Athena Chhattisgarh power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Athena Chhattisgarh power station is a power station under construction in Bade Dumarpali, Kharsia, Raigarh, Chhattisgarh, India. It is also known as Singhitari, Singhitarai.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Athena Chhattisgarh power station | Bade Dumarpali, Kharsia, Raigarh, Chhattisgarh, India | 21.906765, 83.129001 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2: 21.906765, 83.129001
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Unit 1 | construction | coal: unknown | 600 | supercritical | 2025 (planned) |
Unit 2 | construction | coal: unknown | 600 | supercritical | 2025 (planned) |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Unit 1 | Athena Chattisgarh Power Ltd [100%][1] | Vedanta Ltd [100.0%] |
Unit 2 | Athena Chattisgarh Power Ltd [100%][1] | Vedanta Ltd [100.0%] |
Background
The Athena Chhattisgarh power station is a proposed 1200 megawatt (MW) coal-fired power plant in Bade Dumarpali, Kharsia, Raigarh, Chhattisgarh, India.[2]
On January 15, 2009, a public hearing was held under the authority of the Additional District Magistrate, Janjgir-Champa. At the hearing, members of the group Jan Chetana pointed out that the Terms of Reference (ToR) for the plant required that a study cover an area of 10 km radius around the proposed site, but that the study actually only included an area of 7 km radius, thereby excluding the village of Singhitari. Based on this evidence, the Additional District Magistrate cancelled the public hearing. However, in August 2009, the Ministry of Environment and Forestry approved the project, clearing the way for construction.[3]
At this point, Ramesh Agrawal, with help from lawyers with the Legal Initiative for Forests and Environment (LIFE) challenged the clearance before the National Environmental Appellate Authority (NEAA). As a result, in November 2009 the NEAA issued a one-page order stating that the proceedings of the public hearing did not have any validity. The NEAA then quashed the environmental clearance for the project on March 8, 2010. On April 5, 2010, the public hearings were held again 25-30 km away from the project site, and only 10-15 villagers were able to attend.[4]
On June 4, 2010, the project received Environmental Clearance,[5] which was renewed in March 2016.[6]
The power station was planned for completion in 2014,[7] but in April 2015 was still listed as under construction.[8] It is now planned for operation in 2016,[9] later pushed to 2017.[10]
Insolvency proceedings
In November 2017, it was reported that work at the site was on hold due to financial constraints. The commissioning date was listed as "uncertain".[11] The power station is one of a number of Troubled Indian Coal Plant Construction Sites.
Andhra Pradesh State Power Generation Company was planning to acquire the 1.2 GW plant (co-owned by Athena Ventures, PTC India and IDFC) to resolve the stranded asset outside National Company Law Tribunal (NCLT). However, the Andhra Pradesh State Engineering Board (APSEB) in April 2020 wrote to the Andhra Pradesh Energy Secretary to advise against acquiring the asset. APSEB suggested that the acquisition of the power plant would be risky (as it still did not have a coal linkage), expensive, and techno-commercially unfeasible for the State’s grid.[12][13]
In 2021 documents, the Central Electricity Authority noted the following about the project: "Admitted to NCLT on 15.05.2019; The Liquidator is under process and making efforts for Sale as a going concern."[14]
Vedanta Acquisition
In July 2022, mining major Vedanta Limited acquired Athena Chhattisgarh Power Limited for Rs 5.65 billion to meet its captive power requirements. The project had two partially complete power units of 600 MW each. Vedanta reportedly outbid Jindal Power Limited (JPL) for the acquisition. In a regulatory filing announcing the acquisition, Vedanta stated, “The acquisition is expected to fulfil the power requirement for Vedanta’s aluminium business and through vertical integration, add synergies by providing a cost advantage pertaining to power consumption.” Athena Chhattisgarh Power was a special purpose vehicle promoted by Athena Energy Ventures Private Limited, a joint venture among Athena Projects Private Limited, PTC India Limited, and Infrastructure Development Finance Company Limited. Units 1 and 2 (600 MW each) of the power plant were 80 per cent and 30 per cent complete respectively and therefore, the plant had never been operational. The acquisition was likely to be completed during 2022-23.[15][16]
The June 2023 and the November 2023 Broad Status reports stated that the plant was likely to be revived under Vedanta by FY 2030-31.[17]
In the August 2024 Broad Status report, the expected date of revival had been updated to 2025.[18]
Continued development under Vedanta
In March 2023, Athena Chhattisgarh Power Limited (ACPL) applied to renew its Environmental Clearance for the 2 x 600 MW proposal in Singhitarai. The EAC granted ToR for conducting an EIA study for the project.[19] (Documents related to the original permit were available in MOEF files J- 13011/7/2009-IA II (T) and J- 13011/7/2009-IA II (T)ia.) The Terms of Reference are dated May 10, 2023.[20]
In September 2023, the Expert Appraisal Committee (EAC) of the Ministry of Environment, Forest and Climate Change recommended that environmental clearance be granted.[21] A formal letter was issued by January 2024.[22]
Reporting in April 2024 announced that Vedanta had secured an 11-year term loan of Rs 3,900 crore from Power Finance Corporation Ltd (PFC) for the purpose of completing construction of the new units at the Athena Chhattisgarh and Meenakshi Energy coal plants.[23]
Citizen opposition
According to the Environmental Justice Atlas, "The ministry of environment and forest (MoEF) had earlier granted approval to the ACPL project. The matter was challenged in the National Environment Appellate Authority (NEAA) by the Ngo Jan Chetanaa. The group challenged the environmental clearance on the ground that the MoEF approved the project without considering the mandates of public hearing. The Public Hearing was held on January 15, 2009 but was later cancelled by the chairperson in view of the documents not being made available to the affected public. However, the National Environment Appellate Authority (NEAA) went through the video recording of the Public Hearing and was convinced that there was discrepancy in what was recorded in the minutes of the public hearing and what was spoken in public by the officials. In fact, it was observed that there was massive opposition of the public to the project. Based on the complaint coupled with evidence, the NEAA stayed the clearance; in November 2009 the NEAA issued a one-page order stating that the proceedings of the public hearing did not have any validity. The NEAA then quashed the environmental clearance for the project on March 8, 2010. On April 5, 2010, the public hearings were held again, but 25-30 km away from the project site. Only 10-15 villagers were able to attend the meeting. On June 4, 2010, the project received Environmental Clearance."[24]
Citizen groups
- Jan Chetana
Financing
According to Brickworks Rating report as per information available in 2015, the initial project cost was Rs. 6200 Crore, with Debt: Equity Ratio of 3:1. The financial closure was achieved in March 2011, and Project Loans were sanctioned by a consortium of banks led by State Bank of India.[25] Other sources suggest that there were 17 other lenders involved.[26] As of January 2022, total bank debt amounted to Rs 7,281 crore and it was most likely restructured as part of the company's insolvency proceedings.[27] It was not clear if any bank debt was still outstanding following Vedanta's acquisition.
Reporting in April 2024 announced that Vedanta had secured an 11-year term loan of Rs 3,900 crore from Power Finance Corporation Ltd (PFC) for the purpose of completing construction of the new units at the Athena Chhattisgarh and Meenakshi Energy coal plants.[23] It was unclear what amount of the loan would be used for the construction of the Athena Chattisgarh power station.
Articles and Resources
References
- ↑ 1.0 1.1 https://web.archive.org/web/20240218234419/https://economictimes.indiatimes.com/industry/energy/power/vedanta-to-buy-athena-chhattisgarh-power-for-rs-564-crore/articleshow/92727754.cms?from=mdr. Archived from the original on 18 February 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ "Pending application of IPP's up to 31ST July, 2011," Ministry of Coal, August 2011, page 9.
- ↑ Kanchi Kohli, "Public Hearings on Power Projects: Cleared, Denied, Cleared, ...," The Movement of India, July-August 2010
- ↑ Kanchi Kohli, "Public Hearings on Power Projects: Cleared, Denied, Cleared, ...," The Movement of India, July-August 2010
- ↑ "2×600 MW Coal Based TPP at village s Singhitarai, Benipali, Odekera & Nimohi, by Athena Chhattisgarh Power Pvt. Ltd.," Thermal MoEF News, July 2, 2011
- ↑ Environmental clearance extension, India MoEF, March 22, 2016
- ↑ Monthly Report on Broad Status of Thermal Power Projects in the Country, Central Electricity Authority, September 2012
- ↑ Monthly Report on Broad Status of Thermal Power Projects in the Country, Central Electricity Authority, April 2015
- ↑ "Monthly Report on Broad Status of Thermal Power Projects in the Country," India CEA, November 2015
- ↑ "Monthly Report on Broad Status of Thermal Power Projects in the Country," India CEA, July 2016
- ↑ "Monthly Report on Broad Status of Thermal Power Projects in the Country," Government of India Ministry of Power, November 2017
- ↑ "Time to retire stranded thermal power units," The Hindu Business in Line, March 28, 2021
- ↑ "Move to acquire Athena opposed by APSEB," The Hindu, April 23, 2020
- ↑ “Broad Status Report,” Thermal Project Monitoring Division , Central Electricity Authority, November 2021
- ↑ "Stressed Asset Deal: Vedanta acquires Athena Chhattisgarh Power," Power Line, August 2, 2022
- ↑ "Vedanta to buy Athena Chhattisgarh Power for Rs 564 crore," Economic Times, July 7, 2022
- ↑ Broad Status Report of Under Construction Thermal Power Projects (June, 2023) Central Electricity Authority, Government of India, June 2023
- ↑ “Broad Status Report of Under Construction Thermal Power Projects (August, 2024),” Central Electricity Authority, Government of India, August 2024
- ↑ "Minutes of the 39th Meeting of the Re-Constituted EAC on EIA of Thermal Power Projects," MoEF, March 31, 2023
- ↑ "Terms of Reference," MoEF, May 10, 2023
- ↑ "Minutes of 47th Meeting of the Re-Constituted Expert Appraisal Committee (EAC) (Thermal Power Projects), held from 26/09/2023 to 26/09/2023," India Ministry of Environment, Forest and Climate Change, October 18, 2023
- ↑ Environmental Clearance, MOEF, January 6, 2024
- ↑ 23.0 23.1 Vedanta secures 11-year Rs 3,900 crore loan from PFC, says report, Business Standard, April 15, 2024
- ↑ "Athena Chhattisgarh Power Limited (ACPL), India" Environmental Justice Atlas, accessed April 2, 2014.
- ↑ "Brickwork Ratings Withdraws the ratings for the Bank Loan Facilities of ₹5442.00 Crores of Athena Chhattisgarh Power Ltd. (ACPL or 'the company')" (PDF). www.brickworkratings.com. 2019.
{{cite web}}
: line feed character in|title=
at position 88 (help)CS1 maint: url-status (link) - ↑ "PROJECT STATUS OF 2 X 600 MW SINGHITARAI THERMAL POWER PROJECT Janjgir-Champa District, Chhattisgarh" (PDF). environmentclearance.nic.in. 2017.
{{cite web}}
: line feed character in|title=
at position 18 (help)CS1 maint: url-status (link) - ↑ "No Buyers For Athena Chhattisgarh Power plant? Watch Report". /www.facebook.com. January 2022.
{{cite web}}
: CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.