Guoxin Binhai Port power station (江苏国信盐城滨海港发电项目) is a power station under construction in Huanghai New District, Binhai, Yancheng, Jiangsu, China. It is also known as 江苏国信滨海港发电有限公司.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Guoxin Binhai Port power station | Huanghai New District, Binhai, Yancheng, Jiangsu, China | 34.298193, 120.188459 (approximate) |
The map below shows the approximate location of the power station.
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year | Retired year |
---|---|---|---|---|---|---|
Unit 1 | construction | unknown | 1000 | ultra-supercritical | – | – |
Unit 2 | construction | unknown | 1000 | ultra-supercritical | – | – |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Unit 1 | Jiangsu Guoxinbin Haigang Power Generation Co Ltd | Jiangsu Guoxin Corp Ltd [51.00%]; Zhongneng Power (Suzhou) Co Ltd [16.70%]; Shanghai Electric Power Co Ltd [15.40%]; Yancheng State-owned Assets Investment Group Co Ltd [12.00%]; other [4.90%] |
Unit 2 | Jiangsu Guoxinbin Haigang Power Generation Co Ltd | Jiangsu Guoxin Corp Ltd [51.00%]; Zhongneng Power (Suzhou) Co Ltd [16.70%]; Shanghai Electric Power Co Ltd [15.40%]; Yancheng State-owned Assets Investment Group Co Ltd [12.00%]; other [4.90%] |
Project-level coal details
- Permit(s): 2022-06-09
Background
The province issued a "Plan" in 2021 (《江苏省发展改革委关于下发大型清洁高效煤电项目规划建设方案的通知》(苏发改能源发〔2021〕396号)), specifically for this project, and an operating company was established. The investment was estimated at 3 billion RMB.[1][2]
The power station was reportedly permitted in June 2022.[3]
The power station has been described as a strategic cooperation project between Yancheng and the Provincial Guoxin Group, and is also a key energy project planned and constructed in Jiangsu's 14th Five-Year Plan. It is jointly invested and constructed by Jiangsu Guoxin Co., Ltd., State Power Investment GCL Binhai Power Generation Co., Ltd., and Yancheng Guoneng Investment Co., Ltd.[4]
In September 2022, a ceremony was held to mark the project's construction start.[5][6]
Plant Details for expansion
- Sponsor: Jiangsu Guoxin Binhai Port Power Generation Co., Ltd. (江苏国信滨海港发电有限公司)
- Parent company: Jiangsu Guoxin Corp. Ltd. (51%), State Power Investment Group GCL Binhai Power Generation Co., Ltd. (34%), Yancheng National Energy Investment Co., Ltd. (15%.)
- Location: Binhai, Yancheng, Jiangsu Province, China
- Coordinates: 34.096, 119.997 (approximate)
- Status: Construction
- Gross capacity: 2 x 1,000 MW
- Type: Ultra-supercritical
- Start year:
- Coal type:
- Coal source:
- Source of financing:
Articles and Resources
References
- ↑ "国信拟建盐城滨海港2×1000MW煤电项目, 北极星电力网新闻中心, 2021/8/27
- ↑ 江苏国信(002608.SZ):拟与协鑫滨海、盐城国能共建盐城滨海港2×1000MW高效清洁超超临界燃煤发电项目, JRJ, 2021-11-15
- ↑ 国家电投参股!国信滨海港2×100万千瓦清洁高效燃煤发电项目获得核准, BJX, 2022-06-09
- ↑ Guoxin Yancheng Binhai Port Efficient and Clean Coal Power Project Started, Seetao, 2022-9-27
- ↑ 国信盐城滨海港高效清洁煤电项目开工, 盐城市滨海县委宣传部, 2022-09-27
- ↑ 国信盐城滨海港高效清洁煤电项目开工建设, 盐阜大众报 2022-09-27
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.