Fuling Baitao power station (重庆涪陵白涛化工园区热电联产项目, 涪陵白涛燃机热电联产项目) is a power station in Baitao Industrial Park, Fuling District, Chongqing, China with multiple units of varying statuses, none of which are currently operating.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Fuling Baitao power station Baitao Industrial Park, Fuling District, Chongqing, China 29.5531276, 107.4860139 (approximate)[1]

The map below shows the approximate location of the power station.

Loading map...


Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year
1 Construction[1] fossil gas: natural gas[2] 490[2] combined cycle[2] yes[2] 2025 (planned)[3]
2 Announced[1][4] fossil gas: natural gas[4] 490[4] combined cycle[4] yes[4]

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
1 Chongqing Baitao Gas Turbine Thermal Power Co Ltd [100%][2] Chongqing Baitao Gas Turbine Thermal Power Co Ltd [100.0%]
2 Chongqing Baitao Gas Turbine Thermal Power Co Ltd [100%][2] Chongqing Baitao Gas Turbine Thermal Power Co Ltd [100.0%]

Background

The original owner of this project was Chongqing Fuling Julong Power Co., Ltd.(重庆涪陵聚龙电力有限公司), which was later changed to Chongqing Baitao Gas Turbine Thermal Power Co., Ltd. (重庆白涛燃机热电有限公司)[5][6]

Articles and Resources

References

  1. 1.0 1.1 1.2 "重庆涪陵白涛化工园区1×490MW热电联产项目开工". 2024-03-08. Archived from the original on 2024-04-11. Retrieved 2024-04-08.
  2. 2.0 2.1 2.2 2.3 2.4 2.5 https://www.58heating.com/news/show.php?itemid=5365. {{cite web}}: Missing or empty |title= (help)
  3. https://www.sohu.com/a/838191409_121106884. {{cite web}}: Missing or empty |title= (help)
  4. 4.0 4.1 4.2 4.3 4.4 "涪陵白涛化工园区山窝组团热电联产项目开工_电力网". mm.chinapower.com.cn. 2024-03-07. Archived from the original on 2024-04-16. Retrieved 2024-04-08.
  5. "总投资为12.77亿,重庆涪陵白涛化工园区热电联产项目获得重庆市发展和改革委员会核准批复". 2022-11-03. Retrieved 2023-10-16.{{cite web}}: CS1 maint: url-status (link)
  6. "重庆市发展和改革委员会关于涪陵白涛燃机热电联产项目的节能审查意见". 2023-09-01. Retrieved 2023-10-16.{{cite web}}: CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of gas-fired power stations, a downloadable dataset, and summary data, please visit the Global Oil and Gas Plant Tracker on the Global Energy Monitor website.