Beijing Jingneng Guangdong Dongyuan Gas power station
Part of the Global Oil and Gas Plant Tracker, a Global Energy Monitor project. |
Related categories: |
Beijing Jingneng Guangdong Dongyuan Gas power station (广东京能东源热电联产, 河源市东源县天然气热电联产项目) is a power station in pre-construction in Heyuan, Dongyuan County, Guangdong, China. It is also known as 东源县燃气热电联产项目.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Beijing Jingneng Guangdong Dongyuan Gas power station | Heyuan, Dongyuan County, Guangdong, China | 23.83268, 114.774929 (approximate)[1] |
The map below shows the approximate location of the power station.
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | CHP | Start year |
---|---|---|---|---|---|---|
1-1 | Pre-construction[2] | fossil gas: natural gas[3][4][1][2] | 400[1] | combined cycle[1] | yes[1] | 2025 (planned)[2] |
1-2 | Pre-construction[2] | fossil gas: natural gas[3][4][1][2] | 400[1] | combined cycle[1] | yes[1] | 2025 (planned)[2] |
2-1 | Pre-construction[2] | fossil gas: natural gas[4][1][2] | 400[1] | combined cycle[1] | yes[1] | – |
2-2 | Pre-construction[2] | fossil gas: natural gas[4][1][2] | 400[1] | combined cycle[1] | yes[1] | – |
CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
1-1 | Beijing Energy Clean Energy and Power Shareholding Huanan Branch Co Ltd [100%][1] | Beijing Energy Clean Energy and Power Shareholding Huanan Branch Co Ltd [100.0%] |
1-2 | Beijing Energy Clean Energy and Power Shareholding Huanan Branch Co Ltd [100%][1] | Beijing Energy Clean Energy and Power Shareholding Huanan Branch Co Ltd [100.0%] |
2-1 | Beijing Energy Clean Energy and Power Shareholding Huanan Branch Co Ltd [100%][1] | Beijing Energy Clean Energy and Power Shareholding Huanan Branch Co Ltd [100.0%] |
2-2 | Beijing Energy Clean Energy and Power Shareholding Huanan Branch Co Ltd [100%][1] | Beijing Energy Clean Energy and Power Shareholding Huanan Branch Co Ltd [100.0%] |
Background
Unit 1 and Unit 2 are scheduled to commence construction in March 2024 and achieve production by the end of 2025.[5]
Articles and Resources
References
- ↑ 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 1.11 1.12 1.13 1.14 1.15 1.16 1.17 1.18 1.19 1.20 https://www.beipa.org.cn/newsinfo/4477265.html.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 2.0 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 https://www.sohu.com/a/716174422_121123763.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 3.0 3.1 https://web.archive.org/web/20240508050014/https://new.qq.com/rain/a/20240125A03C6P00. Archived from the original on 08 May 2024.
{{cite web}}
: Check date values in:|archive-date=
(help); Missing or empty|title=
(help) - ↑ 4.0 4.1 4.2 4.3 http://www.gddongyuan.gov.cn/hdjl/fkyj/content/post_565344.html.
{{cite web}}
: Missing or empty|title=
(help) - ↑ "总投资超30亿,明年3年动工!广东京能东源2×400MW(9F改进型)热电联产工程选址东源县仙塘镇热水村". 2023-08-30. Retrieved 2023-10-18.
{{cite web}}
: CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of gas-fired power stations, a downloadable dataset, and summary data, please visit the Global Oil and Gas Plant Tracker on the Global Energy Monitor website.