The Bootstrap Energy Nueces County facility is a proposed 600 MW, $1.3 billion bitcoin mining facility located near Corpus Christi, Texas, USA.

Location

The map below shows the approximate location of the Bootstrap Energy Nueces County facility near Corpus Christi, Texas, USA. The land purchased for the project is in the vicinity of the intersection of McKinzie Road and Highway 44, but the precise location is unknown.

Loading map...

Background

The project would be one of the largest in the US, with two 300 MW substations planned.[1] The 114 acre parcel will be developed in two phases. As of June 22, 2022, it is unclear if project construction has begun, or when operations may commence.

Project Details

  • Power usage (MW): 600
  • Owner: Bootstrap Energy
  • Parent:
  • Location:
  • Coordinates: 27.7847725, -97.5761225

Articles and Resources

References

  1. "Bitcoin mining facility coming to Corpus Christi". KRIS 6 News. 3/30/2022. Retrieved 6/22/2022. {{cite news}}: Check date values in: |access-date= and |date= (help)