Bir Rebaa Nord–Menzel Ledjmet Est Gas Pipeline

From Global Energy Monitor
This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor.
Sub-articles:

Bir Rebaa Nord–Menzel Ledjmet Est Gas Pipeline is an existing natural gas pipeline, running from Bir Rebaa Nord gas field to Menzel Ledjmet Est gas field, Algeria.

Location

The pipeline runs from Bir Rebaa Nord gas field, Ouargla province, to Menzel Ledjmet Est gas field, Illizi province, Algeria.

Loading map...

Background

The Bir Rebaa Nord–Menzel Ledjmet Est Gas Pipeline is a 185-km, 16-inch gas pipeline connecting two gas fields. The pipeline is owned by Sonatrach, and was built by Algerian firms. It was built on an accelerated schedule in collaboration with Eni, which will be using the pipeline. It was completed in March 2020.[1][2]

Project Details

  • Operator: Sonatrach
  • Current capacity: 2.5 billion cubic meters per year
  • Length: 185 kilometers
  • Status: Operating
  • Start Date: Mar. 2020

Articles and resources

References

Related GEM.wiki articles

External resources

External articles