Durgapur II Coal Mine is a proposed coal mine in Raigarh, Chhattisgarh, India.
Location
Table 1: Project-level location details
Mine Name | Location | Coordinates (WGS 84) |
---|---|---|
Durgapur II Coal Mine | Raigarh, Chhattisgarh, India | 22.4333333, 83.1411111 (exact) |
The map below shows the exact location of the coal mine:
Project Details
Table 2: Project status
Status | Status Detail | Project Type | Opening Year | Closing Year |
---|---|---|---|---|
Proposed | Pre-Permit | New | – | – |
Table 3: Operation details
Capacity (Mtpa) | Production (Mtpa) | Year of Production | Mine Type | Mining Method | Mine Size (km2) | Mine Depth (m) | Workforce Size |
---|---|---|---|---|---|---|---|
4 | – | – | Underground & Surface | Mixed | – | 60* | * |
Table 4: Coal resources and destination
Total Reserves (Mt) | Year of Total Reserves Recorded | Total Resources (Mt) | Coalfield | Coal Type | Coal Grade | Primary Consumer/ Destination |
---|---|---|---|---|---|---|
70.12 | – | 96.9 | – | Subbituminous | Thermal | – |
Table 5: Ownership and parent company
Owner | Parent Company | Headquarters |
---|---|---|
South Eastern Coalfields Ltd | Coal India Ltd [100.0%] | India |
Note: The above section was automatically generated and is based on data from the Global Coal Mine Tracker April 2024 release and the September supplement.
Background on Mine
The Durgapur II Taraimar coal mine project proposed a 3 million tonnes per annum opencast and 1 million tonnes per annum underground mine on a lease area of 1070 ha is located in villages Taraimar, Bayasi Basti, Bayasi Colony, Dharma Colony, and Rupunga, Tehsil Dharamjaigarh, District Raigarh, State Chhattisgarh, India.
The mine was first allocated to Bharat Aluminium ompany Limited for establishing the coal mine and a captive coal washery of 4 MTPA to meet the coal requirements of 1110 MW linked Thermal Power Plants (810 MW existing +300MW proposed) at Korba. The project secured the environment clearance for its development on 24 May 2012. [1]
The coal mine was cancelled by the Supreme Court on 24 September 2014 in the wake of coalgate scandal.[2] The mine was listed for auction by the Ministry of coal in December 2019. Karnataka Power Corporation Limited and Goa Industrial Development Corporation Limited posted their bid for the mine. However, the mine was not allotted due to tepid response.[3]
Expansion Details
- Status:
- Size of Expansion:
- Permits and Applications:
Articles and Resources
Additional data
To access additional data, including an interactive map of world coal mines, a downloadable dataset, and summary data, please visit the Global Coal Mine Tracker on the Global Energy Monitor website.
References
- ↑ Environment Clearance for Durgapur II Taraimar coal mine Project, MoEF&CC India, 24 May, 2012
- ↑ Order of the Supreme Court of India regarding allocation of coal blocks, 24/09/2014, India Environment Portal, 24 Septembr 2014, acccessed on April 7, 2020
- ↑ 6 New coal mines allocated, will generate Rs 15,000 Cr revenue: Ministry, 15 December, 2019; Indus Dictum site accessed on April 7, 2020