Delong Nickel Phase IV power station

From Global Energy Monitor

Background

In March 2023, Zhongwei New Materials and Delong Nickel Industry jointly established PT Nadesico Nickel Industry (PT NNI). PT NNI was planned to build a Delong Nickel Phase IV project in Indonesia, with a designed annual production capacity of 80,000 tons. The project would include the construction of a 2 x 330 MW captive coal-fired power station.[1] The power station's two units appeared to be referred to as Unit 2 and Unit 3.

In late March 2023, an on-site kickoff meeting was held.[2]

In March 2024, the power station was under construction.[3]

In June 2024, Unit 3 was successfully connected to the grid.[4]

In September 2024, Unit 3 passed its trial operation period.[5]

In October 2024, construction of Unit 2 was ongoing.[6]