia) is an operating floating LNG terminal in Croatia. A Phase 2 expansion of the project is proposed.
Location
The map below shows the location of Omišalj, the approximate location of the project, on the island of Krk, in Primorje-Gorski Kotar County.
Project details
- Owner: HEP 85.00%, Plinacro 15.00%[1]
- Parent: HEP 85.00%, Plinacro 15.00%[1]
- Location: Omišalj, Krk Island, Primorje-Gorski Kotar County, Croatia
- Coordinates: 45.066667, 14.6 (approximate)
- Capacity: 2.9 bcm/y, 2.13 mtpa[2]
- Originally 2.6 bcm/y, and increased by 0.3 bcm/y in 2022[2]
- Cost: €233.6 million (US$256.2 million)[3]
- Financing:
- Connecting Europe Facility (CEF) grant (2014) of €4,758,382 (US$5,788,847)[4]
- CEF grant (2015) of €514,994 (US$626,528)[5]
- CEF grant (2016) of €747,000 (US$908,849)[6]
- CEF grant (2016) of €101,400,000 (US$111.2 million)[7]
- Croatian government grant of €100 million (US$109.4 million)[3]
- Equity investment of €32.2 million (US$35.3 million) from HEP and Plinacro
- Status: Operating[8]
- Type: Import
- FID status: FID (January 2019)[9][10]
- Start year: 2021[11]
- Associated infrastructure: Omišalj-Zlobin-Bosiljevo-Sisak-Kozarac-Slobodnica LNG main evacuation pipeline
Note: mtpa = million tonnes per year; bcfd = billion cubic feet per day; bcm/y = billion cubic meters/year
Background
Krk FSRU is a floating liquefied natural gas (FLNG) regasification terminal in Croatia.[12][13] The project was originally planned to be an onshore regasification facility, but was switched to a FLNG proposal in 2015, being declared by the Croatian government as a Strategic Investment Project.[14][15][16][17] The project is a part of the European Union's Projects of Common Interest (PCI), making it eligible for public funding. The project includes construction of an 18 km pipeline, part of the Omišalj-Zlobin-Bosiljevo-Sisak-Kozarac-Slobodnica LNG main evacuation pipeline, which will act as an extension of the existing Hungary-Croatia interconnection (Városföld – Slobodnica), providing 2.6 bcm/y from the LNG terminal to the Croatian gas transmission system.[18] The maximum capacity will eventually be 7 billion cubic meters per year.[19]
The project was originally planned to go into service in 2018.[20] The project would cost about US$418 million in total.[21] As of May 2017, the investment decision had been pushed back to Q1 2018.[22]
In August 2017 it was reported that preliminary work had started on the terminal, with commissioning planned for 2019.[23] Initial annual capacity is planned to be 2 billion cubic meters (1.5 mtpa) and may be increased to 5 billion cubic meters (3.7 mtpa).[24]
In November 2018, LNG Croatia selected Golar Power and its proposal to convert an existing LNG carrier to an FSRU at a cost of 159.6 million euros ($180.8 million).[25] This procurement of a smaller than planned FSRU reduced the overall project costs to €233.6 million (US$256.2 million).[3] At a December 2018 auction two Croatian companies, INA and HEP, expressed interest in buying up to 520 million cubic meters of gas per year, representing just a third of the terminal's annual output.[26]
As of September 2019, the project was still on track to start operations in January of 2021, and begin turning profits in 2025. Once online, the terminal would have an annual capacity of 2.6 billion cubic meters of gas, equivalent to the country’s annual usage. The EU contributed 101 million euros ($111 million) to develop the Krk terminal, with the Croatian government matching the amount and national grid HEP d.d. and state-owned gas pipeline operator Plinacro d.d. adding about 15 million euros each. The project is the first of its kind for Croatia, which has the EU's fifth-longest coastline, and is the result of the U.S. lobbying to reduce the country's need for Russian gas.[27]
According to Gas Infrastructure Europe, construction was underway as of December 2019.[28]
As of March 2020, the terminal has received binding offers from just two buyers that have committed to a total of 520 million cubic metres of gas per year (mcm/y), significantly less than the 1.5 bcm/y needed for the terminal to break even.[29]
In June 2020, Croatia's minister for energy and environment Tomislav Coric announced that the terminal will commence operations on January 1, 2021, with full capacity booked for the next few years. LNG Croatia informed that the terminal capacities have been sold out until October 2023, and that up to October 2027 capacity of 2.1 billion cubic meters of gas annually has already been locked in. Confirmed customers include Powerglobe Qatar LLC, Hungary’s state-owned energy group MVM, the Croatian unit of Swiss-based MET Holding, and two Croatian energy firms.[30]
In June 2020, PowerGlobe Qatar booked all free capacities at Croatia's Krk FSRU until 2023.[31]
In September 2020, Hungary signed a six-year agreement with Shell to receive 250 million cubic metres of LNG per year (mcm/year) via the terminal. This means that by the end of 2027, gas arriving from the Krk FSRU will meet 10% of Hungary's gas needs.[32]
FSRU LNG Croatia, converted from Golar Viking LNG carrier at the Hudong-Zhonghua shipyard in China, arrived in Krk in December 2020 and started commercial operations in January 2021, as scheduled. The FSRU facility, which was purchased from and is operated by Golar LNG Limited, has a technical capacity of 1.9 MTPA. The capacity at the terminal has been booked by HEP, MFGK Croatia, MET Croatia Energy Trade and Power Globe Qatar.[33]
Commercial operations began on January 1, 2021.[8]
In March 2022, Croatia's prime minister Andrej Plenković announced plans to marginally increase the terminal's capacity from its current 2.6 bcm/y to 2.9 bcm/y[34], and said that Croatia would work with the European Commission to secure additional EU money for the capacity increase. Since it started operating in January 2021, the Krk Terminal has received 25 LNG cargoes, with 17 of them coming from the US.[35]
In April 2022, it was announced that the capacity of the terminal had been raised to 2.9 bcm/y with no additional investment required.[2]
Financing
In February 2017, the project was awarded a grant for the construction of the terminal of €101,400,000 (US$111.2 million) under the European Union's Connecting Europe Facility (CEF).[7] This followed three previous grants for studies from the CEF of €4,758,382 (US$5,788,847)[4], €514,994 (US$626,528)[5], and €747,000 (US$908,849)[6]. The CEF has supported the project with grants totalling €107,420,376 (US$118,524,224).
The Croatian government provided a further grant of €100 million (US$109.4 million), and HEP and Plinacro have made an equity investment of €32.2 million (US$35.3 million).[3] The government funding followed approval in August 2019 from the European Commission for state aid for the construction and operation of the terminal. In addition, the terminal company was also granted a 'security of supply fee' which is financed by levies charged by the Croatian gas transmission system operator (TSO) to Croatian gas users to cover any shortfall in revenues from the operation of the terminal.[36]
Phase 1 Expansion Project
- Owner: Golar Power
- Parent: LNG Croatia LLC
- Location: Omišalj, Krk Island, Primorje-Gorski Kotar County, Croatia
- Coordinates: 45.066667, 14.6 (approximate)
- Capacity: 3.2 bcm/y[37][38]
- Status: Proposed
- Type: Import
- Cost: €25 million, with an additional €155 million invested in the associated pipeline[39]
- Formerly €479 million (US$546 million)[40]
- Financing: €25 million from the European Commission[41]
- FID status: FID (2022)[39]
- Start year: 2025[42]
- Formerly 2024-2025[43]
- Associated infrastructure: Omišalj-Zlobin-Bosiljevo-Sisak-Kozarac-Slobodnica LNG main evacuation pipeline
Note: mtpa = million tonnes per year; bcfd = billion cubic feet per day; bcm/y = billion cubic meters/year
Phase 1 Expansion background
According to industry group ENTSOG, in the Ten-Year Network Development Plan (TYNDP) 2020, there is an expansion planned of 4.4 bcm/year (3.2 mtpa).[44] ENTSOG referred to this expansion as Phase 1 in October 2022, despite an earlier April 2022 expansion of 0.3 bcm/y.[45]
The expansion of the terminal was not included in the 5th PCI list published by the European Commission in November 2021.[46]
The April 2022 edition of the LNG database published by Gas Infrastructure Europe continued to list an expansion of undefined capacity at the Krk terminal, with a projected start-up date of 2029.[47] In June 2022, prime minister Andrej Plenković confirmed that the Croatian government was planning a 3.2 bcm/y expansion at the Krk terminal, bringing the terminal's total capacity to 6.1 bcm/y and allowing it to supply natural gas to Slovenia, Bosnia and Hungary.[37][38][48][49]
In August 2022, the government of Croatia announced that it had decided to proceed with the expansion project.[39]
In September 2022, Hrvoje Krhen, Managing Director of LNG Croatia, said that the revised expansion plan was to have the additional capacity ready and available for "the gas season 2024-2025".[43]
In June 2023, Wärtsilä was contracted to expand the project's capacity.[50]
In September 2023, LNG Croatia said that it had started the necessary actions to begin the expansion. Over the coming weeks, it plans to complete project engineering of the new regasification module and to begin production of the module.[51]
As of February 2024, the main part of the gasification module design process, as well as its installation and implementation of the existing gasification system on the FSRU terminal, had been completed, as reported by CE Energy News.[52]
In May 2024, the European Commission approved €25 million in financing for the expansion project.[41]
Phase 2 Expansion Project
- Owner:
- Parent: LNG Croatia LLC
- Location: Omišalj, Krk Island, Primorje-Gorski Kotar County, Croatia
- Coordinates: 45.066667, 14.6 (approximate)
- Capacity: 4.1 bcm/y[53]
- Formerly 7 bcm/y[45]
- Status: Proposed[45]
- Type: Import
- Cost:
- FID status: Pre-FID[45]
- Start year: 2030[45]
- Associated infrastructure:
Note: mtpa = million tonnes per year; bcfd = billion cubic feet per day; bcm/y = billion cubic meters/year
Phase 2 Expansion Background
According to ENTSOG's Ten-Year Network Development Plan (TYNDP) as of October 2022, the promoters are considering developing an onshore LNG terminal near the FSRU with capacity of 7 bcm/y.[45]
The project was included in ENTSOG's TYNDP as of June 2024, now with a capacity of 4.1 bcm/y.[53]
Opposition
Due to environmental and economic concerns, the terminal remains largely unpopular among local residents. According to Food and Water Europe, "...the project is now strongly opposed by all local municipalities from Krk Island, the Primorje-Gorski Kotar County and by local environmental NGOs."[54] In March 2018, thousands of protestors gathered in Rijeka, Croatia to oppose the terminal.[55]
Local opposition groups cite concern over how the terminal will impact the bay and its marine life. The terminal plans to use sea water from the bay in the process of converting product from a liquid to a gas, which will cool the water, leading to environmental consequences for the small bay. The terminal operators also plan to use chlorine to protect the pipes against algae and shells, which will cause further environmental damage. Local groups opposing the terminal include Zelena Akcija and Eko Kvarner. Environmentalists and Krk local municipalities organised a protest against the terminal in March of 2018. Meanwhile, the government passed a new law which would speed up construction of the terminal.[56]
International opposition has warned that the terminal would likely be importing fracked gas from America, making it a particularly detrimental project for the climate.[54]
Articles and resources
References
- ↑ 1.0 1.1 2020 World LNG Report, page 102, International Gas Union, April 27, 2020
- ↑ 2.0 2.1 2.2 Željko Trkanjec, Request for allocation of new capacity of LNG terminal on Krk, EURACTIV, Apr. 12, 2022
- ↑ 3.0 3.1 3.2 3.3 John Snyder, Floating LNG ratchets up in the Mediterranean, Riviera Maritime Media, Apr. 15, 2020
- ↑ 4.0 4.1 Studies for LNG terminal Krk: legal & financial advisory, FEED, main design, tender documentation for EPC, power supply system documentation, European Commission, accessed Jan. 13, 2021
- ↑ 5.0 5.1 Field and laboratory investigation studies and preparation of reports, European Commission, accessed Jan. 13, 2021
- ↑ 6.0 6.1 Studies for the LNG terminal Krk FSRU solution, European Commission, accessed Jan. 13, 2021
- ↑ 7.0 7.1 Construction of LNG terminal Krk, European Commission, accessed Jan. 13, 2021
- ↑ 8.0 8.1 Dragana Petrushevska, Croatia's Krk LNG terminal starts commercial operations See News, January 4, 2021
- ↑ TYNDP - Annex A - Projects Tables ENTSOG, accessed February 4, 2021
- ↑ "Krk LNG project update 2019" (PDF). European Commission. Retrieved 2022-04-14.
{{cite web}}
: CS1 maint: url-status (link) - ↑ The LNG Industry: Annual Report 2020, page 38, International Group of Liquefied Natural Gas Importers, accessed April 29, 2020
- ↑ Hrvatska LNG Terminal, A Barrel Full, accessed April 2017
- ↑ About us, LNG Croatia website, accessed July 2017.
- ↑ LNG Regasification Terminal in Krk, Croatia, LNG Croatia document, July 2015.
- ↑ Croatia considers FSRU for Krk LNG imports, LNG World Shipping, 3 Mar. 2016.
- ↑ "Debunking myths: Croatia's Krk Gas Terminal" (PDF). Stop Climate Chaos. Retrieved 2022-04-14.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Croatia Gives Krk Gas Terminal 'Strategic' Status". Balkan Insight. 2015-07-17. Retrieved 2022-04-14.
- ↑ Development of LNG terminal in Krk(HR)(Phase I)and connecting pipeline Omišalj–Zlobin(HR), European Commission, accessed December 2, 2019
- ↑ Austria, Food and Water Watch Europe, accessed December 3, 2019
- ↑ Croatia floating LNG terminal taking a year longer to finish, Reuters, 25 Jan. 2017.
- ↑ EU approves EUR 102m grant for LNG terminal in Croatia, Croatian Government press release, 17 Feb. 2017.
- ↑ Decision on LNG Terminal on Krk Delayed for Next Year, Total Croatia News, 3 May 2017.
- ↑ Zoran Radosavljevic, "Croatia starts preliminary work on Adriatic LNG terminal," EURACTIV.com, Aug 18, 2017
- ↑ "About Us," LNG Croatia LLC, accessed August 2017
- ↑ Croatia picks Golar Power to supply future LNG terminal, Reuters, Nov. 9, 2018
- ↑ Je li plutajući LNG terminal osuđen na to da postane gubitaš i prije nego što je izgrađen, tportal, Dec. 24, 2018
- ↑ Jasmina Kuzmanovic Floating Adriatic Port Closer to Easing Russia Gas Dominance, Bloomberg, September 10, 2019
- ↑ LNG Database Gas Infrastructure Europe, accessed December 6, 2019
- ↑ Jelena Prtorić, Is the EU locking into natural gas despite its promise to lead the global phase-out of fossil fuels? Equal Times, March 9, 2020
- ↑ Igor Ilic, "Croatia's new LNG terminal to start operations in January fully booked," Reuters, Jun. 16, 2020
- ↑ Iskra Pavlova, PowerGlobe Qatar books all free capacities at Croatia's Krk LNG terminal for next 3 years SeeNews, Jun. 15, 2020
- ↑ Iskra Pavlova, Shell to supply gas to Hungary via Croatia's Krk LNG terminal SeeNews, Sep. 7, 2020
- ↑ GIIGNL 2021 Annual Report, accessed May 5, 2021
- ↑ Trkanjec, Zeljko (2022-03-28). "Croatia to consider increase in capacity of Krk LNG terminal". Euractiv.
{{cite web}}
: CS1 maint: url-status (link) - ↑ Croatia plans to boost Krk LNG terminal capacity, LNG Prime, Mar. 28, 2022
- ↑ EU Greenlights State Aid for Croatia’s Krk LNG Terminal, Offshore Energy, Aug. 13, 2019
- ↑ 37.0 37.1 "PM Plenkovic: Croatia plans to double the capacity of its LNG terminal". N1. June 20, 2022.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 38.0 38.1 Elliott, Stuart (June 21, 2022). "Croatia to expand capacity of floating LNG import terminal to 6.1 Bcm/year: PM". S&P Global.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 39.0 39.1 39.2 LNG Prime Staff (2022-08-18). "Croatia decides to boost Krk LNG capacity". LNG Prime. Retrieved 2022-12-13.
- ↑ Ten Year Network Development Plan 2020 - Annex A - Projects Tables, ENTSOG, accessed Dec. 7, 2021
- ↑ 41.0 41.1 Simmonds, Lauren (2024-05-09). "EC Approves Big Sum For LNG Terminal Expansion". Total Croatia. Retrieved 2024-07-26.
- ↑ GIIGNL. The LNG Industry: Annual GIIGNL Report. June 2024.
- ↑ 43.0 43.1 Claudia Patricolo, Expansion of the Krk LNG terminal can be completed for the gas year 2024-2025, CEEnergy News, Sep. 6, 2022
- ↑ ENTSOG TYNDP 2020 - Annex A - Projects Tables, 12 Nov 2019
- ↑ 45.0 45.1 45.2 45.3 45.4 45.5 UPDATED TYNDP 2022 List of Projects. ENTSOG. October 21, 2022.
- ↑ ANNEX to COMMISSION DELEGATED REGULATION (EU) …/... amending Regulation (EU) No 347/2013 of the European Parliament and of the Council as regards the Union list of projects of common interest, European Commission, Nov. 19, 2021
- ↑ "LNG Database". Gas Infrastructure Europe. Retrieved June 23, 2022.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Croatia could more than double Krk LNG terminal's capacity – PM". SeeNews. June 2, 2022.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Plenković: Investment Decision on Expansion of LNG Terminal Very Close". Total Croatia News. May 30, 2022.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Wärtsilä to extend regasification capacity for Croatian LNG terminal". LNG Industry. 2023-06-16. Retrieved 2023-09-14.
- ↑ "LNG Croatia begins operations to increase capacity of Krk LNG terminal - CEENERGYNEWS". ceenergynews.com. 2023-10-11. Retrieved 2024-07-26.
- ↑ "Krk LNG terminal's capacity expansion marks progress - CEENERGYNEWS". ceenergynews.com. 2024-02-28. Retrieved 2024-07-26.
- ↑ 53.0 53.1 ENTSOG. ENTSOG TEN-YEAR NETWORK DEVELOPMENT PLAN 2024: TYNDP 2024 Annex A1 - Project Tables. June 18, 2024.
- ↑ 54.0 54.1 Croatia, Food and Water Europe, accessed December 3, 2019
- ↑ Thousands Protest against Floating LNG Terminal, Total Croatia News, March 3, 2018
- ↑ Igor Ilic, Croatia's Krk LNG project faces opposition as investment decision looms, Reuters, February 19, 2018