Fujian Sansteel Minguang Co., Ltd. Gas Power Project

From Global Energy Monitor
Part of the
Global Oil and Gas Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related categories:

Fujian Sansteel Minguang Co., Ltd. Gas Power Project (福建三钢闽光股份有限公司80MW煤气高效发电机组) is an operating power station of at least 240-megawatts (MW) in Sanyuan District, Sanming, Fujian, China.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Fujian Sansteel Minguang Co., Ltd. Gas Power Project Sanyuan District, Sanming, Fujian, China 26.257284, 117.614241 (exact)[1]

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • 1, 2, 3: 26.257284, 117.614241

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year
1 Operating[2] industrial by-product: blast furnace gas[2] 80[2] steam turbine[2] not found 2017[2]
2 Operating[3] industrial by-product: blast furnace gas[4] 80[4] steam turbine[5] not found 2023[3]
3 Operating[6] industrial by-product: blast furnace gas[4] 80[4] steam turbine[5] not found 2023[6]

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
1 Sansteel Minguang Co Ltd Fujian [100%][4][1] Fujian Metallurgical Holding Co Ltd [53.4%]; other [46.6%]
2 Sansteel Minguang Co Ltd Fujian [100%][4][1] Fujian Metallurgical Holding Co Ltd [53.4%]; other [46.6%]
3 Sansteel Minguang Co Ltd Fujian [100%][4][1] Fujian Metallurgical Holding Co Ltd [53.4%]; other [46.6%]

Project-level captive use details

  • Captive industry use (heat or power): power[4]
  • Captive industry: Iron & Steel[4]
  • Non-industry use: none[4]


Background

Unit 1 was commissioned and connected to the grid in 2017.[7]

In October 2022, the Fujian Provincial Development and Reform Commission approved the Unit 2 and Unit 3 projects. [8]On August 22, 2023, Unit 2 was successfully connected to the grid.[9] Unit 3 is expected to be completed in November 2023.[10]

Articles and Resources

References

  1. 1.0 1.1 1.2 1.3 https://cti-cert.com.tw/new/5732.html. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 2.2 2.3 2.4 https://news.cc123.com/falv/d099114757d4fcf7.htm. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 https://m.bjx.com.cn/mnews/20230829/1328749.shtml. {{cite web}}: Missing or empty |title= (help)
  4. 4.0 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 4.9 https://archive.org/details/screenshot-2023-05-29-at-1.53.33-pm. {{cite web}}: Missing or empty |title= (help)
  5. 5.0 5.1 https://www.cacem.com.cn/index.php?m=content&c=index&a=show&catid=95&id=15183. {{cite web}}: Missing or empty |title= (help)
  6. 6.0 6.1 https://m.bjx.com.cn/mnews/20231121/1344651.shtml. {{cite web}}: Missing or empty |title= (help)
  7. "福建省经信委关于福建三钢闽光股份有限公司80MW煤气高效发电机组并网运行条件确认的批复". 2017-12-20. Retrieved 2323-10-17. {{cite web}}: Check date values in: |access-date= (help)CS1 maint: url-status (link)
  8. "福建省发展和改革委员会关于三钢闽光动力厂两台煤气高效发电机组项目核准的批复". 2022-10-10. Retrieved 2023-10-17.{{cite web}}: CS1 maint: url-status (link)
  9. "三钢闽光动力厂煤气发电项目1#机组成功并网发电!". 2023-08-29. Retrieved 2023-10-17.{{cite web}}: CS1 maint: url-status (link)
  10. "福建三钢闽光股份有限公司动力厂两台煤气高效发电机组调试试运行项目招标公告". 2022-12-22. Retrieved 2023-10-17.{{cite web}}: CS1 maint: url-status (link)