Bhusawal Thermal Power Station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Bhusawal Thermal Power Station is an operating power station of at least 1210-megawatts (MW) in Pimpri-Sekam, Bhusawal, Jalgaon, Maharashtra, India with multiple units, some of which are not currently operating. It is also known as Bhusawal-C Thermal Power Station Unit 1 (Unit C4), Bhusawal-A Thermal Power Station Unit 1 (Unit A1), Bhusawal-C Thermal Power Station Unit 2 (Unit C5), Bhusawal-B Thermal Power Station Unit 2 (Unit B3), Bhusawal-B Thermal Power Station Unit 1 (Unit B2).
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Bhusawal Thermal Power Station | Pimpri-Sekam, Bhusawal, Jalgaon, Maharashtra, India | 21.04798, 75.85502 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Unit 6, Unit A1, Unit B2, Unit B3, Unit C4, Unit C5: 21.04798, 75.85502
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year | Retired year |
---|---|---|---|---|---|---|
Unit 6 | construction | coal: bituminous | 660 | supercritical | 2025 (planned) | – |
Unit A1 | retired | coal: bituminous | 55 | subcritical | 1968 | 2010 |
Unit B2 | retired | coal: bituminous | 210 | subcritical | 1979 | 2017 |
Unit B3 | operating | coal: bituminous | 210 | subcritical | 1982 | – |
Unit C4 | operating | coal: bituminous | 500 | subcritical | 2012 | – |
Unit C5 | operating | coal: bituminous | 500 | subcritical | 2013 | – |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Unit 6 | Maharashtra State Power Generation Co Ltd [100%] | MSEB Holding Co Ltd [100.0%] |
Unit A1 | Maharashtra State Power Generation Co Ltd [100%] | MSEB Holding Co Ltd [100.0%] |
Unit B2 | Maharashtra State Power Generation Co Ltd [100%] | MSEB Holding Co Ltd [100.0%] |
Unit B3 | Maharashtra State Power Generation Co Ltd [100%] | MSEB Holding Co Ltd [100.0%] |
Unit C4 | Maharashtra State Power Generation Co Ltd [100%] | MSEB Holding Co Ltd [100.0%] |
Unit C5 | Maharashtra State Power Generation Co Ltd [100%] | MSEB Holding Co Ltd [100.0%] |
Background on Units 1-3
The existing power station began as a 475 megawatt (MW) power station owned by Maharashtra State Power Generation Company (MSPGCL), a Maharashtra government owned company. It comprised one 55MW unit, which was taken offline in 2010, and two 210 MW units built in 1979-1982.[1]
Unit 2 was retired in 2017.[2]
Units 4 and 5
Unit 4 (500 MW) was commissioned on March 7, 2012.[3]
Unit 5 (also 500 MW) was completed in June 2012.[4]
Unit 6
As of November 2011, the company reported that it had acquired land, fuel, and environmental clearance for Bhusawal TPS Unit 6, a 660 MW expansion.[5]
Environmental Clearance was obtained in November 2012.[6]
In April 2017, the company applied to extend the Environmental Clearance's validity.[7] The Expert Appraisal Committee recommended the extension for an additional three years on November 14, 2019, subject to a few additional conditions.[8]
In 2019, state-run engineering firm BHEL announced it "bagged" an order from Maharashtra State Power Generation Company (Mahagenco) for emission controls at the unit. The revised order value for the total project was now around ₹3,750 crore.[9]
In March 2020, plant sponsor MSPGCL submitted an amended application for environmental clearance that included plans for pollution controls.[10]
According to the government's November 2021 Broad Status report, boiler erection began on the unit in November 2019 and the boiler was 70% complete. The unit was expected by December 2022,[11] then pushed to June 2023.[12][13]
Planet satellite imagery from January 2019 to January 2022 showed progress at the site.
The May 2023 Broad Status report stated that the Unit 6 expansion was expected to enter commercial operation in October 2023.[14]
In June 2023, the Expert Appraisal Committee recommended the extension of the project's Environmental Clearance to the new unit for an additional year, i.e. until November 26, 2024. [15]
The November 2023 Broad Status report pushed back the date of commercial operation to February 2024.[16] According to the October 2024 Broad Status report, the unit was scheduled to begin commercial operation in January 2025.[17]
Articles and Resources
References
- ↑ Maharashtra State Power Generation Company, "Installed Capacity", Maharashtra State Power Generation Company website, accessed November 2011.
- ↑ "CEA approval /clearance for retirement of old 210 MW Bhusawal Tharmal Power Unit No. 2," India CEA, Aug 31, 2017
- ↑ ALL INDIA REGIONWISE GENERATING INSTALLED CAPACITY (MW) OF POWER UTILITIES INCLUDING ALLOCATED SHARES IN JOINT AND CENTRAL SECTOR UTILITIES, Central Electricity Authority, March 31, 2012
- ↑ Maharashtra State Power Generation Company, "Information on Mahagenco's Power Projects: Ongoing Thermal Power Projects – 4730 MW", Maharashtra State Power Generation Company website, August 26, 2011.
- ↑ "Information on Mahagenco's Power Projects," November 19, 2011
- ↑ Environmental Clearance for unit 6, India MoEF, November 27, 2012
- ↑ "Application for Extension of validity of Environmental Clearance (Form-I) For The Proposed 1x660 MW Unit of Coal Based Thermal Power Plant at Bhusawal, District Jalgaon, Maharashtra State," MSPGCL, April 2017
- ↑ "Minutes of the 35th Meeting of the Re-Constituted Expert Appraisal Committee (EAC) on Environmental Impact Assessment (EIA) of Thermal Power Projects Held on 14th November, 2019" Expert Appraisal Committee, November 14, 2019
- ↑ "BHEL bags order for emission control equipment for 660-MW power unit in Maharashtra," Live Mint, January 23, 2019
- ↑ Amended EC, India MoEF, March 6, 2020
- ↑ “Broad Status Report,” Thermal Project Monitoring Division, Central Electricity Authority, November 2021
- ↑ “Broad Status Report of Under Construction Thermal Power Projects,” Central Electricity Authority, May 2022
- ↑ “Broad Status Report of Under Construction Thermal Power Projects,” India Central Electricity Authority, November 2022
- ↑ Broad Status Report of Under Construction Thermal Power Projects, Central Electricity Authority, Government of India, May 2023
- ↑ Minutes of Agenda of 43rd Meeting of the Expert Appraisal Committee Ministry of Environment, Forest and Climate Change, June 19, 2023
- ↑ "Broad Status Report of Under Construction Thermal Power Projects" (PDF). Central Electricity Authority. November 2023.
{{cite web}}
: CS1 maint: url-status (link) - ↑ Broad Status Report of Under Construction Thermal Power Projects (October 2024), Central Electricity Authority, October 2024
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.