Asam-Asam power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Asam-Asam power station is an operating power station of at least 260-megawatts (MW) in Asam-Asam, Jorong, Tanah Laut, South Kalimantan, Indonesia with multiple units, some of which are not currently operating. It is also known as Kalselteng-2.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Asam-Asam power station | Asam-Asam, Jorong, Tanah Laut, South Kalimantan, Indonesia | -3.9265336, 115.105805 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2, Unit 5, Unit 6, Unit B-3, Unit B-4: -3.9265336, 115.105805
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Unit 1 | operating | coal: lignite, bioenergy: wood & other biomass (solids) | 65 | unknown | 2013 |
Unit 2 | operating | coal: lignite, bioenergy: wood & other biomass (solids) | 65 | unknown | 2013 |
Unit 5 | construction | coal: lignite | 100 | CFB | 2023 (planned) |
Unit 6 | construction | coal: lignite | 100 | CFB | 2023 (planned) |
Unit B-3 | operating | coal: lignite, bioenergy: wood & other biomass (solids) | 65 | subcritical | 2000 |
Unit B-4 | operating | coal: lignite, bioenergy: wood & other biomass (solids) | 65 | subcritical | 2000 |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Unit 1 | PT PLN (Persero) [100%] | PT PLN (Persero) [100.0%] |
Unit 2 | PT PLN (Persero) [100%] | PT PLN (Persero) [100.0%] |
Unit 5 | PT PLN (Persero) | PT PLN (Persero) |
Unit 6 | PT PLN (Persero) | PT PLN (Persero) |
Unit B-3 | PT PLN (Persero) [100%] | PT PLN (Persero) [100.0%] |
Unit B-4 | PT PLN (Persero) [100%] | PT PLN (Persero) [100.0%] |
Background
The Asam-Asam power station originally consisted of four units: the two-unit, 130-MW Banjarmasin Asam-Asam-A plant, built in 2000; and the two-unit, 130-MW Kalsel Asam-Asam plant, built in 2013.[1] All four existing units are owned by PLN.
In June 2016, the plant suffered damage to its control system that led to blackouts in some areas of South and Central Kalimantan. The problems were blamed on postponement of maintenance due to Ramadan. A team of experts from Japan was working to fix the damage.[2]
In October 2021, the power station began co-firing with 5% woody biomass.[3] In December 2024, Unit 1 conducted a trial of co-firing 5% bank notes.[4]
Expansion
As of 2013, PLN was planning to add two more 100-MW units, known as the Banjarmasin Asam-Asam-B power station; the two additional units are described in the media at Units 5 & 6 of the Asam-Asam plant or Units 5&6 of Kalselteng-2. The original plan was apparently to build three additional units; this plan was scrapped due to various problems, including investors withdrawing from the project. In May 2013, though, the project was reborn, but now as two rather than three units.[5]
According to an October 2013 report, development of the project "is still waiting for a letter of feasibility of PT PLN (Persero) from the government." The report continued: "Garibaldi Thohir, President Director of Adaro Energy, said the government’s guarantee is needed because even as Independent Power Producer (IPP), South Kalimantan coal power plant is including on Public Private Partnership (PPP) project scheme."[6]
As of January 2015, South Kalimantan government officials were urging PLN to accelerate the expansion project, in order to help prevent blackouts in the area.[7]
In November 2015, it was reported that two units of 100 MW each had been pre-qualified for tender.[8]
In February 2016, the project entered the auction process. The process was considered likely to finish in 2016, but PLN officials stressed that success was not a certainty.[2]
Construction began in July 2017. Commercial operation of Units 5 and 6 is planned for July and October 2020.[9]
In February 2020, it was reported that hundreds of construction workers who had been building the expansion had been laid off and that construction was stalled.[10]
As of October 2021, the expansion had an anticipated start date in 2022.[11]
In March 2023, test operations and synchronization began for Asam-Asam power station Unit 5. Target operation for the expansion was slated for November 2023.[12]
In August 2023, local residents raised concerns that they would not be given priority for job recruiting when Units 5 and 6 began operating. A representative of PLN confirmed that residents of the nearby community would be given priority for hiring at the new units.[13]
As of January 2024, the expansion units were not yet operating. Synchronization tests were underway.[14] In April 2024, the expansion was not yet operating.[15]
In July 2024, synchronization and testing of the units was ongoing.[16] A September 2024 article mentioned the management of fly ash and bottom ash waste from Units 5 and 6, but there was no further news about the status of the expansion project.[17]
Financing
On July 31, 2017, ITOCHU Corporation announced that it had concluded an EPC (Engineering, Procurement, and Construction) agreement for the Kalselteng-2 Units 5 & 6 project.[18] The Japan Bank for International Cooperation (JBIC) and MUFG Bank agreed to cofinance the project with approximately US$241 million in loans. JBIC is providing JPY10.1 billion and US$53 million in loans (for a total of approximately US$144 million), and MUFG is providing JPY6.8 billion and US$36 million in loans (for a total of approximately US$97 million). MUFG's portion of the financing is insured by Nippon Export and Investment Insurance.[19][20]
In October 2020, MUFG announced that it was planning to halve its overseas coal investments by 2030 and eliminate them by 2040.[21]
Articles and Resources
References
- ↑ PLN Siapkan 2 PLTU Baru, Banjarmasin Post, 26 Oct. 2013.
- ↑ 2.0 2.1 "PLN Invites Japanese Experts to Fix Asam-asam Steam Power Plant," Media Indonesia, 20 June 2016
- ↑ PLN konsisten turunkan emisi PLTU Asam Asam, Antara News, August 3, 2022
- ↑ PLN Indonesia Power dan Bank Indonesia Manfaatkan Limbah Uang Kertas untuk Bahan Bakar PLTU, Dunia Energi, December 11, 2024
- ↑ PLTU Unit Lima Dan Enam Siap Dibangun, Kalimantan News, 27 May 2013.
- ↑ Wilda Asmarini, "Adaro-Korea Power Plant Project Awaits Government's Guarantee," Indonesia Finance Today, October 25, 2013
- ↑ Ayo Percepat Pembangunan PLTU Baru, Banua Online, 16 Jan. 2015.
- ↑ "Tender Info: PLN Prequalifies EPC of Sulsul Barr-2 Kalselteng-2 Coal-Fired Steam Power Plants," RambuEnergy, November 15, 2015
- ↑ "Kalselteng-2 Coal-Fired Power Plant Project," Energy Central, August 7, 2017
- ↑ Ratusan Pekerja Proyek PLTU Asam-Asam Unit 5-6 Dirumahkan, kalsel.prokal.co, Feb. 15, 2020
- ↑ Rencana Usaha Penyediaan Tenaga Listrik (RUPTL) 2021-2030, PT PLN Persero
- ↑ Pasok Listrik Kalselteng dan Pembangunan IKN, PLN Tambah 100 MW di Unit 5 PLTU Kalselteng 2, Balikpapan, March 12, 2023
- ↑ Warga Desa Mengadu, Minta PLTU Asam Asam Merekrut Warga Lokal, PT Duta Prokal, August 11, 2023
- ↑ Laik Sinkron, PLTU Kalselteng 2 (2×100) MW Unit 1 Siap Pasok Listrik Ke Sistem Interkoneksi, Banjarbaru Klik, January 14, 2024
- ↑ Direktur Operasi Pembangkit Batubara PLN Indonesia Power Melakukan Inspeksi Ke PLTU Asam-Asam, Radar Banjarmasin, April 16, 2024
- ↑ PLTU Kalselteng 2 Berhasil Load Rejection Test Unit 2, Siap Sumbang 100 MW ke Sistem Kalimantan, Kaltimpost, July 23, 2024
- ↑ PLN UIP KLT Ubah Limbah FABA PLTU Kalselteng 2 Jadi Rumah Ikan, iNews Balikpapan, September 19, 2024
- ↑ "ITOCHU Announces EPC Agreement for Coal Fired Power Plant in Indonesia," ITOCHU press release, July 31, 2017
- ↑ Buyer's Credit for National Power Company of Indonesia, Japan Bank for International Cooperation, June 21, 2017
- ↑ Republic of Indonesia / Loan Insurance for Kalselteng 2 Coal-fired Power Plant Project, Nippon Export and Investment Insurance, June 21, 2017
- ↑ MUFG to Join Rivals in Phasing Out Coal Power Financing, Bloomberg Law, Oct. 15, 2020
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.