Moheshkhali-Anwara Parallel Gas Pipeline is an operating gas pipeline in Bangladesh.[1][2]
Location
The pipeline runs from Moheshkhali to Anwara, Bangladesh.[1]
Project details
- Operator: GTCL[3]
- Owner: GTCL[3]
- Parent company: Petrobangla[1]
- Capacity: 1200 million cubic feet per day[4]
- Length: 79 km[2][5]
- Diameter: 42[2]
- Status: Operating[2]
- Start year: 2021[2]
- Cost: Tk. 1314.72 crore (approximately $15.4 Million)[1]
- Financing: GTCL own fund[1]
- Associated infrastructure: Moheshkhali FLNG Terminal (Petrobangla)
Background
The pipeline is operated by GTCL, a subsidiary of Petrobangla. The project started in July 2016 and was completed in June 2021.[2] The pipeline runs parallel to the 91-km long Moheshkhali-Anwara Gas Transmission Pipeline.[3]
Articles and resources
References
- ↑ 1.0 1.1 1.2 1.3 1.4 Construction of Moheshkhali-Anwara Parallel Pipeline, GTCL, accessed January 28, 2021.
- ↑ 2.0 2.1 2.2 2.3 2.4 2.5 "Existing Pipeline". GTCL. Retrieved 2021-08-23.
- ↑ 3.0 3.1 3.2 Annual Report 2019 (PDF). PETROBANGLA. 2020. p. 24.
- ↑ "Annual Report 2021" (PDF). Petrobangla.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Annual Report 2020" (PDF). Petrobangla.
{{cite web}}
: CS1 maint: url-status (link)