CEB Long Term Generation Expansion Plan unnamed plants

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

CEB Long Term Generation Expansion Plan unnamed plants is a cancelled power station in southern region, Ūva paḷāta, Sri Lanka.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
CEB Long Term Generation Expansion Plan unnamed plants southern region, Ūva paḷāta, Sri Lanka 7.0, 81.0 (approximate)

The map below shows the approximate location of the power station.

Loading map...


Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology
Unspecified coal units 2020-2032 cancelled coal: unknown 1200 unknown

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unspecified coal units 2020-2032 Ceylon Electricity Board [100%] Ceylon Electricity Board [100.0%]

Coal plans

The Ceylon Electricity Board (CEB) is the largest electricity company in Sri Lanka. Long-term generation expansion planning studies are carried out every two years by the Transmission & Generation Planning Branch of the Ceylon Electricity Board, Sri Lanka.

2013

The 2013 study proposed 11 coal plants totaling 3,300 MW of capacity in the period 2020-2032. The proposed construction plan it outlined was proposed to comprise one 300 MW coal-fired unit every year between 2020 and 2032.[1]

  • 1 x 300 MW coal plant in 2020
  • 1 x 300 MW coal plant in 2021
  • 1 x 300 MW coal plant in 2022
  • 1 x 300 MW coal plant in 2023
  • 1 x 300 MW coal plant in 2024
  • 1 x 300 MW coal plant in 2025
  • 1 x 300 MW coal plant in 2026
  • 1 x 300 MW coal plant in 2028
  • 1 x 300 MW coal plant in 2030
  • 1 x 300 MW coal plant in 2031
  • 1 x 300 MW coal plant in 2032

2015

The 2015 report assumed six units of the proposed Sampur power station totaling 1,700 MW would come online by 2030 (the Sampur project was later cancelled in September 2016).[2]

In addition, the plan included four 300 MW coal plants built in the "Southern region," commissioned between 2024 and 2034.[3]

2017

In its April 2017 CEB Long Term Generation Expansion Plan report for 2018-2037, CEB compared two scenarios for coal, one in which future coal power was limited to 1,800 MW of supercritical capacity commissioned from 2023 to 2032, and one in which no coal capacity was commissioned through 2037. In an initial recommendation to the Public Utilities Commission (PUC), CEB found the least cost option for Sri Lanka would be to build the 1800 MW of coal capacity.[4]

In July 2017 the government’s PUC overturned the plan, saying CEB had not considered the ‘externalities' – the economic costs of the social and environmental impacts – of the various fuels. The total cost of meeting Sri Lanka’s growing demand with coal increased from $11.9 billion to $15bn when those impacts were considered, compared to $12.4bn for meeting demand without coal. Instead, Sri Lanka's PUC said it plans to add 3.1GW of new renewable energy and 5.4GW of oil and gas generation through 2037. The plan may mark the end for new coal generation in Sri Lanka, given the country’s pledge under the Paris climate accord to add no new coal power to the system after 2030.[5][6]

However, in December 2017 it was reported that the government was considering building two coal power plants each with capacity 600 MW, one in Trincomalee and the other at Norochchole.[7] The proposals were mentioned in a 2017 joint cabinet paper (63/2017/PE), after the LTGP for 2017-2038 was approved.[8]

2018

In May 2018, the Sri Lanka Cabinet approved a policy paper detailing the energy mix for the country's future electricity generation. It stated 30 percent of Sri Lanka electricity generation will be sourced from coal, 30 percent by Liquefied Natural Gas, 25 percent by large hydro, and 15 percent from furnace oil and renewables. The Cabinet paper does not detail the megawatt which would encompass the percentages given.[9]

Despite the push for new coal plants, environmental groups say the already approved LTGP for 2017-2038 currently in force cannot be changed until 2019, according to government policy. The LTGP as it stands included no new coal proposals. According to the groups, "should the ministry need to introduce new proposals, it must wait until 2019 to do so, and seek public comments on all such new proposals. The public, being an energy consumer, has a right to comment on the nature of what they are supplied with for consumption; therefore, giving public opinion prior to the tabling of changes is moreover a consumer right."[8]

2019

In May 2019 the Times Online reported that Cabinet approval had been granted to set up three coal power plants in the country: two 300 megawatt coal plants in Trincomalee and another 300 megawatt coal plant in Norochcholai. No other details are given.[10]

In June 2019 it was reported the Cabinet had sanctioned four new 300 MW coal power units — two at the Lakvijaya Power Plant (also known as the Norochcholai plant) and two in Trincomalee, the Foul Point power station. The Cabinet also approved a proposal to amend the Sri Lanka Electricity Act to weaken the industry regulator, Public Utilities Commission of Sri Lanka (PUCSL), which had rejected Ceylon Electricity Board (CEB)’s proposal to include new coal plants in the country’s power development plan in 2017. Cabinet wants PUCSL’s role limited to only “consumer protection” and regulating safety standards, while new power development projects will be decided by the Cabinet and the Minister for Power and Energy Minister only.[11]

2020

Ceylon Electricity Board (CEB)'s Long Term Generation Expansion Plan, dated March 2020, lays out the following plans for new coal power plants:

  • 2023 - new 300 MW unit at the Lakvijaya Power Plant
  • 2026 - 2 x 300 MW Foul Point power station (phase I)
  • 2030 - 300 MW coal unit (location unspecified)
  • 2033 - 300 MW coal unit (location unspecified)
  • 2034 - 300 MW coal unit (location unspecified)
  • 2038 - 300 MW coal unit (location unspecified)


2021: No New Coal announcement

In July 2021, Sri Lanka formally committed to no new coal in its updated Nationally Determined Contributions (NDC).[12]

In August 2021, perturbed by reports that the government was going to terminate the ongoing 300 MW extension project, the Ceylon Electricity Board Engineers Union (CEBEU) appealed to the President to allow the completion of the Lakvijaya Power Plant extension.[13]

That month, the Public Utilities Commission of Sri Lanka (PUCSL) also instructed the CEB to submit a new LTGEP reflecting national policy.[14][15][16]

In advance of the 26th United Nations Convention on Climate Change in Glasgow (October-November 2021), Sri Lanka was among seven countries that announced a No New Coal Compact.[17]

2022

Ceylon Electricity Board's 2022-2041 Long-Term Generation Expansion Plan included the intention to move forward with new and expanded coal projects. An October 2021 letter by the Public Utilities Commission of Sri Lanka (attached to the existing plan as Annex 15) stated that an updated plan must be prepared on or before June 30, 2022.[18] Though the Ceylon Electricity Board has labelled the Annex as an "approval to carry out development contained therein", an August 2021 letter from the Commission clearly stated that resubmission in line with the government policy includes "no capacity addition of coal power plants".[19]

In June 2022, CEB Engineers Union President Anil Ranjith claimed the CEB does not have enough electricity supply to meet the country’s existing electricity demand: "Until we increase our supply, through thermal, wind, LNG, coal or solar, and store our energy, the power cuts will continue." Sri Lanka experienced daily scheduled power cuts starting in February 2022 due to "fuel shortages brought about by the country’s worsening economic crisis affecting the uninterrupted thermal power generation."[20]

As of mid-June 2022, a revised Long-Term Generation Expansion Plan did not appear to be available.

In August 2022, CEB again requested an extension for the submission of the revised plan.[21]

In December 2022, a Ministry of Power and Energy committee report stated that Sri Lanka must add 5,766 MW of generation capacity to the grid by 2026. The report outlined that this could be achieved through 151 MW from major hydro, 175 MW of hydro, 3,805 MW of solar, 1,475 MW of wind and 160 MW of biomass.[22]

Though not yet confirmed by an update from CEB, the power stations were presumed shelved and likely cancelled.

2023: Discontinuation

In February 2023, CEB released its 2023-2042 Long Term Generation Expansion Plan, which explicitly confirmed the discontinuation of all non-committed coal power plants identified in previous plans, including the estimated 1,200 MW capacity of proposed coal power plants referred to as "High Efficient (sic) and Eco Friendly Coal fired thermal power plant 1200 MW". [23]

The plants are therefore presumed cancelled.

Concerns about including coal in the plan

Environmental concerns

Shortly after the release of the plan Dr Janaka Ratnasiri, Former Chief Technical Adviser of the Ministry of Environment, described the proposed coal-building program as an “environmentally damaging plan” and impracticable. As the proposed power plants would be based on imported coal they would need to be located on the coast and would need adequate land both for the plant and to dump up the waste coal ash. Ratnasiri estimated that if all 16 of the proposed plants were built there would be over 1.235 million tonnes of ash collected annually from the 16 plants.[24]

“The enhancement of the concentration of particulates at ground level could be determined by carrying out dispersion modelling and local expertise is available to carry out this task. Regrettably, CEB has failed to get this exercise done. An enhancement of particulates in air will increase the risk of people exposed being subject to respiratory ailments, particularly the elderly and children. The government will have to spend billions of rupees more for the treatment of these people, but this cost has been ignored when working out the so called “least cost” options. For people in these provinces who are already suffering from kidney disease, it is nothing but falling from the frying pan to the fire,” Ratnasiri said. “Sri Lanka has gazetted the Ambient Air Quality (AAQ) Standards and it is essential that these standards are not violated. The LTGE Plan has not addressed the issue of how the ambient air quality will deteriorate with the installation of so many coal plants.”[24]

Ratnasiri said the CEB's report narrowly focussed on the costs of power generation but not the total economic cost. “What has been included is the cost to the CEB only, but what should have been included are the costs both to the CEB and the government. The damage caused to the environment as well as to human health has not been considered in the Plan, this too is a cost. It is estimated that over 4,500 tonnes of coal ash will be collected a day from all the 16 plants. Their safe disposal will cost an enormous amount. In addition to this direct cost, there are hidden costs caused by the leaching of heavy metals such as mercury, cadmium, arsenic and also radioactive substances from the ash dumps into the water table. None of these issues has been considered in the Plan,” he said.[24]

However, Additional General Manager of the CEB, M C Wickremasekera, dismissed suggestions that the proposed plants would release significant amounts of mercury, nickel, chromium and zinc, claiming that the imported coal currently used did not contain measurable amounts of these elements.[24]

Economic concerns

R Anil Cabraal, Director, KMRI Lanka (Pvt) Ltd and Board Member, Energy Forum of Sri Lanka raised concerns about the economic consequences of the proposed coal building plans. "The risks and high costs the country faced due to over dependence on hydro power generation and then oil was significant. There is a need to avoid similar concentrations with coal," he said. "From a macro economic perspective coal over dependence also contributes to an adverse balance of trade," he said.[24]

Imported coal, which is denominated in US dollars, would become more expensive if the Sri Lankan rupee deprectiated, “Already, the expansion plan assumption of exchange rate of LKR 114 per USD has been exceeded, as the exchange rate today is about 15 percent higher at LKR 131 per USD, thus, further increasing the cost of coal electricity,” Cabraal said.[24]

Wickremasekera defended the economics of coal and invoked the intermittency of solar. “Prices of all commodities will increase in the long run. However, our next option is petroleum and that is a much higher cost than coal, as we have economically harnessed all available resources. Hence, after considering all other options, we decided to opt for coal. As far as other renewable power sources are concerned, solar is a rather uncertain energy source. For instance, if solar produces 500 MW, then on a day that there is cloud cover it could reduce to nothing at all. We must have an alternate source of energy to meet the demand. So, under these conditions we have opted for the most viable option,” Wickremasekera said.[24]

Articles and Resources

References

  1. "Long Term Generation Expansion Plan 2013-2032," Ceylon Electricity Board, October 2013, page 8-2, A7-16 (Annex 7.6)
  2. "SC informed coal power plant will not be in Sampur," Colombo Gazette, September 13, 2016
  3. "Long Term Generation Expansion Plan 2015-2034," Ceylon Electricity Board, July 2015, page E-5
  4. "Long term generation expansion plan 2018-2037," Ceylon Electricity Board (CEB), Apr 25, 2017
  5. "No coal in Sri Lanka’s PUCSL approved long-term power generation plan," Lanka Business Online, July 20, 2017
  6. "Sri Lanka plans no new coal plants until at least 2037," Climate Home, August 4, 2017
  7. "Sri Lanka’s power development – Government in the reverse gear?" The Island, December 17, 2017
  8. 8.0 8.1 "Environment organisations’ response to cabinet proposal for two new coal power plants in Sri Lanka," Daily FT, Dec 20, 2017
  9. "Cabinet approves Super Critical Coal for Sri Lanka," Daily News, May 12, 2018
  10. "Cabinet approves proposal to set-up three coal power plants in the country," Times Online, 29 May 2019
  11. "Cabinet approves four coal power plants, moves to reduce PUCSL’s authority," Sunday Times, June 23, 2019
  12. “Sri Lanka: Updated Nationally Determined Contributions,” Ministry of Environment, July 2021
  13. "CEB engineers ask President to allow completion of coal-fired power plant extension project," The Island, August 1, 2021
  14. "LCLTGEP 2022-2041 Resubmission," Public Utilities Commission of Sri Lanka, August 9, 2021
  15. "LCLTGEP 2022-2041 Communications," Public Utilities Commission of Sri Lanka, updated August 16, 2021
  16. "CEB to revise power plan to reach 70% renewable energy target," Sunday Times, August 15, 2021
  17. "No new coal-based power plants to be set up in Sri Lanka: Govt," AFP, October 27, 2021
  18. "Long Term Generation Expansion Plan: 2022-2041," Ceylon Electricity Board, October, 2021
  19. "Least Cost Long Term Generation Expansion Plan 2022-2041 Resubmission," Public Utilities Commission of Sri Lanka, August 9, 2021
  20. "Sri Lanka to experience power cuts for three more years, warns CEB engineers union," Economy Next, June 15, 2022
  21. "Submission of the Draft Long Term Generation Expansion Plan (LTGEP) 2023-2042," Ceylon Electricity Board, August 24, 2022
  22. "Plan to integrate renewable energy to national grid," The Sunday Times, December 11, 2022
  23. "Long Term Generation Expansion Plan 2023-2042," Ceylon Electricity Board, February 2023
  24. 24.0 24.1 24.2 24.3 24.4 24.5 24.6 Camelia Nathaniel, CEB on a coal spree', Sunday Leader, December 8, 2013.

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.