Adani Godda power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Adani Godda power station is an operating power station of at least 1600-megawatts (MW) in Motia, Godda, Jharkhand, India. It is also known as Paraspani power station.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Adani Godda power station Motia, Godda, Godda, Jharkhand, India 24.814107, 87.135465 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2: 24.814107, 87.135465

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year
Unit 1 operating coal: unknown 800 ultra-supercritical 2023
Unit 2 operating coal: unknown 800 ultra-supercritical 2023

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1 Adani Power Ltd [100%] Adani Power Ltd [100.0%]
Unit 2 Adani Power Ltd [100%] Adani Power Ltd [100.0%]

Project-level coal details

  • Coal source(s): imported

Background

In February 2016 Adani Power applied for a terms of reference to build a 2 x 800 MW coal-fired power station in Godda district.[1]

On August 11, 2016, Adani Power signed an MoU with Bangladesh Power Development Board to set up a 2x800 MW thermal power plant on build-own-operate (BOO) basis in India. Adani will export the entire power generated from the power project to Bangladesh.[2]

The terms of reference was granted in July 2016. An EIA was submitted in April 2017. The plant would be ultra-supercritical.[2]

Environmental clearance was granted on August 31, 2017.[3]

According to locals in December 2018, Adani has begun uprooting trees and burial sites for the plant, and have been protected by the police. Locals have protested and Adani has retreated for now. Many locals said they have refused to accept monetary compensation for the land, on the grounds that they never agreed to give their land to the Adani Group.[4]

According to IEEFA, the tariffs quoted by the Bangladesh Power Development Board for power from the plant are not competitive, because Adani would run the facility with imported coal from Adani’s Australian Carmichael Coal Project, via the port of Dhamra, Odisha (owned by Adani Ports) some 700 kilometres away from the power plant by rail. They suggest the real reason for the plant is to prop up the prospects of Adani's proposed Carmichael megamine in Queensland through a favorable PPA for Adani.[5] In what is being seen increasingly as a three government (Australia, Bangladesh and India) subsidy operation to secure profits for Adani's Carmichael mine and Godda coal plant operations, IEEFA estimates that Bangladesh will pay the equivalent of about 6 rupees (8 U.S. cents) per kilowatt hour for Godda's output, while the price of buying power from India on the open market would be around 3 rupees.[6]

According to Scroll.in, on February 25, 2019, the Modi government cleared the way for the plant to become the first standalone power project in India to get the status and benefits of a Special Economic Zone, giving the project access to a host of duty-waivers, tax exemptions, and faster clearances. In addition, the amended guidelines mandate that all electricity generated in the SEZ be exported, meaning Jharkhand could lose its share of local electricity from the project. To enable SEZ status for the Adani project, the government had to amend 2016 guidelines that prohibited the establishment of a standalone power project inside an SEZ.[7]

In September 2019 it was reported that work on the project had begun, carried out by Chinese company SEPCO3. The coal plant was planned to be operational starting in 2022. According to NewsClick, "thousands have lost their lands [for the coal plant] despite rallying against the administration consistently year after year". The displaced "includes forceful acquisition of 50 acres of 40 families against their wishes."[8]

Opposition continues against the project. Minister and senior Congress leader Alamgir Alam said his party would insist that the government take a relook at the project: “Land was acquired without holding a meeting of the gram sabha. According to the Land Acquisition, Rehabilitation and Resettlement Act, 2013, farmers must be given four times the actual market price of land. But the BJP government deliberately ignored the provisions."[9]

In June 2021, the project was delayed and reportedly scheduled to be ready by the end of 2022.[10]

However, in October 2021, an Adani Power official said: “The COVID-19 has impacted and delayed the schedule of implementation and commissioning of 1,600-MW ultra-supercritical coal-based thermal power project in the state of Jharkhand. Company officials are working day and night to complete this.” The plant was likely to be inaugurated by March 2022 (Q1).[11]

In July 2022, it was reported that Adani's deadline had shifted to December 2022. However, the work required to complete all the interlocking elements of the colossal power plant was likely to take a year and a half. One insider also believed it would take "at least another five years for the plant to produce the full 1600 MW."[12]

In December 2022, a leaked copy of the power purchase agreement signed by Bangladesh revealed that the country would have to pay Adani about US$450 million per year in capacity and maintenance charges even if it doesn’t need the power, in addition to shipping and transmission costs. An energy analyst estimated that the energy will cost Bangladesh five times the cost of a solar project.[13]

In January 2023, Bangladesh’s Minister for Power, Energy and Mineral Resources stated that electricity from the plant would cost two cents more per kWh than was estimated the month prior. It was also reported that the date for starting commercial operations had been set as December 16, 2022. However, reporting referenced that based on a site visit, the first unit was still only producing around 250 MW during a test run. Nasrul Hamid said: "By mid-March, we will hopefully get around 750MW from the power plant."[14]

The first unit was not listed in CEA's installed capacity report for December 2022, and was not considered operational in December 2022 for purposes of the Global Coal Plant Tracker.

In February 2023, experts analyzed the "lopsided" agreement signed by Adani and the Bangladesh Power Development Board. One key finding was that Bangladesh must remain in the agreement even if Adani breached the contract. Additionally, Adani received a tax exemption on the deal and simultaneously planned to charge Bangladesh a tariff for the exempt taxes, essentially allowing the conglomerate to double dip on tax dollars and save well over $1 billion over the 25-year contract.[15]

In March 2023, Unit 1 was officially commissioned and electricity supply to Bangladesh began.[16] By June 2023, the full plant was operational.[17]

According to reporting from August 2024, India’s Ministry of Power agreed to relax the 2018 rules on power exports to Bangladesh, and the Adani Godda power station would be allowed to sell electricity into the Indian market.[18] This rule-change reportedly prompted outrage from critics who said that India’s government was “bailing out” Gautam Adani, whose company could face large financial losses following political turmoil in Bangladesh.[19]

As of September 2024, Bangladesh’s interim government was planning to review the power purchase contract between the Bangladesh Power Development Board (BPDB) and the Adani Group. The Adani Group claimed that the BPDB owed the company US$800 million for power purchases.[20]

In early November 2024, Adani Power shut down a unit at the Godda power station, halving the electricity supply to Bangladesh in response to an alleged $850 million in unpaid bills.[21] Bangladesh’s Ministry of Power had opened a line of credit worth US$170 million in an effort to avert additional power cuts from the plant.[22]

Coal source

The plant will be fuelled by imported coal which the company plans to procure under long term firm agreement from countries like Indonesia, South Africa and Australia. The imported coal will be received at Dhamra Port in Odisha and be transported to the project site by rail. The annual coal requirement is estimated to be about 7-9 MTPA.[2]

Opposition

Locals report being assaulted and harassed to give over their land for the power project. According to Newslaundry, the violence was barely covered in the media: "A few local editions of language media publications carried small reports on the violence. One local journalist Nagmani told Newslaundry, 'I had footage of police lathi-charge in Motia but SDPO Abhishek Kumar forced me to delete it.'”[23]

A legal case filed at the High Court of Jharkhand by local villagers iwasscheduled to be heard in early August 2020. The claimants accuse Adani and its agents of using "coercion, fraud [and] undue influence" to illegally exclude thousands of people affected by the power plant development from a required social impact assessment. The court case also challenges the forced takeover of land for the development by the State Government on behalf of Adani. Under Indian law, a government can only acquire land for a private company if the project is for "public purpose". The claimants believe that the project fails to meet the definition of "public purpose" under the law. The state of Jharkhand denies all the allegations being put by the claimants and is contesting the court action. The project is also the subject of a separate environmental challenge to be heard by India's National Green Tribunal.[24]

Financing

  • Source of financing: 2019: 80% debt financing from Power Finance Corporation and Rural Electrification Corporation, 20% equity financing from Adani Power[25]

Financial close for the project had been due to be concluded by November 2018, but by March 2019 had not yet been achieved. Adani Power was reported to be courting both international and domestic lenders for the financing of the project, with estimated costs of US$1.94 billion.[26] In September 2019, financial close was confirmed: Power Finance Corporation and Rural Electrification Corporation, both state-controlled financial institutions, are providing equal tranches of a US$1.4 billion loan and the promoter Adani Power is providing US$203 million in equity.[25]

Articles and Resources

References

  1. Form 1, India MoEF, February 4, 2016
  2. 2.0 2.1 2.2 EIA, Adani Power, April 2017
  3. Environmental clearance, India MoEF, August 31, 2017
  4. "Taking Over Fertile Land For Adani Group From Protesting Farmers, Jharkhand Government Manipulates New Law Meant To Protect Them," India Spend, December 1, 2018
  5. "Adani Godda Power Project Too Expensive, Too Late, and Too Risky for Bangladesh," IEEFA, April 2018
  6. Clyde Russell, "COLUMN-Adani claims Carmichael coal win, but it's a pyrrhic victory built on subsidies: Russell," Reuters, July 13, 2020
  7. "In final days of Modi government, Adani project in Jharkhand becomes India's first power sector SEZ," Scroll.in, March 25, 2019
  8. "Jharkhand: Construction Begins in Adani's Godda Plant, Villagers Dejected". NewsClick. 2019-09-07. Retrieved 2020-01-03.
  9. "Adani project on less-sure ground". The Telegraph. January 3, 2020.{{cite web}}: CS1 maint: url-status (link)
  10. "1,600-MW Jharkhand project delayed amid Covid-19 lockdown: Adani Power," Business Standard, June 1, 2020
  11. "Adani Godda ultra-supercritical power project delayed by COVID-19 pandemic, likely to be operational by March 2022," The Free Press Journal, October 23, 2021
  12. "Delays to hit Adani’s Godda power station for another year," Adani Watch, July 6, 2022
  13. "How political will often favors a coal billionaire and his dirty fossil fuel," The Washington Post, December 9, 2022
  14. "Adani Godda Power Plant: Bangladesh likely to get 750MW by March," The Daily Star, January 4, 2023
  15. "Heads Adani wins, tails Bangladesh loses," The Daily Star, February 27, 2023
  16. "Adani power chapter begins in Bangladesh," TBS News, March 9, 2023
  17. "Back Adani’s Godda plant for power supply to Bangladesh becomes fully operational," Live Mint, June 27, 2023
  18. “Adani now allowed to sell Bangladesh-bound power in India,” Reuters, August 13, 2024
  19. “Adani’s Godda coal-power plant and Bangladesh: rule change on power exports benefits Modi’s ‘crony’,” Adani Watch, August 23, 2024
  20. “Bangladesh's interim government to review Adani Power deal: Report,” Hindustan Times, September 12, 2024
  21. “Adani cuts 50% electricity supply to Bangladesh: Here’s why,” Mint, November 3, 2024
  22. “Bangladesh Devises Payment Plan to Avert Adani Power’s Cuts,” BNN Bloomberg, November 6, 2024
  23. "Adani Power Vs The People Of Jharkhand," Newslaundry, December 22, 2016
  24. Stephen Long, "Adani power plant and coal plans threatened by land owner court action," ABC, July 9, 2020
  25. 25.0 25.1 [1] Brickworks Ratings on Adani Power (Jharkhand), September 9, 2019
  26. "India approves Jharkhand power SEZ," IJGlobal, March 5, 2019

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.