Delong Nickel Phase IV power station
From Global Energy Monitor
Background
In March 2023, Zhongwei New Materials and Delong Nickel Industry jointly established PT Nadesico Nickel Industry (PT NNI). PT NNI was planned to build a Delong Nickel Phase IV project in Indonesia, with a designed annual production capacity of 80,000 tons. The project would include the construction of a 2 x 330 MW captive coal-fired power station.[1] The power station's two units appeared to be referred to as Unit 2 and Unit 3.
In late March 2023, an on-site kickoff meeting was held.[2]
In March 2024, the power station was under construction.[3]
In June 2024, Unit 3 was successfully connected to the grid.[4]
In September 2024, Unit 3 passed its trial operation period.[5]
In October 2024, construction of Unit 2 was ongoing.[6]
- ↑ 一年一度镍业大典 55 页深度(2024 版), Haitong International, July 24, 2024
- ↑ 印尼德龙四期2×300MW项目汽机房动、静设备单元开工会, 陕西西北火电工程有限公司, March 22, 2023
- ↑ 印尼德龙四期2×330MW项目#3机组蒸汽吹管顺利完成, bxg.m.mysteel, March 30, 2024
- ↑ 印尼德龙四期2×330MW项目#3机组并网发电, cnfeol, June 3, 2024
- ↑ 印尼德龙四期2×330MW项目#3机组168小时试运圆满完成, bxg.m.mysteel, September 12, 2024
- ↑ 印尼德龙四期2×330MW项目#2机组发电机穿转子, 51bxg, October 8, 2024