Cangzhou Yundong Cogen power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Cangzhou Yundong Cogen power station (华润电力沧州运东热电) is an operating power station of at least 700-megawatts (MW) in Litianmu Town, Cang County, Cangzhou, Hebei, China.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Cangzhou Yundong Cogen power station | Litianmu Town, Cang County, Cangzhou, Hebei, China | 38.3288062, 117.0685273 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2: 38.3288062, 117.0685273
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Unit 1 | operating | coal: unknown | 350 | supercritical | 2020 |
Unit 2 | operating | coal: unknown | 350 | supercritical | 2020 |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Unit 1 | China Resources Power (Cangzhou Yundong) Co Ltd [100%] | China Resources Power Holdings Co Ltd [90.0%]; Cangxian Construction Investment Co Ltd [5.0%]; Cangzhou Construction Investment Group Co Ltd [2.5%]; Hebei Hengfeng Power Generation Co Ltd Trade Union Committee [1.6%]; Guanxu Investment [0.9%] |
Unit 2 | China Resources Power (Cangzhou Yundong) Co Ltd [100%] | China Resources Power Holdings Co Ltd [90.0%]; Cangxian Construction Investment Co Ltd [5.0%]; Cangzhou Construction Investment Group Co Ltd [2.5%]; Hebei Hengfeng Power Generation Co Ltd Trade Union Committee [1.6%]; Guanxu Investment [0.9%] |
Background on Project
China Resources has proposed a 2 x 350 MW combined heat and power coal plant for Cang County. It was permitted for construction in December 2015.[1]
Construction started in December 2017.[2] Planet satellite photos show construction progress from December 2017 to November 2019.
Unit 1 was commissioned in April 2020.[3] Unit 2 was commissioned in August 2020.[4]
Articles and Resources
References
- ↑ "投资30亿元 华润电力沧州运东热电联产项目获核准," March 2, 2016
- ↑ "华润电力沧州运东2×350MW热电联产工程开工," Sohu, 2017-12-8
- ↑ "华润电力沧州运东热电联产工程1号机通过168试运行," 北极星电力网新闻中心, 2020/4/21
- ↑ "华润沧州运东热电工程2号机组完成168小时试运行," 北极星电力网新闻中心, 2020/8/4