Badaguichiri Cement Plant power station is an operating power station of at least 30-megawatts (MW) in Badaguichiri, Illéla, Tahoua, Niger. It is also known as Tambass Cement Plant power station.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Badaguichiri Cement Plant power station Badaguichiri, Illéla, Tahoua, Niger 14.505942, 5.408871 (exact)[1]

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1: 14.505942, 5.408871

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year
Unit 1 Operating[2] coal: unknown[3] 30[1] unknown 2023[2]

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1 Taizhou Wangkang Trading Co Ltd [100%][4] Taizhou Wangkang Trading Co Ltd [100.0%]

Project-level captive use details

  • Captive industry use (heat or power): power[1]
  • Captive industry: Cement & Building[1]


Project-level coal details

  • Coal source(s): Tefereyre Coal Mine

Background

In May 2023, China Africa Building Material NIG SA (CBM Nig) received approval from Niger’s energy regulatory authority to construct a 30 MW captive coal-fired power station for a cement plant in the rural commune of Badaguichiri in Tahoua Region, Niger.[5] CBM Nig was the engineering, procurement, and construction (EPC) contractor for the cement plant and power station, with the Wangkang Group as investors.[6][7]

The Badaguichiri Cement Plant was inaugurated in July 2023,[8][9] and the power station was presumed to be operating.

In August 2024, the Minister of Energy visited the power station and confirmed it would receive coal from the Société nigérienne du charbon (SONICHAR).[10]

Articles and Resources

References

  1. 1.0 1.1 1.2 1.3 (PDF) https://www.arse.ne/wp-content/uploads/2024/01/Decision-N-003-ARSE-CR-2023-Portant-avis-de-non-objection-sur-une-demande-d-autorisation-et-etablisement-et-exploitation-installation-autoproduction-thermique-Bouji2.pdf. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 https://www.lesahel.org/inauguration-officielle-de-la-cimenterie-cmb-nig-de-badaguichiri-repondre-aux-besoins-des-populations-nigeriennes-a-travers-une-production-du-ciment-a-grande-echelle/. {{cite web}}: Missing or empty |title= (help)
  3. http://news.aniamey.com/h/120837.html. {{cite web}}: Missing or empty |title= (help)
  4. https://www.sinoma-suzhou.com/newsinfo/5916626.html. {{cite web}}: Missing or empty |title= (help)
  5. “College de Regulation Decision No 003 ARSE/CR/2023,” Autorité de Régulation du Secteur de l’Energie, République du Niger, May 9, 2023
  6. “苏州中材尼日尔3000t/d熟料水泥生产线项目点火成功,” Sinoma (Suzhou) Construction Co., May 16, 2023
  7. “一带一路|希望森兰助力尼日尔最大水泥生产线点火投产,” Hope Senlan Technology Co., May 2023
  8. “La cimenterie de Badaguichiri, Fiche technique,” L’Agence Nigérienne de Presse, July 18, 2023
  9. “Inauguration officielle de la cimenterie CMB NIG de Badaguichiri: Répondre aux besoins des populations nigériennes à travers une production du ciment à grande échelle,” Le Sahel, July 20, 2023