Nabinagar Thermal Power Project

From Global Energy Monitor
(Redirected from Nabinagar I power station)
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Nabinagar Thermal Power Project is an operating power station of at least 1000-megawatts (MW) in Dhundwa, Nabinagar, Aurangabad, Bihar, India. It is also known as Nabi Nagar TPP.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Nabinagar Thermal Power Project Dhundwa, Nabinagar, Aurangabad, Bihar, India 24.705081, 84.088738 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2, Unit 3, Unit 4: 24.705081, 84.088738

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year
Unit 1 operating coal: unknown 250 subcritical 2016
Unit 2 operating coal: unknown 250 subcritical 2017
Unit 3 operating coal: unknown 250 subcritical 2019
Unit 4 operating coal: unknown 250 subcritical 2021

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1 Bhartiya Rail Bijlee Co Ltd [100%] NTPC Ltd [74.0%]; Indian Railways [26.0%]
Unit 2 Bhartiya Rail Bijlee Co Ltd [100%] NTPC Ltd [74.0%]; Indian Railways [26.0%]
Unit 3 Bhartiya Rail Bijlee Co Ltd [100%] NTPC Ltd [74.0%]; Indian Railways [26.0%]
Unit 4 Bhartiya Rail Bijlee Co Ltd [100%] NTPC Ltd [74.0%]; Indian Railways [26.0%]

Project-level coal details

  • Coal source(s): Pachra and South Pachra blocks of North Karanpura Coalfields

Background

The proposed plant was originally planned to comprise four 250MW generating units.[1] The project is located near the village of Dhundwa near Nabinagar. The power station would primarily be used to supply power to the Eastern and Western districts of Railways operations in the states of Bihar, Jharkhand, West Bengal, Chhatisgarh, Maharashtra, Gujarat and Madhya Pradesh.[2][3]

In 2011, the power station was described as at an advanced stage of construction[4] by Bharatiya Rail Bijlee Company, a joint venture company formed by the Ministry of Railways and the National Thermal Power Corporation.[5][3]

A 2014 NTPC investor presentation said units 1-3 of the project would be completed FY2015-2017. The third unit is listed as 500 MW.[6]

In July 2015, Times of India reported the plants is 4x250 MW, and unit 1 was planned to come online in November 2015,[7] but was later pushed to 2016. The power station is expected to be completed by 2017.[8]

Unit 1 was commissioned in March 2016.[9] Unit 2 was commissioned in April 2017.[10]

Units 3-4 were planned for 2018.[11]

Unit 3 was commissioned in March 2019.[12]

The Central Electricity Authority reported that Unit 4 was commissioned in November 2021,[13] and the company announced it was commissioned December 1, 2021.[14]

Financing

The National Thermal Power Corporation agreed to provide US$161,298,897 in equity, while Indian Railways agreed to provide US$56,676,561 in equity.[15]

Ownership

The joint venture project will be developed by Bhartiya Rail Bijli Company, with NTPC having 74% equity in the project and the Ministry of Railways the remaining 26%.[16]

The joint venture company was first proposed with the signing of a Memorandum of Understanding back in February 2002. However, it was not until in February 2007 that the company was finally approved by the national government's the Cabinet Committee on Economic Affairs.[17]

Equipment burnt

In November 2010, it was reported that, according to the Superintendent of Police, four dumpers, three cranes and other machinery at the project site had been burnt. It was also reported that several workers on the site were held captive and assaulted by the armed attackers. The media report attributed the attack on the plant works to "Maoists" and "naxalites."[18]

Articles and Resources

References

  1. "Railways to set up 1000 MW power plant in Nabinagar", Economic Times of India, July 31, 2009.
  2. "Railways to set up 1000 MW power plant in Nabinagar", Economic Times, July 31, 2009.
  3. 3.0 3.1 "Projects Info | 18-24 August, 2008", Construction Update.com, accessed December 2011.
  4. Mamata Banerjee, Minister for Railways, "Speech of Mamata Banerjee introducing the Railway Budget 2011-12", February 25th, 2011.
  5. National Thermal Power Corporation, "Future Capacity Additions", National Thermal Power Corporation website, accessed May 2011.
  6. "NTPC Investor Presentation," NTPC, 2014
  7. "Nabinagar unit likely to generate power by Nov," Times of India, July 15, 2015
  8. "Monthly Report on Broad Status of Thermal Power Projects in the Country," India CEA, November 2015
  9. "First unit of NTPC-Rail JV synchronised at Bihar's Nabinagar," Business Standard, March 20, 2016
  10. "Broad Status Report," India Central Electrical Authority, April 2017
  11. “Broad Status of Thermal Power Projects in the Country,” India Ministry of Power, September 2017
  12. "Executive Summary," India CEA, March 2019
  13. "Installed Capacity," India CEA, November 2021
  14. "NTPC declares unit-4 of Nabinagar Thermal Power Project commercially operation," Business Standard, December 1, 2021
  15. "Nabinagar Thermal Power". www.infraline.com. Retrieved 2020-10-22.
  16. "Railway Budget 09-10: Railways to set up 1,000 MW power plant with NTPC", Economic Times of India, July 3, 2009.
  17. "NTPC, Railways form JV to set up power plant in Bihar", The Economic Times, November 6, 2007.
  18. "Maoists burn equipment of NTPC plant", Economic Times, November 25, 2010.

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.