Guangzhou Zengcheng Wanglong Gas Thermal power station (广州增城旺隆燃气热电站, 广州增城旺隆气电替代工程) is a power station under construction in Xintang Town, Zengcheng, Guangzhou, Guangdong, China.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Guangzhou Zengcheng Wanglong Gas Thermal power station Xintang Town, Zengcheng, Guangzhou, Guangdong, China 23.09291, 113.564884 (exact)[1]

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • 1, 2: 23.09291, 113.564884

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year
1 Construction[2] fossil gas: natural gas[3][2][1][4] 460[1] combined cycle[1] not found[4] 2026 (planned)[5]
2 Construction[2] fossil gas: natural gas[3][2][1][4] 460[1] combined cycle[1] not found[4] 2026 (planned)[5]

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
1 Guangzhou Development Power Technology Co Ltd [100%][6][1][7] Guangzhou Development Group Inc [100.0%]
2 Guangzhou Development Power Technology Co Ltd [100%][6][1][7] Guangzhou Development Group Inc [100.0%]

Background

Guangzhou Zengcheng Wanglong Gas Thermal power station (广州增城旺隆燃气热电站) received approval from the Guangzhou Development and Reform Commission on June 2, 2022, and entered the construction phase on October 26, 2023.[8]

Articles and Resources

References

  1. 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 https://web.archive.org/web/20221004212312/http://www.zc.gov.cn/gk/zdly/hjbhxxgk/jsxmhjyxpjxx/content/post_8333880.html. Archived from the original on 2022-10-04. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 2.2 2.3 https://web.archive.org/web/20231026150537/http://www.stcn.com/article/detail/1016357.html. Archived from the original on 2023-10-26. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 "2×460MW!广州发展增城旺隆气电替代工程项目获得核准-北极星电力新闻网". m.bjx.com.cn. 2022-06-07. Archived from the original on 2024-05-06. Retrieved 2024-04-23.
  4. 4.0 4.1 4.2 4.3 https://www.163.com/dy/article/IIEQLRQF0552XW5S.html. {{cite web}}: Missing or empty |title= (help)
  5. 5.0 5.1 https://www.msn.com/zh-cn/news/other/%E5%B9%BF%E5%B7%9E%E5%A2%9E%E5%9F%8E-%E6%97%BA%E9%9A%86%E6%B0%94%E7%94%B5%E6%9B%BF%E4%BB%A3%E5%B7%A5%E7%A8%8B%E9%A1%B9%E7%9B%AE%E4%B8%BB%E5%8E%82%E6%88%BF%E5%BC%80%E5%BB%BA-%E8%AE%A1%E5%88%922026%E5%B9%B4%E6%8A%95%E4%BA%A7/ar-AA1th4Nx. {{cite web}}: Missing or empty |title= (help)
  6. 6.0 6.1 https://web.archive.org/web/20210605000420/https://news.bjx.com.cn/html/20171128/864261-8.shtml. Archived from the original on 2021-06-05. {{cite web}}: Missing or empty |title= (help)
  7. 7.0 7.1 https://www.qcc.com/firm_15J5UVG.shtml. {{cite web}}: Missing or empty |title= (help)
  8. "广州发展旗下广州增城旺隆气电替代工程开工". 2023-10-26. Retrieved 2023-10-27.{{cite web}}: CS1 maint: url-status (link)

Additional data

To access additional data, including an interactive map of gas-fired power stations, a downloadable dataset, and summary data, please visit the Global Oil and Gas Plant Tracker on the Global Energy Monitor website.