Ekibastuz-2 power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Ekibastuz-2 power station (Экибастузская ГРЭС-2) is an operating power station of at least 1000-megawatts (MW) in Ekibastuz, Pavlodar, Kazakhstan with multiple units, some of which are not currently operating. It is also known as GRES-2 power station.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Ekibastuz-2 power station | Ekibastuz, Ekibastuz, Pavlodar, Kazakhstan | 52.023972, 75.47625 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2, Unit 3, Unit 4, Unit 5, Unit 6: 52.023972, 75.47625
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Unit 1 | operating | coal: bituminous | 500 | supercritical | 1990 |
Unit 2 | operating | coal: bituminous | 500 | supercritical | 1993 |
Unit 3 | pre-permit | coal: bituminous | 636 | supercritical | 2027 (planned)[1] |
Unit 4 | pre-permit[1] | coal: bituminous | 636 | supercritical | 2029 (planned)[1] |
Unit 5 | shelved[2] | coal: bituminous | 636 | supercritical | 2029 (planned) |
Unit 6 | shelved[2] | coal: bituminous | 636 | supercritical | 2030 (planned) |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Unit 1 | Ekibastuz GRES-2 JSC [100%] | Samruk-Energo JSC [50.0%]; Samruk-Kazyna SWF JSC [50.0%] |
Unit 2 | Ekibastuz GRES-2 JSC [100%] | Samruk-Energo JSC [50.0%]; Samruk-Kazyna SWF JSC [50.0%] |
Unit 3 | Ekibastuz GRES-2 JSC [100%] | Samruk-Energo JSC [50.0%]; Samruk-Kazyna SWF JSC [50.0%] |
Unit 4 | Ekibastuz GRES-2 JSC [100%] | Samruk-Energo JSC [50.0%]; Samruk-Kazyna SWF JSC [50.0%] |
Unit 5 | Ekibastuz GRES-2 JSC [100%] | Samruk-Energo JSC [50.0%]; Samruk-Kazyna SWF JSC [50.0%] |
Unit 6 | Ekibastuz GRES-2 JSC [100%] | Samruk-Energo JSC [50.0%]; Samruk-Kazyna SWF JSC [50.0%] |
Project-level coal details
- Coal source(s): Ekibastuz coal basin
Background
The Ekibastuz GRES-2 Power Station is a coal-fuelled power generating station in Ekibastuz, Kazakhstan. The station has installed capacity of 1,000 MW, provided by two units of 500 MW each.
Ekibastuz-2 was part a coal-fired complex that included Ekibastuz-1 power station. The construction project was never finished, with only ten of 16 planned power units completed. Only two 500MW units at the Ekibastuz GRES-2 Power Station were commissioned (in 1990 and 1993). After that, construction was suspended.[3]
The plant produced 6433 million kWh in 2021[4] and 6002 million kWh in 2022.[5]
Ownership
At the end of 2005 a joint venture between INTER RAO UES JSC and Samruk-Energo JSC was established to operate the GRES-2 Power Station. Its shareholders proposed overhauling existing units and building new ones. In July 2019, Samruk-Kazyna bought Inter RAO's 50% share in the plant.[6] The plant is therefore 50% owned by Samruk-Energy and 50% by Samruk Kazyna. Samruk-Energy is fully owned by Samruk Kazyna.
Expansion & delays
Proposed Unit 3 (500 MW)
Construction of Unit 3 was started in 1990 but later stopped. A 500 MW power unit N3 was then planned to be built in 2008-2009, but also stopped.[7]
In 2010, an agreement to build a third unit at the power plant was reached at a meeting of the Presidents of Kazakhstan and Russia,[8] and the agreement was ratified in January 2011. The project was to be 500 MW at a projected cost of US$770 million. The new capacity was to come online by 2013, with all the additional output to be supplied to Russia. The project cost would be co-funded with a US$700 million loan from Vneshekonombank of Russia and the Eurasian Bank of Kazakhstan.[9]
In January 2014, Russia and China signed an agreement to lend US$400 million for construction of a third electric power generation block at the power station, which matched the deal they first ratified in January 2011.[8]
In March 2014, it was reported that the Inter RAO UES (Inter RAO) and Government of Kazakhstan were planning to undertake the 500 MW power plant expansion, with a project start date of mid-2015 and completion date of 2018.[10] Building and installation works on the unit began that year.[11] However it appears that works did not progress. In April 2018, it was reported that work on the new unit had stalled but resumed in 2018.[12]
Proposed Unit 3 (636 MW)
With the power plant becoming fully owned by Kazakhstan in 2019, Samruk Energy resumed the project with increased capacity of 636MW. In June 2021, reporting noted that construction would not begin until 2023, with the expected commissioning date pushed back to December 2025.[3][13] In September 2021, Samruk Energy stated that for the period of 2020 and the first half of 2021, within the framework of the implementation of the project, a wide range of preparatory work had been carried out. Work included financial and technical audits, refinancing of loan obligations before conclusion of contracts for the adjustment of design estimates, and registration of permits for construction. Additionally, more than 11 tonnes of equipment have so far been delivered to the construction site. Construction has not begun, but the project is expected to be commissioned in 2025.[14]
As of December 2021, Inter Rao Engineering was expected to render EPC services for the expansion. Harbin Electric was expected to be the turbine supplier (1 unit of CLN-636-24.2/566/566 steam turbine with 636MW nameplate capacity). Harbin Electric was also the expected supplier of QFSN3-2 electric generator and the likely supplier of the steam boiler.[15] In its 2021 annual report, Samruk-Energy stated that the approval of the project by Gosekspertiza (State Technical Supervision Authority) was expected by the end of 2021.[4] Environmental impact assessment was published in 2021, and it appeared that public consultation took place in June 2021.[16][4] However in March 2023 it was reported that public consultation would be carried out in March 2023.[17]
In March 2023, it was announced that China Machinery Engineering Corporation (CMEC) together with Samruk-Kazyna are working on a project to build two units (Unit 3 and the additional Unit 4, see below). A memorandum of cooperation was signed already in September 2022, according to one media report.[17] According to the memorandum, CMEC has to develop a timeline, a plan to supply equipment and project execution plan. The expected commissioning of Unit 3 was still foreseen in 2025.[17][18] In May 2023, repeated public hearings of the project took place.[19]
In its 2022 annual report released in spring 2023, Samruk Energy reported that during 2022, 28% of equipment from Kvarts LLP (China) was delivered to the plant, as per mediation agreement concluded in 2021 (it was not clear what the mediation agreement referred to, presumably to previous arrangements). Moreover, negotiations were conducted with Harbin Erantex Technology for shipment and repackaging of equipment to Harbin. An agreement was also signed in 2022 for the construction of hangars, with construction works ongoing at the end of 2022.[20] Investment plan showed that the company spent 10bn tenge on the project in 2022, and plans to spend 6bn tenge in 2023 and 49.5bn tenge in 2024.[21]
In the H1 2023 report, Samruk Energy stated that in May 2023, shipment of 70% of Unit-3 project equipment from China was completed.[22] Another source from October 2023 stated that 53% of the total amount of equipment from China (7,782 tonnes) have been delivered to GRES-2, another 22.6% (1760 tonnes) are on the way. Another 1,874 tonnes (24.1%) of equipment was still located in China. A corresponding investment agreement has been signed on the part of the Ministry of Energy.[23] The project cost of 441bn tenge, with planned commissioning now in December 2026.[23]
In December 2023, it was reported that additional agreements were reached between Samruk Energy and a Russian company ORGRES LLC for the construction of power units No. 3 and No. 4, utilizing Russian equipment.[24][25] Samruk Energy reported in January 2024 that as China cannot be involved in construction of coal-fired generation, an option to implement the project using Russian equipment with preferential financing from Russian financial institutions was being explored. Planned activities for 2024 included obtaining decisions from a financial institution on the loan (March 2024), conclusion of the EPC contract for Units 3 and 4 (March-April 2024), while commissioning of Unit 3 was now pushed to 2027.[26] The report further stated that the Chinese equipment previously delivered for Unit 3 will now be used for Ekibastuz-3 power station.[26]
LLC ORGRES reported on its website that the company will supply main and auxiliary equipment, perform commissioning and auxiliary services (installation supervision, commissioning supervision), and also partially carry out construction and installation work, for both Units 3 and 4.[27]
In February 2024, the prosecutor's office of the Pavlodar region revealed embezzlement of funds allocated for Unit 3 expansion of about 1 billion tenge (ca US 2.2 million dollars).[28] An investigation was ongoing.
Another public consultation of Unit 3 project took place on 29 March 2024, but only with 13 participants present and with most of the participants related to the company (none from the general population).[29] The public consultation report also mentioned that in October 2023, Ekibastuz GRES LLC-2 signed an agreement with the Ministry of Energy on the unit's capacity tariff for 10 years (2027-2036).[29] 75% of equipment from China (or 7,800 tonnes) was said to be delivered to the plant, the rest (24%) remaining in China.[29]
The 2023 annual report of Samruk Energy published in June 2024 referred to recent project updates.[30] In December 2023, the feasibility study was submitted to Gosexpertiza. In January 2024, the investment proposal was submitted to the Market Council (the regulator of the electricity market in Kazakhstan). In February 2024, as part of the review of the application, a meeting on Carbon Capture and Storage was held with independent experts of the Market Council and the investment program was approved. The company was planning to send materials to the Ministry of Energy for conclusion of the investment agreement for return on investment.[30] This contradicted previous reporting from April 2024 that the investment agreement with the Ministry of Energy was already signed in October 2023.[29] The updated investment plan showed that very little was spent on the project in 2023, with 3.1 billion tenge planned to be spent in 2024 and 71 billion in 2025[30] (previous year's plan - 6 billion tenge expenditure in 2023 and 49.5 billion tenge in 2024[21]). It appeared that the final Investment agreement for Unit 3 with the Ministry of Energy was signed in September 2024.[31]
The 2023 report further mentioned that a 'potential transition to an alternative option for replacement of the main process equipment was being considered'.[30] (this presumably referred to the previous news that the equipment delivered from China will now be used at Ekibastuz-3 instead).[26]
In August 2024, EPC contract was signed to build Units 3 and 4 of 540MW each (lower than previously anticipated 636MW units) with a plan to commission Unit 3 now in 2028 and Unit 4 in 2030[32]. Company's reporting clarified that the EPC agreement is with TOO 'KBI Energy Group' (the leader of the consortium), TOO Stroyindustriya (design) and LLC 'ORGRES' (equipment supplier). All equipment will be supplied by Russia, including the boiler (Podolsky Machine Factory) and turbine and generator (Power Machines).[31][33] Approval from Gosekspertiza is expected to be received in Q1 2025 with construction start to follow shortly.[31]
Proposed Unit 4 (636 MW)
The memorandum signed with CMEC disclosed in the media in March 2023 also included the planned construction of Unit 4 with 636-660 MW of capacity.[17][18] Expected commissioning of Unit 4 was in 2027, as of early 2023.[34][35][36]
In July 2023, it was reported that CEEC China Power Engineering Consulting and local partners in Kazakhstan won a bid to take on the owner's engineer role for the expansion project.[37][38] This was presumably for Unit 4. As of December 2023, a tender was being conducted for the feasibility study of Unit 4.[39]
In December 2023, it was reported that an agreement was reached between Samruk Energy and Russian company ORGRES LLC for the construction of units No. 3 and No. 4, utilizing Russian equipment.[24][25] In January 2024, Samruk Energy said that the planned signing of the EPC contract for Unit 3 and 4 is in March-April 2024 and planned commissioning of Unit 4 is now in 2029.[26] ORGRES LLC reported on its website that the company will supply main and auxiliary equipment, perform commissioning and auxiliary services (installation supervision, commissioning supervision), and also partially carry out construction and installation work.[27]
As per above, the EPC contract for Unit 3 and 4 was signed in August 2024.
Proposed Units 5-6
In January and April 2023, additional Units 5 and 6 were announced, to be completed in 2029-2030.[34][40][36] There was no further news on these Units, as of January 2024, and the government order on the development of the power sector until 2035 issued in February 2024 did not mention new Units 5 and 6 (only Units 3 and 4).[41] It therefore appeared that plans for these units have been abandoned.
Financing
Unit 3 (2010): A loan agreement for Unit 3 was closed in July 2010. US$700 million in loans was provided by Vneshekonombank and the Eurasian Bank of Kazakhstan.[9] In October 2013, a second loan agreement for Unit 3 was closed. The China Development Bank agreed to provide a US$400 million loan.[42]
In 2020, Samruk-Energy reported that all outstanding loans in foreign currencies were refinanced by a loan in tenge from the National Bank of Kazakhstan for a total of over 100 billion tenge (ca USD 210m).[43] Therefore it appeared that there is no foreign bank financing anymore.
Unit 3 and 4 (Proposed): An industry article from October 2023 referred to the potential funding by Russia and Eurasian Bank of Development for Units 3 and 4.[44] In January 2024, Samruk Energy reported that in October 2023, preliminary indicative conditions for financing Units 3 and 4 in the amount of up to 205 billion rubles have been received. It was planned to obtain a decision on the loan in March 2024.[26] Reporting from August 2024 still referred to the planned concessional financing from Russian financial institutions based on subsidized interest rate as part of the export support program.[32]
Pollution ranking
The government decree from April 2022 ranked the Ekibastuz-2 GRES power plant as Number 3 in the list of the main polluters in Kazakhstan as of 2021. The government decree comes into force from 2025.[45] It is not clear what the purpose of the ranking is.
Articles and Resources
References
- ↑ 1.0 1.1 1.2 https://web.archive.org/web/20240218224702/https://inbusiness.kz/ru/news/kakie-krupnye-energoproekty-planiruyut-realizovat-v-kazahstane-do-2035-goda. Archived from the original on 18 February 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 2.0 2.1 (PDF) https://web.archive.org/web/20240417094445/https://www.gov.kz/uploads/2024/2/20/60845b9bf4f31194ae43ed12483269a5_original.241160.pdf. Archived from the original (PDF) on 17 April 2024.
{{cite web}}
: Missing or empty|title=
(help) - ↑ 3.0 3.1 "Строительство третьего энергоблока на Экибастузской ГРЭС-2 возобновляется," In Business, June 3, 2021
- ↑ 4.0 4.1 4.2 Samruk Energy. "2021 Annual Report" (PDF). Retrieved December 2022.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link) - ↑ "2022 Samruk Energy Annual Report" (PDF). www.samruk-energy.kz. 2023.
{{cite web}}
: CS1 maint: url-status (link) - ↑ ""Интер РАО" продает половину Экибастузской ГРЭС-2 за $20 млн". inbusiness.kz. July 2019. Retrieved December 2022.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link) - ↑ "Ekibastuz-2 power plant units plan will be ready soon," New Europe, January 12, 2007
- ↑ 8.0 8.1 "China and Russia to spend $400 million on Kazakhstan power plant," Tengri News, January 16, 2014
- ↑ 9.0 9.1 "Kazakh power plant signs $700m financing | News | IJGlobal". ijglobal.com. Retrieved 2020-11-16.
- ↑ "Inter RAO/GoK – Ekibastuz GRES-2 Power Plant Upgrade, Kazakhstan," World Construction Network, March 10, 2014.
- ↑ "2014 Annual Report," Samruk Energy, July 6, 2015
- ↑ "Construction of energy block N3 at Ekibastuz GRES-2 resumed," Kaztag, April 6, 2018
- ↑ "Что творится на казахстанском энергетическом долгострое, оставшемся без российских акционеров," Caravan, June 8, 2021
- ↑ "Сообщение для СМИ" (PDF). Samruk Energy. Sep 14, 2021. Retrieved Nov 17, 2021.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Ekibastuzskaya GRES-2 Expansion Power Plant, Kazakhstan". power-technology.com. December 2021.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Оценка воздействия на окружающую среду" (PDF). ovos.kz. 2021. Retrieved December 2022.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link) - ↑ 17.0 17.1 17.2 17.3 "Китайская компания сохраняет интерес к модернизации Экибастузской ГРЭС-2". https://kz.kursiv.media/. March 2023.
{{cite web}}
: External link in
(help)CS1 maint: url-status (link)|website=
- ↑ 18.0 18.1 "Китайская компания «сохраняет интерес» к строительству третьего энергоблока Экибастузской ГРЭС-2, которое планируется около 30 лет". rus.azattyq.org. March 2023.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Прошли повторные общественные слушания по проекту «Расширение и реконструкция Экибастузской ГРЭС-2 с установкой энергоблока ст. № 3»". gres2.kz. May 2023.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Samruk Energy 2022 Annual Report" (PDF). www.samruk-energy.kz. 2023.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 21.0 21.1 "Samruk Energy 2022 Annual Report" (PDF). www.samruk-energy.kz/. May 2023.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Результаты деятельности АО «Самрук-Энерго» за 1 полугодие 2023 года" (PDF). www.samruk-energy.kz. July 2023.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 23.0 23.1 "Дефицит заставит: правительство наделят правом договариваться о строительстве электростанций без проведения тендера". kz.kursiv.media. October 2023.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 24.0 24.1 "Media: Kazakhstan Signs Agreements with Russia for Construction of Three Combined Heat and Power Plants in the Country". https://russia-islworld.ru/. 23 December 2023.
{{cite web}}
: External link in
(help)CS1 maint: url-status (link)|website=
- ↑ 25.0 25.1 "Kazakhstan-Russia. Agreements in power sector". www.samruk-energy.kz/. January 2024.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 26.0 26.1 26.2 26.3 26.4 "Какие крупные энергопроекты планируют реализовать в Казахстане до 2035 года". inbusiness.kz. 16 January 2024.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 27.0 27.1 "Строительство энергоблоков № 3 и 4 Экибастузской ГРЭС-2". https://orgres-f.ru/. December 2023.
{{cite web}}
: External link in
(help)CS1 maint: url-status (link)|website=
- ↑ "Около 1 млрд тенге похищено при модернизации Экибастузской ГРЭС-2 – прокуратура". vlast.kz. February 2024.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 29.0 29.1 29.2 29.3 "Отчет по исполнению План-графика подготовки и реализации проекта «Расширение и реконструкция Экибастузской ГРЭС-2 с установкой энергоблока ст. № 3» от 01.04.2024 г." (PDF). gres2.kz. April 2024.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 30.0 30.1 30.2 30.3 "Annual Integrated Report of Samruk-Energy JSC based on the results of 2023" (PDF). www.samruk-energy.kz. June 2024.
{{cite web}}
: line feed character in|title=
at position 46 (help)CS1 maint: url-status (link) - ↑ 31.0 31.1 31.2 "Отчет по исполнению План-графика подготовки и реализации проекта «Расширение и реконструкция Экибастузской ГРЭС-2 с установкой энергоблока ст. № 3» на технологических решениях РФ (по состоянию на 01.10.2024 г.)" (PDF). /gres2.kz. 1 October 2024.
{{cite web}}
: line feed character in|title=
at position 179 (help)CS1 maint: url-status (link) - ↑ 32.0 32.1 "Экибастузская ГРЭС-2 подписала ЕРС-договор на строительство 3 и 4 энергоблоков". samruk-energy.kz. August 2024.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Российские технологии предпочли китайским в проекте расширения Экибастузской ГРЭС". orda.kz/. September 2024.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 34.0 34.1 "Стали известны сроки строительства ГРЭС-3 в Экибастузе". https://www.inform.kz/. January 2023.
{{cite web}}
: External link in
(help)CS1 maint: url-status (link)|website=
- ↑ "В Экибастузе построят ГРЭС-3?". salem.su. January 2023.
{{cite web}}
: CS1 maint: url-status (link) - ↑ 36.0 36.1 "В Алматы обсудили энергетические проекты". www.samruk-energy.kz. January 2023.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "CEEC has signed two consecutive contracts in the Kazakhstan market," Seetao, July 10, 2023
- ↑ "中国能建新签两个哈萨克斯坦电站项目," China International Contractors Association, July 14, 2023
- ↑ "Пострадавший от атаки шортистов индийский миллиардер отказался от строительства крупной угольной станции в Казахстане". /kz.kursiv.media. 7 December 2023. Retrieved via the Wayback Machine.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link) - ↑ "Как регулирование майнинга сказалось на энергосистеме Казахстана". kz.kursiv.media. April 2023.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Приказ "Об утверждении Плана мероприятий по развитию электроэнергетической отрасли до 2035 года"". /www.gov.kz. February 2024.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Russian Vnesheconombank attracts loan from China Development Bank for Ekibastuz GRES-2 in Kazakhstan". Trend.Az. 2013-10-22. Retrieved 2020-11-16.
- ↑ "Экибастузская ГРЭС-2 устранила угрозу валютных рисков". samruk-energy.com. 2020.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "На модернизацию Экибастузской ГРЭС-2 могут привлечь средства из России и ЕНПФ". /kz.kursiv.media. October 2023.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "Об утверждении перечня пятидесяти объектов I категории, наиболее крупных по суммарным выбросам загрязняющих веществ в окружающую среду на 1 января 2021 года". adilet.zan.kz. April 2022.
{{cite web}}
: CS1 maint: url-status (link)
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.