Guangzhou Baiyun Hengyun power station (广州白云恒运天然气发电项目一期 (Unit 1-1), 广州白云恒运天然气发电项目一期 (Unit 1-2), 广州白云恒运天然气发电项目二期 (Unit 2-1)) is a power station in Guangzhou, Dalangcun, Baiyun District, Guangdong, China with multiple units of varying statuses, none of which are currently operating.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Guangzhou Baiyun Hengyun power station Guangzhou, Dalangcun, Baiyun District, Guangdong, China 23.2517508, 113.2399112 (exact)[1]

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • 1-1, 1-2, 2-1: 23.2517508, 113.2399112

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year
1-1 Construction[2][3] fossil gas: natural gas[4] 460[4] combined cycle[4] not found 2025 (planned)[3]
1-2 Construction[2][3] fossil gas: natural gas[4] 460[4] combined cycle[4] not found 2025 (planned)[3]
2-1 Announced[4] fossil gas: natural gas[4] 460[4] combined cycle[4] yes[4]

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
1-1 Guangzhou Hengyun Enterprise Group Co Ltd [100%][5][3] Guangzhou Hengyun Enterprise Group Co Ltd [100.0%]
1-2 Guangzhou Hengyun Enterprise Group Co Ltd [100%][5][3] Guangzhou Hengyun Enterprise Group Co Ltd [100.0%]
2-1 Guangzhou Hengyun Enterprise Group Co Ltd [100%][4][3] Guangzhou Hengyun Enterprise Group Co Ltd [100.0%]

Background

Guangzhou Baiyun Hengyun power station (广州白云恒运天然气发电项目) plans for three 460MW-class gas-steam combined cycle generating units. [6]The first phase aims to construct two 460MW-class gas-steam combined cycle peaking units, with construction commencing in June 2023 and an expected operation start in 2025.[7]

Articles and Resources

References

  1. https://www.by.gov.cn/gzjg/byhj/zwgk/zfxxgkml/qt/qt/content/post_8915213.html. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 https://web.archive.org/web/20240506225733/https://m.163.com/dy/article/IUKVMFUE05526O4T.html. Archived from the original on 06 May 2024. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  3. 3.0 3.1 3.2 3.3 3.4 3.5 3.6 https://www.seetao.com/details/218497.html. {{cite web}}: Missing or empty |title= (help)
  4. 4.00 4.01 4.02 4.03 4.04 4.05 4.06 4.07 4.08 4.09 4.10 4.11 https://web.archive.org/web/20230331024210/https://freewechat.com/a/MzA5MjgwNjEyMw==/2650745808/1. {{cite web}}: Check |archive-url= value (help); Missing or empty |title= (help)
  5. 5.0 5.1 https://web.archive.org/web/20220414231441/http://www.hengyun.com.cn/EnvironmentalWork/info.aspx?itemid=7484. Archived from the original on 14 April 2022. {{cite web}}: Missing or empty |title= (help)
  6. "2×460MW!穗恒运A拟投建广州白云恒运天然气发电项目". 2023-02-06. Retrieved 2023-10-27.{{cite web}}: CS1 maint: url-status (link)
  7. "广州白云天然气发电项目2×460MW级燃气机组工程开工". 2023-06-22. Retrieved 2023-10-27.{{cite web}}: CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of gas-fired power stations, a downloadable dataset, and summary data, please visit the Global Oil and Gas Plant Tracker on the Global Energy Monitor website.