Aral Xinhu Cogen power station
From Global Energy Monitor
(Redirected from Xinjiang Bingtuan Nongyishi Alaerxinhu Thermal Power Plant Phase II)
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Aral Xinhu Cogen power station (新疆阿拉尔市新沪热电) is an operating power station of at least 800-megawatts (MW) in Aral, Xinjiang, China. It is also known as 阿拉尔盛源热电厂 (Phase II Unit 3, Phase II Unit 4).
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Aral Xinhu Cogen power station | Aral, Xinjiang, China | 40.5894333, 81.1954343 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Phase I Unit 1, Phase I Unit 2, Phase II Unit 3, Phase II Unit 4: 40.5894333, 81.1954343
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Phase I Unit 1 | operating | coal: unknown | 50 | unknown | 2008 |
Phase I Unit 2 | operating | coal: unknown | 50 | unknown | 2008 |
Phase II Unit 3 | operating | coal: unknown | 350 | supercritical | 2014 |
Phase II Unit 4 | operating | coal: unknown | 350 | supercritical | 2014 |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Phase I Unit 1 | Xinjiang Alal Xinhu Thermal Power Co Ltd [100%] | Alar Tongzhong State-owned Capital Investment Operation (Group) Co Ltd [48.2%]; Xinjiang Production and Construction Corps Electric Power Group Co Ltd [33.3%]; Alar Xinxin State Owned Capital Investment and Operation (Group) Co Ltd [18.5%] |
Phase I Unit 2 | Xinjiang Alal Xinhu Thermal Power Co Ltd [100%] | Alar Tongzhong State-owned Capital Investment Operation (Group) Co Ltd [48.2%]; Xinjiang Production and Construction Corps Electric Power Group Co Ltd [33.3%]; Alar Xinxin State Owned Capital Investment and Operation (Group) Co Ltd [18.5%] |
Phase II Unit 3 | Xinjiang Alal Xinhu Thermal Power Co Ltd [100%] | Alar Tongzhong State-owned Capital Investment Operation (Group) Co Ltd [48.2%]; Xinjiang Production and Construction Corps Electric Power Group Co Ltd [33.3%]; Alar Xinxin State Owned Capital Investment and Operation (Group) Co Ltd [18.5%] |
Phase II Unit 4 | Xinjiang Alal Xinhu Thermal Power Co Ltd [100%] | Alar Tongzhong State-owned Capital Investment Operation (Group) Co Ltd [48.2%]; Xinjiang Production and Construction Corps Electric Power Group Co Ltd [33.3%]; Alar Xinxin State Owned Capital Investment and Operation (Group) Co Ltd [18.5%] |
Background on Project
The first two units of the power station of 50 MW each was built in 2008 in in Xinjiang Uyghur Autonomous Region. In 2012 it was reported that there were plans for two more units of 350 MW each.[1][2][3]
Units 3-4 began operating in 2014.[4]
Articles and Resources
References
- ↑ "关于新疆生产建设兵团农一师阿拉尔新沪热电厂二期2×350MW超临界空冷供热机组扩建工程环境影响报告书的批复", 中华人民共和国环境保护部, 2012-07-02
- ↑ "新疆生产建设兵团阿拉尔新沪热电扩建工程通过核准," NDRC website, 2012-11-12
- ↑ "农一师电力公司2×350兆瓦电厂项目前期打桩工作开始", 兵团新闻网, 2011-4-11
- ↑ "阿拉尔盛源热电公司1号机组并网试运行发电," ChinaNews.com, 9/9/14