Amera Coal Mine
This article is part of the Global Coal Mine Tracker, a project of Global Energy Monitor. |
Sub-articles: |
Related-articles: |
Amera Coal Mine is a proposed coal mine in Amera, Surguja, Chhattisgarh, India.
Location
Table 1: Project-level location details
Mine Name | Location | Coordinates (WGS 84) |
---|---|---|
Amera Coal Mine | Amera, Surguja, Chhattisgarh, India | 23.065899, 83.049535 (exact) |
The map below shows the exact location of the coal mine:
Project Details
Table 2: Project status
Status | Status Detail | Project Type | Opening Year | Closing Year |
---|---|---|---|---|
Proposed[1] | Announced | New | 2025 (planned)[1] | – |
Table 3: Operation details
Capacity (Mtpa) | Production (Mtpa) | Year of Production | Mine Type | Mining Method | Mine Size (km2) | Mine Depth (m) | Workforce Size |
---|---|---|---|---|---|---|---|
1[1] | – | – | Surface | Open Pit | 6.68 | 50* | * |
Table 4: Coal resources and destination
Total Reserves (Mt) | Year of Total Reserves Recorded | Total Resources (Mt) | Coalfield | Coal Type | Coal Grade | Primary Consumer/ Destination |
---|---|---|---|---|---|---|
22.42 | – | – | Lakhanpur | Subbituminous | Thermal | – |
Table 5: Ownership and parent company
Owner | Parent Company | Headquarters |
---|---|---|
South Eastern Coalfields Ltd | Coal India Ltd [100.0%] | India |
Note: The above section was automatically generated and is based on data from the Global Coal Mine Tracker April 2024 release and the September supplement.
Background on Mine
The Amera Opencast Coal Mine Project is sited on a mining lease area of 668.184 ha. The project received its environment clearance for a capacity of 1 million tonnes per annum on 22 February 2005.[2]
The mine proposed an expansion in 2015 but there have been no public statements regarding those developments and it was likely shelved and now cancelled.
According to SECL's annual report in 2022, Project is delayed due to delay in possession of land. Villagers resisting in disbursement of land compensation. 38% disbursement of compensation has been completed. The Project is likely to be completed in 2025-26.[3]
Expansion Details
- Status: Cancelled
- Size of Expansion: 2.0 MTPA
- Permits and Applications: Form 1 for Environment Clearance for Expansion of Amera Opencast Coal Mine Project from 1.0 MTPA to 2.0 MTPA, CPMDI, April 2015
Articles and Resources
Additional data
To access additional data, including an interactive map of world coal mines, a downloadable dataset, and summary data, please visit the Global Coal Mine Tracker on the Global Energy Monitor website.
References
- ↑ 1.0 1.1 1.2 (PDF) https://d3u7ubx0okog7j.cloudfront.net/documents/SECL_Annual_Report_2022-23.pdf.
{{cite web}}
: Missing or empty|title=
(help) - ↑ Form 1 for Environment Clearance for Expansion of Amera Opencast Coal Mine Project from 1.0 MTPA to 2.0 MTPA, CPMDI, April 2015
- ↑ SECL Annual Report 2022-2023, South Eastern Coalfields Limited