Efeler Gürmat-2 geothermal power plant

From Global Energy Monitor
This article is part of the
Global Geothermal Power Tracker, a Global Energy Monitor project.
Report an error

Efeler Gürmat-2 geothermal power plant is an operating geothermal power plant in İncirliova, Aydin, Türkiye.

Project Details

Table 1: Unit-level project details for Efeler Gürmat-2 geothermal power plant

Unit name Status Commissioning year Nameplate capacity Technology Owner Operator
1 Operating[1] 2014[1] 47 MW[1] Flash steam - double[1] Mogan Enerji Yatirim Holding [100%][2] Güriş Inşaat ve Muhendislik; Mr. Müsfik Hamdi Yamantürk; Mogan Enerji Yatirim Holding; Gurenerji Elektrik Uretim; Güriş Holding AS[1][2][1][2][1][2][1][2][1][2]
8 Operating[2] 2021[2] 50 MW[2] Binary cycle[3] Mogan Enerji Yatirim Holding [100%][2] Güriş Inşaat ve Muhendislik; Mr. Müsfik Hamdi Yamantürk; Mogan Enerji Yatirim Holding; Gurenerji Elektrik Uretim; Güriş Holding AS[1][2][1][2][1][2][1][2][1][2]

Location

Table 2: Unit-level location details for Efeler Gürmat-2 geothermal power plant

Unit name Location Coordinates (WGS 84)
1 İncirliova, Aydin, Türkiye 37.8674, 27.6477 (exact)
8 İncirliova, Aydin, Türkiye 37.8644, 27.6441 (exact)

The map below shows the exact locations of the geothermal power plant units:

Loading map...

Articles and Resources

Additional data

To access additional data, including an interactive map of global geothermal power plants, a downloadable dataset, and summary data, please visit the Global Geothermal Power Tracker on the Global Energy Monitor website.

References

  1. 1.00 1.01 1.02 1.03 1.04 1.05 1.06 1.07 1.08 1.09 1.10 1.11 1.12 1.13 https://web.archive.org/web/20220519175153/https://www.nsenergybusiness.com/projects/efeler-geothermal-power-plant/. Archived from the original on 19 May 2022. {{cite web}}: Missing or empty |title= (help)
  2. 2.00 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 2.10 2.11 2.12 2.13 2.14 https://web.archive.org/web/20220813163808/https://www.thinkgeoenergy.com/50-mw-efeler-8-geothermal-power-plant-comes-online-in-aydin-turkey/. Archived from the original on 13 August 2022. {{cite web}}: Missing or empty |title= (help)