Stepnogorsk power station (Степногорская ТЭЦ) is an operating power station of at least 185-megawatts (MW) in Stepnogorsk, Akmola, Kazakhstan.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Stepnogorsk power station Stepnogorsk, Stepnogorsk, Akmola, Kazakhstan 52.483962, 72.03196 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2, Unit 3, Unit 4, Unit 5: 52.483962, 72.03196

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year
Unit 1 operating coal: bituminous 35[1] subcritical yes 1969
Unit 2 operating coal: bituminous 30 subcritical yes 1989
Unit 3 operating coal: bituminous 30 subcritical yes 1989
Unit 4 operating coal: bituminous 30 subcritical yes 1989
Unit 5 operating coal: bituminous 60 subcritical yes 1989

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1 Stepnogorskya TETS LLP [100%][2] Stepnogorskya TETS LLP [100.0%]
Unit 2 Stepnogorskya TETS LLP [100%][2] Stepnogorskya TETS LLP [100.0%]
Unit 3 Stepnogorskya TETS LLP [100%][2] Stepnogorskya TETS LLP [100.0%]
Unit 4 Stepnogorskya TETS LLP [100%][2] Stepnogorskya TETS LLP [100.0%]
Unit 5 Stepnogorskya TETS LLP [100%][2] Stepnogorskya TETS LLP [100.0%]

Project-level coal details

  • Coal source(s): Ekibastuz basin

Background

The Stepnogorsk power station is owned by a private individual Baurzhan Dairbaev, who also owns a company Atyrau Power LLP.[3][4]

The power station's capacity is 180 MW with 5 operating units. Exact unit numbers and individual unit capacities are not certain.[5][6] Construction of the plant started in 1966 and continued until 1989.[6][7] The plant uses bituminous coal from the Ekibastuz basin.[8]

In March 2022, two of the six power boilers developed leaks and the residents of Stepnogorsk were left without heating. The wear and tear of the station exceeded 80%.[3][9]

An industry report dated November 2023 referred to the planned retirement of Unit 1 (35MW) by 2030, in line with the government order.[10] However, the government order from February 2024 on the 'Program for power sector development until 2035' referred to the planned replacement of a depreciated unit with 39MW of capacity (presumably Unit 1) by 2026.[11]

Articles and Resources

References

  1. (PDF) https://web.archive.org/web/20240326002329/https://unece.org/sites/default/files/2024-02/Final%2520Report_Katyshev_15092023%2520RUS.pdf. Archived from the original (PDF) on 26 March 2024. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 2.2 2.3 2.4 https://web.archive.org/web/20240125152021/https://st-tec.kz/. Archived from the original on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 "«Генералы» турбин и котлов Степногорской ТЭЦ". golos-naroda.kz. April 2022.{{cite web}}: CS1 maint: url-status (link)
  4. "Тайный предприниматель: что стоит за загадочной личностью учредителя Степногорской ТЭЦ". orda.kz. February 2023.{{cite web}}: CS1 maint: url-status (link)
  5. "ПРОГРАММА УПРАВЛЕНИЯ ОТХОДАМИ для ТОО «Степногорская ТЭЦ» на период 2022-2026 гг. (page 8)". ecoportal.kz. 2022. {{cite web}}: line feed character in |title= at position 21 (help)CS1 maint: url-status (link)
  6. 6.0 6.1 "ТОО "Степногорская ТЭЦ"". st-tec.kz. Retrieved June 2023. {{cite web}}: Check date values in: |access-date= (help)CS1 maint: url-status (link)
  7. "Глава государства посетил ТЭЦ города Степногорска". www.inform.kz. February 2023.{{cite web}}: CS1 maint: url-status (link)
  8. "Нарушения в деятельности Степногорской ТЭЦ выявили специалисты департамента экологии". 716.kz. February 2021.{{cite web}}: CS1 maint: url-status (link)
  9. "Как будут решать проблемы отопления в Степногорске". www.inform.kz. April 2023.{{cite web}}: CS1 maint: url-status (link)
  10. "https://unece.org/sites/default/files/2024-02/Final%20Report_Katyshev_15092023%20RUS.pdf" (PDF). unece.org/. 2023. {{cite web}}: External link in |title= (help)CS1 maint: url-status (link)
  11. "Приказ "Об утверждении Плана мероприятий по развитию электроэнергетической отрасли до 2035 года"" (PDF). /www.gov.kz. February 2024.{{cite web}}: CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.