Chifeng Waste Coal power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Chifeng Waste Coal power station (京能赤峰能源发展公司煤矸石电厂) is an operating power station of at least 270-megawatts (MW) in Hongshan, Chifeng, Inner Mongolia, China.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Chifeng Waste Coal power station | Hongshan, Chifeng, Inner Mongolia, China | 42.288276, 119.053679 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2: 42.288276, 119.053679
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Unit 1 | operating | coal: waste coal | 135 | subcritical | 2008 |
Unit 2 | operating | coal: waste coal | 135 | subcritical | 2008 |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Unit 1 | Jingneng (Chifeng) Energy Development Co Ltd [100%] | Beijing Jingneng Power Co Ltd [94.7%]; China Energy Investment Corp [5.3%] |
Unit 2 | Jingneng (Chifeng) Energy Development Co Ltd [100%] | Beijing Jingneng Power Co Ltd [94.7%]; China Energy Investment Corp [5.3%] |
Background
The Chifeng Waste Coal power station was approved by the National Development and Reform Commission on September 25, 2006, with construction beginning in May 2007. It began operating in 2008. The project's total investment was 1.6 billion RMB.[1] The plant's hazard and occupational safety controls were then approved in 2009.[2] The plant currently supplies electricity to Liaoning and eastern Inner Mongolia, and heating to the Chifeng urban area.[3]
A second phase for the plant, consisting of 2×350MW units was planned, yet there have been no updates on this expansion since 2019.[3]
Articles and Resources
References
- ↑ "京能(赤峰)能源发展有限公司_电力英才网". EP Job 88. 2007. Retrieved 2021-05-26.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "关于京能(赤峰)能源发展有限公司赤峰煤矸石电厂2×135MW机组新建工程项目职业病危害控制效果评价报告书评审申请的批复_mg老虎机技巧". Inner Mongolia Autonomous Region Health Committee. August 17, 2009. Retrieved 2021-05-26.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 3.0 3.1 "北京京能电力股份有限公司". Ying Jie Sheng. November 18, 2019. Retrieved 2021-05-26.
{{cite web}}
: CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.