Cheyyur Ultra Mega Power Project

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Cheyyur Ultra Mega Power Project is a cancelled power station in Cheyyur Block-B, Cheyyur, Kancheepuram, Tamil Nadu, India.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Cheyyur Ultra Mega Power Project Cheyyur Block-B, Cheyyur, Kancheepuram, Tamil Nadu, India 12.3125, 79.9825 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • ': 12.3125, 79.9825

Project Details

Table 2: Unit-level details

Status Fuel(s) Capacity (MW) Technology
cancelled coal: unknown 4000 supercritical

Table 3: Unit-level ownership and operator details

Owner Parent
Coastal Tamil Nadu Power Ltd [100%] Power Finance Corp Ltd [100.0%]

Project-level coal details

  • Coal source(s): domestic

Background

The project was proposed by the government of India as part of a strategy to add an additional 100,000 megawatts of generation capacity by 2017. The 4,000 megawatt project is in the state of Tamil Nadu.[1][2]

In August 2014, it was reported that the state government would begin work on the project even though bids for its construction and operation had yet to be awarded.[3] In January 2015 state-owned NTPC was the sole bidder on the project.[4] The bid was later cancelled due to tepid private sector response and funding issues raised by bankers, although the state plans to finalize bidding by the end of the year.[5]

In March 2016, the India government said it planned to bid out three ultra mega power projects that year: Cheyyur in Tamil Nadu, Bedabahal in Odisha and Banka in Bihar.[6] According to India's proposed Electricity Plan 2017-2022, fresh bids will be issued on the UMPP after finalization of standard bidding documents by the expert committee.[7]

In December 2018, Power Finance Corporation submitted an online application to the India Ministry of Environment, Forests and Climate Change (MoEFCC) to change its source of coal from imported to domestic. On January 23, 2019, the MoEFCC said a completely fresh application for the project's environmental impact assessment was required, due to the change from imported to domestic coal.[8]

In November 2020, it was reported the project would be scrapped due to delays.[9]

With no further apparent progress since January 2019, the project was considered shelved as of 2021. As of 2023, the project was presumed cancelled.

Coal supply

Coastal Tamil Nadu Power have estimated that the power station would need between 12 and 14 Million tonnes a year or daily consumption of between 40,000 to 45,000 tonnes.[10] The company has stated that the coal for the project would be imported[11], but as yet no source has been specified.

In May 2017, departing from previous plans to use imported coal, Energy Minister Goyal stated that the project would be allotted domestic coal.[12]

Coal loader

The company have proposed that coal for the proposed power station would be imported via a "captive port" proposed to be constructed near the village of Panaiyur, in Kancheepuram district, Tamil Nadu, India. The coal loader would be approximately 5 kilometres to the east of the main power plant location at Cheyyur. Coal would be transported from the port to the power station via a closed conveyor system.[13] (See Panaiyur coal terminal for more details).

Citizen opposition

Kaayal Kadhaigal (stories from the lagoon/ current affairs)

It has been reported that, "Fishermen in Panaiyur Periakuppam village, where the captive coal jetty for the plant would be situated, fear that the project would completely destroy their livelihood. A port is expected to come up between the village and its neighbouring hamlet occupying shorefront of 650 meters. The coal stockyard will hold 310,000 tonnes of coal and would be built on an 83-acre land. The villagers have challenged the clearance given to the coal jetty in the National Green Tribunal and say they would do the same for the power project. Interestingly, the plant and coal jetty are proposed to be set up 6 km apart."[14]

Financing

The 2015 IEEFA report by Tom Sanzillo, “Cheyyurr UMPP: Financial Plan Will Make Electricity Unaffordable,” claims the Cheyyur project would undermine the Indian government’s public policy goal of providing affordable electricity for all. According to the report:

  • Although the India government is trying to make the project more attractive to investors, it would do this by passing along greater costs to the residential, industrial, and agricultural users, and requiring greater governmental subsidies.
  • Already the ratepayer tariff required to build and operate the plant is estimated at 4.9 rupees per kilowatt-hour in 2021, its first of year operation, and the plant would require an average tariff of 5.95 rupees per kilowatt hour over its 40-year life. (By comparison, four other UMPP projects in India and several additional Indian power-generation projects have tariff costs of 1.15 rupee per kilowatt hour to 3.7 rupee per kilowatt hour.)
  • The project is being developed under the assumption that it would require an annual 12 to 14 million tons of imported coal, a business model that would put its coal costs at roughly twice what they would be if domestic coal were used.

In 2019, IEEFA described the project as "stranded due to a lack of interest in Ultra Mega Power Project construction, and concern over the cost of imported coal. Now undercut by lower cost, deflationary renewables".[15]

Articles and Resources

References

  1. Rebecca Petchey, Michael Lampard and Alan Copeland, Thermal coal", Australian commodities, ABARE, Volume 17 number 1, March quarter 2010, page 155.
  2. Amiti Sen & Subhash Narayan, "States make case for second UMPP with advanced land clearances", Economic Times, (India), March 20, 2010.
  3. "Government begins work on four new ultra mega power projects," The Economic Times, Aug 24, 2014.
  4. "NTPC sole bidder for Cheyyur power project," Deccan Chronicle, Jan 5, 2015
  5. "Delay in land acquisition, other reasons, hit ultra mega power projects," PTI, Feb 26, 2015
  6. "Energiser for mega power projects," Telegraph, March 1, 2016
  7. India Electricity Plan 2017-2022, India CEA, Dec 2016, page Intro 1.25
  8. "How economic and environmental concerns are stalling mega power projects," The News Minute, Mar 1, 2019
  9. "Cheyyur ultra mega power project to be scrapped soon". dtNext.in. 2020-11-04. Retrieved 2021-06-15.
  10. Coastal Tamil Nadu Power, Executive Summary of Comprehensive Environmental Impact Assessment of proposed Captive marine terminal and coal conveyor off Panaiyur Chinnakkuppam for Cheyyur UMPP", September 2011, page 3.
  11. Coastal Tamil Nadu Power, "Executive Summary of Rapid EIA Study for Cheyyur Ultra Mega Power Project(4000 MW", Coastal Tamil Nadu Power, undated but approximately June 2011, page 2. (pdf)
  12. Debapriya Mondal, "Cheyyur UMPP to be built on domestic coal: Piyush Goyal," Energy World, May 19, 2017
  13. Coastal Tamil Nadu Power, Executive Summary of Comprehensive Environmental Impact Assessment of proposed Captive marine terminal and coal conveyor off Panaiyur Chinnakkuppam for Cheyyur UMPP", September 2011, page 2.
  14. "Cheyyur Ultra Mega Power Plant, Tamil Nadu, India" Environmental Justice Network, accessed April 21, 2014.
  15. "Seriously Stressed and Stranded The Burden of Non-Performing Assets in India's Thermal Power Sector" (PDF). IEEFA. December 2019.{{cite web}}: CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.