Duyen Hai Power Generation Complex
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Duyen Hai Power Generation Complex is an operating power station of at least 4378-megawatts (MW) in Dan Thanh, Duhen Hai, Tra Vinh, Vietnam.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Duyen Hai Power Generation Complex | Dan Thanh, Duhen Hai, Tra Vinh, Vietnam | 9.58517, 106.52809 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Unit 1-1, Unit 1-2, Unit 2-1, Unit 2-2, Unit 3 Extension, Unit 3-1, Unit 3-2: 9.58517, 106.52809
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Unit 1-1 | operating | coal: bituminous | 622.5 | subcritical | 2015 |
Unit 1-2 | operating | coal: bituminous | 622.5 | subcritical | 2015 |
Unit 2-1 | operating | coal: bituminous | 600 | unknown | 2021 |
Unit 2-2 | operating | coal: bituminous | 600 | unknown | 2021 |
Unit 3 Extension | operating | coal: unknown | 688 | supercritical | 2020 |
Unit 3-1 | operating | coal: bituminous | 622.5 | supercritical | 2017 |
Unit 3-2 | operating | coal: bituminous | 622.5 | supercritical | 2017 |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Unit 1-1 | Vietnam Electricity LLC [100%] | Vietnam Electricity LLC [100.0%] |
Unit 1-2 | Vietnam Electricity LLC [100%] | Vietnam Electricity LLC [100.0%] |
Unit 2-1 | Malakoff Technical Solutions Sdn Bhd [100%] | Malakoff Corporation Bhd [100.0%] |
Unit 2-2 | Malakoff Technical Solutions Sdn Bhd [100%] | Malakoff Corporation Bhd [100.0%] |
Unit 3 Extension | Vietnam Electricity LLC [100%] | Vietnam Electricity LLC [100.0%] |
Unit 3-1 | Vietnam Electricity LLC [100%] | Vietnam Electricity LLC [100.0%] |
Unit 3-2 | Vietnam Electricity LLC [100%] | Vietnam Electricity LLC [100.0%] |
Project-level coal details
- Coal source(s): imported
Background
The planned power plant complex would be made up of three separate coal-fired power plants: Duyên Hải 1, 2, and 3. The first two are made up of two units each, and the third is made up of three units.
In April 2013, construction began on a US$280 million coal seaport, the Duyen Hai coal port, for the power complex. The seaport is being built by China Communications Construction, and is expected to be completed in late 2015; it will be capable of handling 12 million tons of coal per year for consumption at the complex's three power plants.[1]
Duyên Hải-1
The 1,245-MW Duyên Hải-1 is a project of Vietnam Electricity Group (the successor company of the state-owned power monopoly). The construction contractor is the Chinese company Dongfeng Group, and the plant will cost $1.6 billion. Duyên Hải-1 broke ground in Sept. 2010.[2] The two 622-MW units are both expected to enter service in July 2015.[3]
Unit 1 was successfully brought online in January 2015,[4] and Unit 2 in April 2015.[5] The plant entered into commercial operation in June 2015.[6]
(The revised Power Development Plan VII lists Unit 1 at 600 MW with an operating year of 2014, and Unit 2 at 600 MW with an operating year of 2015.)[7]
Financing for Duyên Hải-1
In October 2011, financing for Duyên Hải-1 was closed. US$1.08 billion in loans was provided by Société Générale, BNP Paribas, Bank of China, Industrial and Commercial Bank of China, and China ExIm Bank.[8]
Duyên Hải-2
The 1,200-MW Duyên Hải-2 is a project of the Malaysian company Teknik Janakuasa, a subsidiary of the MMC Corporation Berhad, and will cost $2.2 billion.[9] In April 2011, Janakuasa signed Chinese company Huadian Engineering to take the lead in construction.[10] In 2009, Janakuasa stated that construction would begin in 2010-11, and the plant would be completed in 2014; however, several years of delays apparently followed.
In December 2014, Janakuasa and the Vietnamese government reached preliminary agreement on a build-operate-transfer (BOT) contract to build the plant. The project still needs an investment license to proceed. The current plan is for completion in 2020.[11]
Duyên Hải-2 was permitted in September 2015. Alstom will join Teknik Janakuasa as the main equipment supplier.[12]
Construction of Duyên Hải-2 began in August 2016. It would cover an area of 60 hectares and was estimated at US$2.2 billion. It was planned for operation in 2021.[13]
In June 2019, the completion date for Unit 2 was delayed to 2022 in the Ministry Of Industry And Trade's report on the implementation of the revised seventh Power Development Plan (PDP7).[14]
In February 2020, the National Steering Committee on power development reported that construction was 58.71% complete and that Unit 1 was scheduled to be commissioned in June 2021 and Unit 2 in September 2021.[15]
On March 6, 2020, it was reported that construction of Duyên Hải-2 would be impacted by COVID-19 and that its estimated completion date of 2021 might be delayed.[16] In May 2020, it was reported that foreign workers for the plant were not being permitted to enter Vietnam from China due to Covid-19-related travel restrictions.[17]
In July 2020, the project was reported to be 79.58% complete.[18] In August 2021, it was reported that Unit 1 was commissioned in June 2021 and that Unit 2 had begun trial operations.[19] Unit 2 was commissioned in December 2021.[20]
In April 2024, Janakuasa signed an operation and maintenance contract with PECC2 for the remaining lifetime of Duyên Hải-2.[21]
Financing for Duyên Hải-2
In June 2017, a US$1,760 million loan agreement was closed to finance the 1200-MW project. The loans will be provided by China Exim Bank and ICBC.[22]
Duyên Hải-3 (2 x 622.5 MW) and Duyên Hải-3 Extension (660 MW)
The 1,245-MW Duyên Hải-3 is a project of Electricity of Vietnam (EVN). In August 2011, the engineering, procurement, and construction (EPC) contract for Units 1 & 2 was awarded to a consortium of Chinese companies: Chengda Engineering, Dongfang Electric Corporation, the Southwest Electric Power Design Institute (SWEPDI) (a subsidiary of the China Energy Engineering Group), and Zhejiang Electric Power Construction. The project will cost $1.5 billion, and initial preparation work began in Sept. 2010. [23][24] Construction began in December 2012.[25] Completion of Unit 1 is scheduled for Q4 2015, and Unit 2 for Q2 2016.
In November 2014, the EPC contract was signed between EVN and Sumitomo Corporation for construction of the 660-MW, $890 million coal-fired Unit 3 of Duyên Hải-3 (called "Duyên Hải-3 Extension"). Construction began in December, and is scheduled to be completed by June 2018.[26][27]
In March 2015, the Japan Bank for International Cooperation (JBIC) approved a US$410 million loan for the Duyên Hải-3 expansion.[28] Additionally, a group of 10 private banks - Sumitomo Mitsui Trust Holdings, Sumitomo Mitsui Banking Corporation, Gunma Bank, Joyo Bank, Hyakugo Bank, Iyo Bank, Chiba Bank, Bank of Fukuoka, Bank of Kyoto, and Hachijuni Bank - provided US$273.27 million in loans. Electricity of Vietnam Group (EVN) provided US$398.83 million in equity.[29] The financing provided by the private banks was insured by Nippon Export and Investment Insurance.[30]
Also in March 2015, Toshiba Corporation announced that it had been contracted to provide the turbine for Unit 3.[31] In May 2015, Sumitomo contracted Black & Veatch as project technical lead in May 2015.[32]
In April 2015, state utility Vietnam Electricity Group secured a syndicated loan worth US$214 million for Duyen Hai 3 from three domestic lenders: VietinBank, BIDV, and Vietcombank.[33]
The revised Power Development Plan VII lists Phase 3 Unit 1 at 600 MW with a 2016 completion date, Unit 2 at 600 MW with a 2017 completion, and the Extension at 660 MW with a completion of 2019.[7]
Commissioning of unit 1 began in September 2016, with full operation planned by December 2016.[34] Trial operation began December 2016.[35]
Unit 1 entered commercial operation in March 2017, and Unit 2 in April 2017.[36] A completion date for the extension unit is unknown.
Duyên Hải-3 Extension will use supercritical combustion technology.[37]
In March 2018 a fire broke out at the unit 3 construction site and destroyed 70% of a flue gas desulfurisation tower that was under construction.[38]
In August 2018 an audit of the Duyên Hải-3 project found that EVN had underestimated the project's cost by 8.8 billion Vietnamese Dong (VND).[39]
Duyên Hải-3 Extension began test operations in November 2019[40] and was scheduled to be commissioned in Q1 2020.[41] Duyên Hải-3 Extension was commissioned in May 2020.[42]
As of December 2022, Duyên Hải-3 was experiencing chronic shutdowns and standby periods.[43] In October 2023, an overhaul of Duyên Hải-3 Unit 2 was completed.[44]
Environmental Impact
78 households were resettled to the nearby Mu U Resettlement area in 2010 to make room for the plant — but severe land erosion caused by the loss of sand dunes that have been removed to build the coal port means that the land that people have been resettled to now regularly becomes flooded. Local residents' protests to government officials have led to a plan to resettle these impacted residents again, to the Con Trung Resettlement Area. Many families in the area report that they are unable to grow anything without the protection of the sand dunes, and that their land has become worthless with the repeated flooding.[45]
In May 2017, Politburo member Nguyễn Thiện Nhân visited the Duyen Hai plant. While stating its importance for the regional economy, he also acknowledged that local people were very concerned about the plant's environmental impact.[46]
In October 2022, Tra Vinh made a call for investments in five eco-tourism projects in the province. One project was the 368-hectare Bien Ba Dong tourism complex, which would border the Duyen Hai Power Generation Complex.[47]
Opposition
Since 2011, the communities around the Duyen Hai Power Station in Tra Vinh province of Vietnam’s Mekong Delta complained about the effect of the coal plants on their poor resettlements. In 2014, it was reported that many people living near the Duyen Hai coal plants “are unable to grow anything” because the coal plant has affected the sand dunes, increasing landslides and soil erosion. Multiple villagers are not earning enough money to sustain themselves and express great concern and anxiety over the effects of the coal plant.[48]
Starting in 2015, villagers near the Duyen Hai power plant expressed worries over black smoke, slag dust, and discharging water into the sea. In 2017, after two years of environmental issues, villagers told Nguyen Thein Nhan, Secretary of Ho Chi Minh City Party Committee, about their concerns. He responded that the coal plant is still important to the electricity of the local Mekong Delta, but he acknowledged the environmental concerns.[49]
In 2018, a report on how villagers still suffer from coal ash and dust from the Duyen Hai power plants was released by the Straits Times. Villagers expressed unhappiness over the rising air pollution and the government’s push for coal-fired power plants. Farmers and fisherman complain about lack of agriculture and produce. Environmental groups express concern over Vietnam’s advancement of coal plants, citing that Vietnam may become dependent on foreign, imported coal.[50]
In May 2019, environmentalist groups, such as Unfriend Coal, released a report around how Talanx needs to stop investing and insuring coal plants, including the Duyen Hai power plant. The report explained that the coal plant resulted in “78 households being relocated to an area which regularly floods” and is bad for farming or fishing.[51]
Articles and Resources
References
- ↑ Construction Starts on Duyen Hai Seaport, Viêt Nam News, April 22, 2013.
- ↑ "New thermal power plant built in Tra Vinh", Vietnam Business Register, accessed Jan. 2014.
- ↑ Dong, Minh. Starting Pouring the First Concrete Batch for Gas Furnace of Duyen Hai 1 Thermal Power Plant, Trà Vinh provincial website, accessed Jan. 2014.
- ↑ The unit # 1 of the Duyen Hai 1 Thermal Power Plant (TPP) has synchronized to the National Power System, Vietnam Energy, 4 Feb. 2015.
- ↑ Tổ máy 2 của Nhà máy điện Duyên Hải 1 hòa vào lưới điện quốc gia, Vietnam+, 1 May 2015.
- ↑ Nhiệt điện Duyên Hải 1: Sẽ vận hành thương mại trong tháng 6/2015, Bao Cong Thuong, 24 May 2015.
- ↑ 7.0 7.1 DANH MỤC CÁC DỰ ÁN NGUỒN ĐIỆN VÀO VẬN HÀNH GIAI ĐOẠN 2016 - 2030, Ban hành kèm theo Quyết định số 428/QĐ-TTg ngày 18 tháng 3 năm 2016 của Thủ tướng Chính phủ (LIST OF POWER PROJECT IN OPERATION PERIOD 2016 - 2030, Issued together with Decision No. 428 / QD - TTg of March 18, 2016 by the Prime Minister)
- ↑ "EVN signs Duyen Hai debt | News | IJGlobal". ijglobal.com. Retrieved 2020-12-17.
- ↑ "Power plant project signs on consultant", Viêt Nam News, Jan. 8, 2009.
- ↑ Công ty Huadian Engineering của Trung Quốc đã hỗ trợ Janakasa tới 1,59 tỷ USD để thực hiện dự án này, Cafe F, April 20, 2011.
- ↑ Malaysia's Janakuasa, Vietnam reach deal on 1,200 MW power plant, Reuters UK, 26 Dec. 2014.
- ↑ "Malaysia’s Teknik Janakuasa gets nod to build $2bn power plant in Vietnam," Tuoi Tre News, 09/29/2015
- ↑ "Work begins on Duyen Hai 2 thermal power plant," Vinacomin, 05/08/2016
- ↑ Implementation of Power Projects iIn the Revised Power Development Plan 7, Ministry of Industry and Trade, Republic of Vietnam, Jun. 4, 2019
- ↑ Tình hình thực hiện các dự án điện theo hình thức BOT ở Việt Nam, Feb. 14, 2020
- ↑ Hiep Thanh Wind Power project: deadline well within reach, Energy Central, Mar. 6, 2020
- ↑ Covid-19 tác động tới tiến độ nhiều dự án điện, Bao Dau Thau, May 6, 2020
- ↑ Thanh Hương, Dự án BOT điện mãi không chạm đích, Vietnam Finance, Jul. 12, 2020
- ↑ Nhiều dự án nguồn điện lớn bế tắc, Dautu, Aug. 13, 2021
- ↑ 越南沿海二期2×660MW燃煤电厂项目2号机组顺利通过168小时试运行, BJX, Dec. 14, 2021
- ↑ Ký hợp đồng vận hành và bảo trì Nhà máy Nhiệt điện Duyên Hải 2, Năng lượng Việt Nam, April 10, 2024
- ↑ "Preview of Duyen Hai 2 Thermal Power Plant (1200MW) PPP | Transaction | IJGlobal". ijglobal.com. Retrieved 2020-09-23.
- ↑ Chinese Firms Get $1.3 bln Power Plant Deal in Vietnam, Reuters, Aug. 5, 2011.
- ↑ EPC contract signing ceremony of Duyen Hai 3 power plant, EVN press release, 12 Aug. 2011.
- ↑ Starting construction of Duyen Hai 3 Thermal Power Plant, Tra Vinh Provincial Government press release, 18 Dec. 2012.
- ↑ Construction begins on Duyen Hai 3 power plant extension, Vietnam+, 13 Dec. 2014.
- ↑ Signing EPC Contract for Duyen Hai 3 Power Thermal Plant Extension Project, Vietnam Energy, 27 Nov. 2014.
- ↑ "List of Coal Power Plants funded by JBIC (2003-2015)," Sekitan, April 2015
- ↑ "Preview of Duyen Hai 3 Coal-Fired Power Plant Expansion (688MW) | Transaction | IJGlobal". ijglobal.com. Retrieved 2020-11-30.
- ↑ Buyer's Credit to Vietnam Electricity (EVN), Japan Bank for International Cooperation, Mar. 31, 2015
- ↑ Toshiba to Supply Steam Turbine and Generator for Duyen Hai 3 Extension Coal-fired Power Plant in Vietnam, Toshiba press release, 16 Mar. 2015.
- ↑ Black & Veatch secures role on Vietnam EPC power project expansion, Black & Veatch press release, 4 May 2015.
- ↑ "Deal signed on Mekong power plant". vietnamnews.vn. Retrieved 2020-11-30.
- ↑ "Turbine of Duyen Hai 3 thermal power plant joins national grid," Vietnam Pictorial, 19/09/2016
- ↑ "Duyen Hai power plant produces 5.9 billion kWh of electricity," Vietnam Net, Dec 28, 2016
- ↑ Toàn bộ Nhà máy Nhiệt điện Duyên Hải 3 đã được vận hành, VnMedia, 17 Apr. 2017.
- ↑ "Order Received for construction of Duyen Hai 3 Extension Coal-fired Power Plant (1 x 688MW) from Vietnamese State-run Power Company," Sumitomo Company press release, 26 November 2014
- ↑ Power plant fire allegedly caused by human error, Viet Nam News, Mar. 9, 2018
- ↑ Kiến nghị xử lý 2.000 tỷ đồng tại dự án nhiệt điện lớn nhất ĐBSCL, VN Express, Aug. 16, 2018
- ↑ EVNGENCO1 hoàn thành vượt mức kế hoạch sản lượng năm 2019, Evengenco, Dec. 31, 2019
- ↑ Tổng công ty Phát điện 1: Hoàn thành các chỉ tiêu, Cong Thuong, Jan. 21, 2020
- ↑ Nhiệt điện Duyên Hải 3 được đưa vào vận hành thương mại, Thanh Mien, May 11, 2020
- ↑ Nhiệt điện Duyên Hải nỗ lực vượt khó, hoàn thành nhiệm vụ năm 2022, Công ty Nhiệt điện Duyên Hải, December 31, 2022
- ↑ Hoàn thành công tác đại tu Tổ máy số 2 - Nhà máy Nhiệt điện Duyên Hải 3, Công ty Nhiệt điện Duyên Hải, October 26, 2023
- ↑ Hoang Duong, Coal-power complex brings misery and ecological risk to local people in Vietnam’s Mekong Delta, Mekong Commons, 2 Nov. 2014.
- ↑ Ông Nguyễn Thiện Nhân kiểm tra nhà máy Nhiệt điện Duyên Hải, Zing.vn, 12 May 2017.
- ↑ Tra Vinh calls for $116 mln investment in eco-tourism projects, The Investor, October 18, 2022
- ↑ “Coal-power complex brings misery and ecological risk to local people in Vietnam’s Mekong Delta”, Mekong Commons, November 2, 2014.
- ↑ “Mr. Nguyen Thien Nhan checked Duyan Hai Thermal Power Plant”, Zing News, Translated by Google, December 5, 2017.
- ↑ “Living in the shadow of a coal-fired power plant”, The Straits Times, November 25, 2018.
- ↑ “Talanx: Seriously Clearing Up or Silently Continuing Support for Coal?”, Urgewald, May 2019.
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.