Delong Nickel Phase IV power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Delong Nickel Phase IV power station is an operating power station of at least 330-megawatts (MW) in Morowali Regency, Central Sulawesi, Indonesia with multiple units, some of which are not currently operating. It is also known as 印尼德龙四期.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Delong Nickel Phase IV power station Morowali Regency, Central Sulawesi, Indonesia -2.014, 121.431 (approximate)

The map below shows the approximate location of the power station.

Loading map...


Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year
Unit 2 Construction[1] coal: unknown 330[1] unknown
Unit 3 Operating[2] coal: unknown 330[2] unknown 2024[2]

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 2 PT Nadesico Nickel Industry CNGR Advanced Material Co Ltd; Jiangsu Delong Nickel Industry Co Ltd
Unit 3 PT Nadesico Nickel Industry CNGR Advanced Material Co Ltd; Jiangsu Delong Nickel Industry Co Ltd

Background

In March 2023, Zhongwei New Materials and Delong Nickel Industry jointly established PT Nadesico Nickel Industry (PT NNI). PT NNI was planned to build a Delong Nickel Phase IV project in Indonesia, with a designed annual production capacity of 80,000 tons. The project would include the construction of a 2 x 330 MW captive coal-fired power station.[3] The power station's two units appeared to be referred to as Unit 2 and Unit 3.

In late March 2023, an on-site kickoff meeting was held.[4]

In March 2024, the power station was under construction.[5]

In June 2024, Unit 3 was successfully connected to the grid.[6]

In September 2024, Unit 3 passed its trial operation period.[7]

In October 2024, construction of Unit 2 was ongoing.[8]

Articles and Resources

References

  1. 1.0 1.1 https://www.51bxg.com/news/coil/1728347943343056.html. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 2.2 https://bxg.m.mysteel.com/a/24091414/1CD6F4220DB837AC_abc.html. {{cite web}}: Missing or empty |title= (help)
  3. 一年一度镍业大典 55 页深度(2024 版), Haitong International, July 24, 2024
  4. 印尼德龙四期2×300MW项目汽机房动、静设备单元开工会, 陕西西北火电工程有限公司, March 22, 2023
  5. 印尼德龙四期2×330MW项目#3机组蒸汽吹管顺利完成, bxg.m.mysteel, March 30, 2024
  6. 印尼德龙四期2×330MW项目#3机组并网发电, cnfeol, June 3, 2024
  7. 印尼德龙四期2×330MW项目#3机组168小时试运圆满完成, bxg.m.mysteel, September 12, 2024
  8. 印尼德龙四期2×330MW项目#2机组发电机穿转子, 51bxg, October 8, 2024

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.