CCC Tuxpan Phase I power station (Central CC Tuxpan Fase I) is a power station under construction in Tuxpan de Rodríguez Cano, Veracruz, Mexico.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
CCC Tuxpan Phase I power station Tuxpan de Rodríguez Cano, Veracruz, Mexico 21.0106971, -97.3300535 (exact)[1]

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • 1: 21.0106971, -97.3300535

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year
1 Construction[2][3][4][5] fossil gas: natural gas[6][7] 1056[2][8][6] combined cycle[9][10] not found 2025 (planned)[9][4]

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
1 Comisión Federal de Electricidad EPE [100%][9][11][7] Comisión Federal de Electricidad EPE [100.0%]

Background

The CCC Tuxpan Phase I power station is one of several new combined cycle power projects initiated during the six-year term of Mexican president Andrés Manuel López Obrador (2018-2024).

Official government estimates of the plant's capacity have ranged from 1056 MW[12][13][14] to 1086 MW[15] to 1151.30 MW.[14]

Construction of the plant got underway in February 2022 and was slated for completion by May 2025.[12] Construction was said to be 65.60% complete as of Dec 31, 2023[14], and 79.3% complete by September 2024.[13]

As of September 2024, Mexico's federal electricity commission CFE anticipated that the plant would begin commercial operations in December 2025.[13]

Articles and Resources

References

  1. https://web.archive.org/web/20240125141145/https://www.google.com/maps/place/CCC+TUXPAN+FASE+1/@21.0094352,-97.3328484,735m/data=!3m1!1e3!4m6!3m5!1s0x85d989e809ad2a29:0x13f484ad14f644fc!8m2!3d21.0104757!4d-97.3300745!16s%2Fg%2F11v5jb31t8?entry=tts. Archived from the original on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 (PDF) https://web.archive.org/web/20240517003459/https://gaceta.diputados.gob.mx/PDF/65/2024/abr/Cfe-20240430.pdf. Archived from the original (PDF) on 17 May 2024. {{cite web}}: Missing or empty |title= (help)
  3. https://web.archive.org/web/20240125103637/https://vanguardiaveracruz.com/siemens-iniciara-construccion-de-la-central-de-ciclo-combinado-en-tuxpan/. Archived from the original on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  4. 4.0 4.1 (PDF) https://web.archive.org/web/20240416011248/https://www.cfe.mx/cdn/2019/Archivos/Boletines/Alterna3-comp.pdf. Archived from the original (PDF) on 16 April 2024. {{cite web}}: Missing or empty |title= (help)
  5. https://web.archive.org/web/20240125110700/https://tuxpanveracruz.gob.mx/prensa/empresarios-tuxpenos-en-vinculacion-con-kiewit-corporation-encargada-de-la-construccion-de-la-central-de-ciclo-combinado-tuxpan-fase-1/. Archived from the original on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  6. 6.0 6.1 https://web.archive.org/web/20240125094702/http://aeev.veracruz.gob.mx/proyectos-central-de-ciclo-combinado-tuxpan/. Archived from the original on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  7. 7.0 7.1 (PDF) https://web.archive.org/web/20240125094028/https://www.gob.mx/cms/uploads/attachment/file/611038/Cap7_-_PAMRNT_WEB.pdf. Archived from the original (PDF) on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  8. (PDF) https://web.archive.org/web/20240520202925/https://www.cfe.mx/finanzas/Documents/Plan%2520de%2520Negocios%25202024-2028.pdf. Archived from the original (PDF) on 20 May 2024. {{cite web}}: Missing or empty |title= (help)
  9. 9.0 9.1 9.2 (PDF) https://web.archive.org/web/20240125141014/https://www.cfe.mx/finanzas/reportes-financieros/Informe%20Anual%20Documentos/Informe%20Anual%20Portal.pdf. Archived from the original (PDF) on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  10. (PDF) https://web.archive.org/web/20240125113531/http://sinat.semarnat.gob.mx/dgiraDocs/documentos/ver/estudios/2006/30VE2006E0018.pdf. Archived from the original (PDF) on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  11. (PDF) https://web.archive.org/web/20240125102753/https://www.cfe.mx/finanzas/Documents/Plan_Negocios_2023-2027.pdf. Archived from the original (PDF) on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  12. 12.0 12.1 "Cómo enfrenta la CFE el problema de la generación eléctrica en nuestro país" (PDF). Alterna: Revista de periodismo y divulgación científica de la Comisión Federal de Electricidad. 2022-12-31.{{cite web}}: CS1 maint: url-status (link)
  13. 13.0 13.1 13.2 "Informe de la Gestión Gubernamental 2018-2024 (pp 26-27)" (PDF). CFE Generación VI. 2024-09-30.{{cite web}}: CS1 maint: url-status (link)
  14. 14.0 14.1 14.2 "Informe Anual 2023 (pp 103, 240)" (PDF). CFE (Comisión Federal de Electricidad). 2024-04-25.{{cite web}}: CS1 maint: url-status (link)
  15. "Plan de Negocios 2024-2028 (p 51)" (PDF). 2024-01-31. {{cite web}}: |first= missing |last= (help)CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of gas-fired power stations, a downloadable dataset, and summary data, please visit the Global Oil and Gas Plant Tracker on the Global Energy Monitor website.