Hamina LNG Terminal is an operating LNG terminal in Kymenlaakso, Finland.[1]
Location
The map below shows the location of Hamina Port, the approximate location of the project, in Hamina Municipality, Kymenlaakso Region.
Project Details
- Operator: Hamina LNG Oy[2]
- Owner: Hamina LNG Oy[2]
- Parent: Hamina Energy, Alexela, Wärtsilä[2]
- Location: Port of Hamina, Hamina Municipality, Kymenlaakso Region, Finland
- Coordinates: 60.5183139,27.1608198 (exact)
- Capacity: 6000 MWh/d (0.17 mtpa, 0.22 bcm/y)[3]
- Cost: Approximately €100 million (US$120 million)[4]
- Financing: A grant of approximately €30 million from the Finnish government; debt financing of approximately €67.5 million from Swedish commercial bank SEB[5]
- Status: Operating[1]
- Type: Import
- Start Year: 2022[6]
Note: mtpa = million tonnes per year; bcfd = billion cubic feet per day
Background
Hamina LNG Terminal is a liquefied natural gas (LNG) regasification terminal under development in Kymenlaakso Region. It appears to have been first proposed in December 2014.[7]
Construction began in May 2017.[7] The project was built by Hamina LNG Oy, a joint venture of Hamina Energy Ltd, Estonian energy company Alexela, and Finnish technology company Wärtsilä. It was 30% funded through a state grant.[2]
Tender was issued on the project in October 2016.[8] Construction began in June 2017, and was scheduled to be completed in 2020.[9]
As of October 2020, the terminal was expected to begin operations in April 2021.[10]
In August 2021, a press release from the Hamina LNG company announced that commercial operations had been delayed until an as yet unspecified date in 2022.[6]
In April 2022, Hamina LNG said that the terminal would enter commercial operations in October 2022 and that it had already launched plans to increase the terminal's capacity.[11]
In October 2022, Hamina LNG Terminal began commercial operations.[1]
Articles and resources
References
- ↑ 1.0 1.1 1.2 LNG Prime Staff (2022-10-06). "Finland's Hamina LNG terminal starts commercial ops". LNG Prime. Retrieved 2022-12-13.
- ↑ 2.0 2.1 2.2 2.3 Hamina LNG website, accessed May 2022
- ↑ "LNG-Terminal". Hamina LNG. Retrieved 2024-07-23.
- ↑ Hamina LNG terminal in Finland reaches financial close, International Group of Liquefied Natural Gas Importers, May 17, 2018
- ↑ LNG import terminal in Hamina, Finnvera, accessed Jan. 11, 2021
- ↑ 6.0 6.1 Commercial commissioning of the LNG terminal in Hamina will be postponed, Hamina LNG press release, Aug. 23, 2021
- ↑ 7.0 7.1 "https://www.hydrocarbons-technology.com/projects/hamina-lng-terminal/".
{{cite web}}
: External link in
(help)CS1 maint: url-status (link)|title=
- ↑ Tender issued for Finland's Hamina LNG terminal, Conferenza GNL website, 10 Oct. 2016.
- ↑ Finland: Hamina LNG terminal construction starts, LNG World News, Jun. 22, 2017
- ↑ Commercial commissioning of Hamina LNG’s terminal approaching, Port of Haminakotka, Oct. 21, 2020
- ↑ Sanja Pekic, Hamina LNG terminal in Finland to start operations this year, Offshore Energy, Apr. 12, 2022