Baosteel Zhanjiang Iron & Steel Co Ltd (宝钢湛江钢铁有限公司) is a blast furnace-basic oxygen furnace (BF-BOF) steel plant operating in Zhanjiang, Guangdong, China.

Location

The map below shows the exact location of the plant in Zhanjiang, Guangdong, China:

Loading map...
  • Location: No. 18 Dongdao Avenue, Dongjian Street, Zhanjiang Economic and Technological Development Zone, Zhanjiang City, Guangdong Province
  • Coordinates (WGS 84): 21.056035, 110.486570 (exact)

Background

The No. 1 blast furnace system and No. 2 blast furnace system, including 2 blast furnaces and 3 BOF, have been put into operation. The No. 3 blast furnace system, including a 5050m3 blast furnace and a 350 tonne basic oxygen furnace, is still under construction and is expected to be put into operation in 2021.[1][2]

The No. 3 blast furnace system, including a 5050m3 blast furnace and a 350 tonne basic oxygen furnace was put into operation on December 28, 2021。[3]

On December 23, 2021, Baosteel Zhanjiang 1 million-ton hydrogen-based shaft furnace project started. The project will build China's first self-integrated mega-ton shaft furnace, and the world's first shaft furnace that directly adds hydrogen for reduction production.[4][5]

Low-emissions/green steelmaking

This steel plant is associated with a green steel project tracked in the Green Steel Tracker. Details about the project are included below.

Table 1: Green Steel Project Details

All references for the above data are available in the Green Steel Tracker.
Project 1
Company China Baowu Group
Company has climate goals? Yes
Location Zhanjiang, China
Project name Baowu Zhanjiang ENERGIRON
Project website [https://tenova.com/newsroom/latest-tenova/largest-hydrogen-based-dri-facility-china

https://www.energiron.com/energiron-largest-hydrogen-based-dri-facility-in-china-for-baosteel-zhanjiang/ Site]

Project scale Full scale
Project status Operating
Year to be online 2023
Technology to be used NG-DRI to H-DRI
Technology details ENERGIRON ZR –Zero Reformer using natural gas, coke-oven gas, and hydrogen.
Iron production capacity (million tonnes per year) 1
Steel production capacity (million tonnes per year) Not stated
CO2 capture (million tonnes CO2 per year) Not stated
Hydrogen generation capacity(MW) Not stated
Investment size Not stated
Actual start year 2023
Partners Tenova, Energiron, Sinosteel Engineering & Technology Co., Ltd.
Date of announcement 2022-02-01

Plant Details

Table 2: General Plant Details

Phase Plant status Announced date Construction date Start date Workforce size Power source
Main plant Operating[6][7] 2011[8][9][10][11] 4422[12] Photovoltaic Power Generation[13]
Expansion Operating[14] 2021-08[15] 2021-12[16] 2023[15] Photovoltaic Power Generation[13]

Table 3: Ownership and Parent Company Information

Phase State-owned entity status Parent company Parent company GEM ID Owner Owner company PermID Owner company GEM ID
Main plant Partial Baoshan Iron & Steel Co Ltd [90.0%]; Guangdong Hengjian Investment Holding Co Ltd [10.0%] E100000122571 [90%]; E100000125565 [10%] Baosteel Zhanjiang Iron & Steel Co Ltd[12] 5037438588 E100000121815

Table 4: Process and Products

Phase Steel product category Steel products ISO 14001 ISO 50001 Main production equipment Detailed production equipment
Main plant finished rolled[17] hot rolled plates, cold rolled sheets,hot-dip galvanized plates and wide plates[17] 2018-01-16 00:00:00[18][19] 2021-12-16 00:00:00[18][19] BF, BOF[20] 4 BOF (4x350-tonne)[20]
Expansion finished rolled[17] hot rolled plates, cold rolled sheets,hot-dip galvanized plates and wide plates[17] DRI[15] 1 Hydrogen based shaft furnace (1 million tonne)[15]

Table 5: Crude Steel Production Capacities (thousand tonnes per annum)

*Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Phase Capacity operating status* Basic oxygen furnace steelmaking capacity Nominal crude steel capacity (total)
Main plant operating 12528 TTPA[17][21][22][7][17][21][22][7][17][21][22][7][17][21][22][7] 12528 TTPA[17][21][22][7][17][21][22][7][17][21][22][7][17][21][22][7]
Expansion operating

Table 6: Crude Iron Production Capacities (thousand tonnes per annum)

*Please see our Frequently Asked Questions page for an explanation of the different capacity operating statuses.
Phase Capacity operating status* Blast furnace capacity Sponge iron/DRI capacity Nominal iron capacity (total)
Main plant operating 12250 TTPA[17][7][23][17][7][23][7] 12250 TTPA[17][7][23][17][7][23][7]
Expansion operating 1000 TTPA[24] 1000 TTPA[24]

Table 7: Upstream Products Production Capacities (thousand tonnes per annum)

Phase Sinter Coke
Main plant 14488 TTPA[19] 4018 TTPA[19]
Expansion

Blast Furnace Details

Table 8: Blast Furnace Details

Unit name Status Announced date Construction date Start date Furnace manufacturer and model Current size Current capacity (ttpa) Decarbonization technology Most recent relining
1 operating[20] unknown unknown 2015-09-25 00:00:00[25] CISDI[26] 5050 m³[20] 4115[17][7][23] unknown 2023-06-17[27]
2 operating[20] unknown unknown 2016-07-15 00:00:00[25] CISDI[26] 5050 m³[20] 4115[17][7][23] unknown unknown
3 operating[20] unknown unknown 2022-01-01 00:00:00[28] CISDI[26] 5050 m³[20] 4020[7] unknown unknown

Articles and Resources

Additional data

To access additional data, including an interactive map of steel power plants, a downloadable dataset, and summary data, please visit the Global Steel Plant Tracker on the Global Energy Monitor website.

References

  1. "宝钢湛江钢铁三高炉系统炼钢工程4#转炉顺利就位"东方财富网,August 8, 2020
  2. "广东省工业和信息化厅关于宝钢湛江钢铁有限公司三高炉项目产能置换调整方案的通告",广东省工业和信息化厅,July 30, 2021
  3. 宝钢湛江钢铁三高炉系统项目全部通过竣工验收,中国钢铁新闻网,December 30, 2021
  4. 关于宝钢湛江钢铁有限公司氢基竖炉系统项目(一步)产能置换方案的公示,广东省工业和信息化厅,August 3, 2021
  5. 世界首套!宝钢湛江100万吨级氢基竖炉工程开工,宝钢股份,December 29, 2021
  6. https://web.archive.org/web/20220126002330/http://www.ipe.org.cn/IndustryRecord/regulatory-record.aspx?companyId. Archived from the original on 26 January 2022. {{cite web}}: Missing or empty |title= (help)
  7. 7.00 7.01 7.02 7.03 7.04 7.05 7.06 7.07 7.08 7.09 7.10 7.11 7.12 7.13 7.14 7.15 7.16 7.17 https://web.archive.org/web/20220113201316/https://www.thepaper.cn/newsDetail_forward_3241216. Archived from the original on 13 January 2022. {{cite web}}: Missing or empty |title= (help)
  8. https://web.archive.org/web/20210303170032/https://www.baosteel.com/zhanjiang2014/news.html. Archived from the original on 03 March 2021. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  9. https://web.archive.org/web/20190918120142/https://www.reuters.com/article/us-china-baosteel-zhanjiang/china-approves-baosteels-11-billion-steel-project-in-guangdong-idUSBRE84O07D20120525. Archived from the original on 18 September 2019. {{cite web}}: Missing or empty |title= (help)
  10. https://web.archive.org/web/20200718232344/http://www.baosteel.com:80/group_en/channels/2898.html. Archived from the original on 18 July 2020. {{cite web}}: Missing or empty |title= (help)
  11. https://web.archive.org/web/20220320180510/http://www.csteelnews.com/xwzx/yjgg/202112/t20211230_58310.html. Archived from the original on 20 March 2022. {{cite web}}: Missing or empty |title= (help)
  12. 12.0 12.1 https://web.archive.org/web/20220111172450/https://www.qcc.com/firm/3e0343f3c76e0d12b6ecf0833394591d.html. Archived from the original on 11 January 2022. {{cite web}}: Missing or empty |title= (help)
  13. 13.0 13.1 https://web.archive.org/web/20231116140828/https://www.sohu.com/a/721237358_313737. Archived from the original on 16 November 2023. {{cite web}}: Missing or empty |title= (help)
  14. https://web.archive.org/web/20240111012043/http://www.csteelnews.com/qypd/qydt/202312/t20231229_83231.html. Archived from the original on 11 January 2024. {{cite web}}: Missing or empty |title= (help)
  15. 15.0 15.1 15.2 15.3 https://web.archive.org/web/20220812113448/http://news.gqsoso.com/qita/202108/0394568.html. Archived from the original on 12 August 2022. {{cite web}}: Missing or empty |title= (help)
  16. https://web.archive.org/web/20220318130053/https://info.lgmi.com/html/202112/29/0153.htm. Archived from the original on 18 March 2022. {{cite web}}: Missing or empty |title= (help)
  17. 17.00 17.01 17.02 17.03 17.04 17.05 17.06 17.07 17.08 17.09 17.10 17.11 17.12 17.13 17.14 17.15 17.16 17.17 https://web.archive.org/web/20220120014536/https://govt.chinadaily.com.cn/a/201804/04/WS5b7889ce498e855160e8f8af.html. Archived from the original on 20 January 2022. {{cite web}}: Missing or empty |title= (help)
  18. 18.0 18.1 https://web.archive.org/web/20190701013817/http://www.ibaosteel.com:80/ibaosteel/quickEntry/qualityAssurance?method=system&sourceSys=ibaosteel. Archived from the original on 01 July 2019. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  19. 19.0 19.1 19.2 19.3 https://web.archive.org/web/20231004171631/http://cx.cnca.cn/CertECloud/result/skipResultList?certNumber=&orgName=%E5%AE%9D%E9%92%A2%E6%B9%9B%E6%B1%9F%E9%92%A2%E9%93%81%E6%9C%89%E9%99%90%E5%85%AC%E5%8F%B8&fromIndex=true. Archived from the original on 04 October 2023. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  20. 20.0 20.1 20.2 20.3 20.4 20.5 20.6 20.7 https://web.archive.org/web/20220207192044/https://finance.sina.com.cn/money/future/indu/2020-03-02/doc-iimxxstf5776330.shtml. Archived from the original on 07 February 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  21. 21.0 21.1 21.2 21.3 21.4 21.5 21.6 21.7 https://web.archive.org/web/20220126024501/https://www.baosteel.com/en/about/product. Archived from the original on 26 January 2022. {{cite web}}: Missing or empty |title= (help)
  22. 22.0 22.1 22.2 22.3 22.4 22.5 22.6 22.7 http://www.csteelnews.com/xwzx/yjgg/202112/t20211230_58310.htmlhttp://district.ce.cn/newarea/roll/201810/12/t20181012_30501285.shtmlhttp://district.ce.cn/newarea/roll/201810/12/t20181012_30501285.shtml. {{cite web}}: Missing or empty |title= (help)
  23. 23.0 23.1 23.2 23.3 23.4 23.5 http://www.csteelnews.com/xwzx/yjgg/202112/t20211230_58310.htmlhttp://district.ce.cn/newarea/roll/201810/12/t20181012_30501285.shtml. {{cite web}}: Missing or empty |title= (help)
  24. 24.0 24.1 https://web.archive.org/web/20240209190502/https://www.aist.org/news/steel-news/2024/january/15-19-january-2024/baosteel-mill-starts-energiron-dri-facility. Archived from the original on 09 February 2024. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  25. 25.0 25.1 https://read01.com/zh-my/7RNDNm7.html#.Y-2eGOxBxhE. {{cite web}}: Missing or empty |title= (help)
  26. 26.0 26.1 26.2 (PDF) https://web.archive.org/web/20211128092238/https://www.cisdi.co.uk/Newsletter/2019/2019_08_CISDI_Newsletter.pdf. Archived from the original (PDF) on 28 November 2021. {{cite web}}: Missing or empty |title= (help)
  27. https://www.cet.com.cn/xwsd/3400733.shtml. {{cite web}}: Missing or empty |title= (help)
  28. https://web.archive.org/web/20230523060416/https://www.nbd.com.cn/articles/2023-05-22/2835316.html. Archived from the original on 23 May 2023. {{cite web}}: Missing or empty |title= (help)

Resources