ACWA Power Sirdarya I power station (Сырдарьинская ТЭС,ТЭС «ACWA Power Сырдарья» (Russian)) is an operating power station of at least 1500-megawatts (MW) in Shirin, Bayaut, Sirdaryo, Uzbekistan. It is also known as ACWA Power Sirdarya, Sirdarya CCGT power plant.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
ACWA Power Sirdarya I power station Shirin, Bayaut, Sirdaryo, Uzbekistan 40.237699, 69.111537 (exact)[1]

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • CC1: 40.237699, 69.111537

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year
CC1 Operating[2][3][4][5][6][7][8][9][10] fossil gas: natural gas[11] 1500[12][13][14][15] combined cycle[16][13][14] not found 2024[17][14][4][8][9][18][19][10][20][21]

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
CC1 ACWA Power Sirdarya LLC [51%]; Silk Road Fund [49%][22][22] Silk Road Fund [49.0%]; ACWA Power Co [26.0%]; The Silk Road Fund Co Ltd

Background

A ground-breaking ceremony was held in January 2021[23], and early site preparation has started in April 2021.[24] This project is different from the Syrdarya II power station. The project, which is estimated to cost US$1.02 billion,[25] is financed by the Asian Infrastructure Investment Bank (AIIB), European Bank for Reconstruction and Development, OPEC Fund for International Development, and DEG (Deutsche Investitions- Und Entwicklungsgesellschaft Mbh); with some commercial lenders backed by Multilateral Investment Guarantee Agency guarantees.[26]

As of July 2022, construction was 44% complete.[27] The plant is planned to be launched by the end of 2023.[27]

In October 2023, the first generation unit of the new power station began operation. The capacity of the launched unit is approximately 120 MW, which represents 8% of the project capacity for the power station. By the end of the year, the plan is to reach 1000 MW, and by the end of March 2024, the station will operate at full capacity.[28]

In March 2024, it was reported that 1000 MW of the plant's capacity (two gas turbines) had been commissioned.[29] In May 2024, President of Uzbekistan Shavkat Mirziyoyev and Minister of Energy of Saudi Arabia Abdulaziz bin Salman Al Sauda attended an inauguration ceremony of the plant.[30]

In November 2024, Ipoteka Bank of Uzbekistan signed a strategic partnership agreement with ACWA Power for the construction of the plant. As part of this partnership, Ipoteka Bank provided ACWA Power Sirdarya with a working capital facility (WCF) of USD 40 million for a term of 36 months, with an option for automatic renewal for an additional 12 months. The loan is secured by collateral both within Uzbekistan and internationally, positioning Ipoteka Bank as a key player among senior creditors.[31]

As of December 2024, the project is still listed as "under construction" on the website of ACWA Power.[32]

Articles and Resources

References

  1. https://web.archive.org/web/20210624191341/https://drive.google.com/file/d/1tAGiNo0K5aiKCQbSemtgrVb1VPhQ9iYN/view?usp=sharing. Archived from the original on 2021-06-24. {{cite web}}: Missing or empty |title= (help)
  2. https://web.archive.org/web/20210629220908/https://www.seetao.com/details/60900.html. Archived from the original on 2021-06-29. {{cite web}}: Missing or empty |title= (help)
  3. https://web.archive.org/web/20211101224525/https://kun.uz/en/news/2020/11/04/syrdarya-starts-construction-of-new-thermal-power-plant. Archived from the original on 2021-11-01. {{cite web}}: Missing or empty |title= (help)
  4. 4.0 4.1 https://web.archive.org/web/20220913223120/https://yuz.uz/ru/news/v-srdarinskoy-oblasti-vozvoditsya-novaya-elektrostantsii-v-1500-mvt. Archived from the original on 2022-09-13. {{cite web}}: Missing or empty |title= (help)
  5. https://yuz.uz/ru/news/-v-srdare-k-2026-godu-zapustyat-dve-nove-teplove-elektrostantsii. {{cite web}}: Missing or empty |title= (help)
  6. https://web.archive.org/web/20230412003944/https://disclosures.ifc.org/project-detail/ESRS/45205/syrdarya-ccgt. Archived from the original on 2023-04-12. {{cite web}}: Missing or empty |title= (help)
  7. https://web.archive.org/web/20230420102802/https://www.uzdaily.uz/ru/post/76808. Archived from the original on 2023-04-20. {{cite web}}: Missing or empty |title= (help)
  8. 8.0 8.1 https://dunyo.news/ru/news/spot-tes-v-shirine-syrdarinskoy-oblasti-nachala-davat-energiyu-6540c306ced96. {{cite web}}: Missing or empty |title= (help)
  9. 9.0 9.1 https://www.acwapower.com/news/acwa-power-signs-485-billion-deal-for-central-asias-largest-wind-farm/. {{cite web}}: Missing or empty |title= (help)
  10. 10.0 10.1 "ACWA Power is implementing the first project for the production of green hydrogen in Uzbekistan". Energy Central. 2024-03-10. Archived from the original on 2024-04-15. Retrieved 2024-04-01.
  11. https://web.archive.org/web/20221101072635/http://www.nsenergybusiness.com/projects/syrdarya-combined-cycle-power-project/. Archived from the original on 2022-11-01. {{cite web}}: Missing or empty |title= (help)
  12. "ACWA Power Sirdarya, ПГУ мощностью 1500 МВт (НЭП), Республика Узбекистан" (PDF). www.miga.org. 2020-10-01. Archived from the original (PDF) on 2024-04-09. Retrieved 2024-04-01.
  13. 13.0 13.1 https://www.utilities-me.com/utilities/acwa-power-launches-operations-at-1-2-billion-sirdarya-ccgt-power-plant-in-uzbekistan. {{cite web}}: Missing or empty |title= (help)
  14. 14.0 14.1 14.2 https://www.saurenergy.me/acwa-powers-1-5-gw-sirdarya-power-plant-now-fully-operational/. {{cite web}}: Missing or empty |title= (help)
  15. "Mitsubishi Power". Mitsubishi Power. Archived from the original on 2024-04-15. Retrieved 2024-04-01. {{cite web}}: Text "Uzbekistan's Natural Gas Power Generation Reborn with State-of-the-Art Facilities" ignored (help)
  16. https://web.archive.org/web/20221211123331/https://minenergy.uz/en/lists/view/22. Archived from the original on 2022-12-11. {{cite web}}: Missing or empty |title= (help)
  17. https://web.archive.org/web/20221003063717/http://minenergy.uz/en/lists/view/77. Archived from the original on 2022-10-03. {{cite web}}: Missing or empty |title= (help)
  18. https://web.archive.org/web/20221203022715/https://www.gazeta.uz/ru/2021/11/09/power-plant/. Archived from the original on 2022-12-03. {{cite web}}: Missing or empty |title= (help)
  19. https://web.archive.org/web/20230202082501/https://thermalpowercentralasia.com/investment-projects/. Archived from the original on 2023-02-02. {{cite web}}: Missing or empty |title= (help)
  20. https://web.archive.org/web/20221013163953/https://minenergy.uz/ru/news/view/1507. Archived from the original on 2022-10-13. {{cite web}}: Missing or empty |title= (help)
  21. https://web.archive.org/web/20230315194207/https://kun.uz/en/news/2023/02/16/uzbekistan-to-put-into-operation-3-tpps-with-a-total-capacity-of-4633-mw-by-2026. Archived from the original on 2023-03-15. {{cite web}}: Missing or empty |title= (help)
  22. 22.0 22.1 https://web.archive.org/web/20221228114142/http://www.acwapower.com/en/projects/sirdarya-ccgt/. Archived from the original on 2022-12-28. {{cite web}}: Missing or empty |title= (help)
  23. "Uzbekistan gas combined cycle power plant project started--Seetao". www.facebook.com. Archived from the original on June 29, 2021. Retrieved January 29, 2022.
  24. uz, Kun. "Syrdarya starts construction of new thermal power plant". Archived from the original on November 1, 2021. Retrieved January 20, 2022.
  25. "ACWA Power partners with Ipoteka Bank to develop $1.02bn CCGT plant in Uzbekistan". Daryo. Nov 14, 2024.
  26. "AIIB Supports Private Sector Investment in Efficient Energy Generation in Uzbekistan". AIIB.org. Nov 8, 2021. Retrieved Jun 1, 2022.
  27. 27.0 27.1 https://web.archive.org/web/20220913223120/https://yuz.uz/ru/news/v-srdarinskoy-oblasti-vozvoditsya-novaya-elektrostantsii-v-1500-mvt. {{cite web}}: |archive-url= requires |archive-date= (help); Missing or empty |title= (help)
  28. "ТЭС в Ширине Сырдарьинской области начала давать энергию". dunyo.news. October 31, 2023. Retrieved November 3, 2023.{{cite web}}: CS1 maint: url-status (link)
  29. "ACWA Power is implementing the first project for the production of green hydrogen in Uzbekistan". energycentral.com. March 11, 2024. Retrieved April 1, 2024.{{cite web}}: CS1 maint: url-status (link)
  30. "ACWA Power signs $4.85 billion deal for Central Asia's largest wind farm". ACWA Power. May 3, 2024. Retrieved November 18, 2024.{{cite web}}: CS1 maint: url-status (link)
  31. "Ipoteka bank заключил стратегическое партнерство с ACWA Power для реализации крупного энергетического проекта в Узбекистане". daryo.uz. November 13, 2024. Retrieved November 19, 2024.{{cite web}}: CS1 maint: url-status (link)
  32. "Assets". ACWA Power. November 18, 2024. Retrieved November 18, 2024.{{cite web}}: CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of gas-fired power stations, a downloadable dataset, and summary data, please visit the Global Oil and Gas Plant Tracker on the Global Energy Monitor website.