CEEC Chongzuo power station (中能建崇左发电项目) is a power station in Qvjiu Town, Fusui County, Chongzuo, Guangxi, China with multiple units of varying statuses, none of which are currently operating.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
CEEC Chongzuo power station | Qvjiu Town, Fusui County, Chongzuo, Guangxi, China | 22.494869, 107.555455 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Phase II Unit 3, Phase II Unit 4, Unit 1, Unit 2: 22.494869, 107.555455
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Phase II Unit 3 | announced | coal: unknown | 660 | ultra-supercritical | 2025 (planned) |
Phase II Unit 4 | announced | coal: unknown | 660 | ultra-supercritical | 2025 (planned) |
Unit 1 | construction | coal: unknown | 660 | ultra-supercritical | 2025 (planned) |
Unit 2 | construction[1] | coal: unknown | 660 | ultra-supercritical | 2025 (planned) |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Phase II Unit 3 | China Energy Construction Chongzuo Development Investment Co Ltd [100%] | China Energy Engineering Corp Ltd [100.0%] |
Phase II Unit 4 | China Energy Construction Chongzuo Development Investment Co Ltd [100%] | China Energy Engineering Corp Ltd [100.0%] |
Unit 1 | China Energy Construction Chongzuo Development Investment Co Ltd [100%] | China Energy Engineering Corp Ltd [100.0%] |
Unit 2 | China Energy Construction Chongzuo Development Investment Co Ltd [100%] | China Energy Engineering Corp Ltd [100.0%] |
Background on Project
The draft EIA for the plant was released in June 2021. According to the updated project schedule, the power plant was scheduled to start construction in July 2021. Unit No. 1 was planned to be put into operation in July 2023, and Unit No. 2 in December 2023.[2]
Construction reportedly began in April 2022.[3] In August 2022, a news article reported that the project had again begun construction.[4]
However, with no known permit documents or evidence of construction, the units are presumed still under pre-permit development.
According to a 2023 list of key construction projects in Guangxi, the power project had indeed begun construction in August 2022.[5] The power station was estimated to begin operation in 2025.[5]
A second phase of the power plant (2 x 660 MW units) was reportedly announced in 2023.[5]
Articles and Resources
References
- ↑ https://web.archive.org/web/20240125084929/https://news.bjx.com.cn/html/20230821/1326808.shtml. Archived from the original on 25 January 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ "广西崇左市拟建2台百万千瓦煤电机组," 北极星电力网新闻中心, 2021/6/24
- ↑ 2×660MW!中国能建崇左电厂项目开工, BJX, 2022-04-15
- ↑ 中能建崇左2×660MW电厂工程开工, BJX, 2022-08-19
- ↑ 5.0 5.1 5.2 广西能源基础设施建设2023年工作推进方案:加快油气及煤炭储运建设 计划完成投资44.8亿元, BJX, March 30, 2023