Henan Yongcheng power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Henan Yongcheng power station (河南永城发电厂) is an operating power station of at least 630-megawatts (MW) in Yongcheng, Shangqiu, Henan, China with multiple units, some of which are not currently operating. It is also known as 永煤集团裕东发电厂 (Unit 1 & 2), 中煤永城2x1000MW高效超超临界机组 (New Unit 1 & 2), 永城发电厂.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Henan Yongcheng power station Yongcheng, Shangqiu, Henan, China 33.95412, 116.415988 (approximate)

The map below shows the approximate location of the power station.

Loading map...


Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year
New Unit 1 construction coal: unknown 1000 ultra-supercritical
New Unit 2 construction coal: unknown 1000 ultra-supercritical
Unit 1 operating coal: anthracite 315 subcritical 2005
Unit 2 operating coal: anthracite 315 subcritical 2005

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
New Unit 1 China Coal Power Co Ltd [100%] China National Coal Group [100.0%]
New Unit 2 China Coal Power Co Ltd [100%] China National Coal Group [100.0%]
Unit 1 Shangqiu Yudong Power Generation Co Ltd [100%] Henan Province Energy Chemical Group Co Ltd [100.0%]
Unit 2 Shangqiu Yudong Power Generation Co Ltd [100%] Henan Province Energy Chemical Group Co Ltd [100.0%]

Background

Yongcheng power station is a two-unit coal-fired power plant with a total capacity of 630 MW.[1] The plant was completed in 2005, and is owned by Yongcheng Mine Group.[2][3] An additional 2,000 MW of coal capacity is under development.

New Project

A new project was listed in Yongcheng City's 14th Five-Year plan.[4][5]

The project was permitted November 3, 2022.[6] Construction reportedly began December 29, 2022.[7]

The project was so rushed that based on available information, it was hard to tell if it was being built at the same site or if the project was a relocation. There is a possibility the older 2 x 315 MW could be shut down to make room for the new one.[8]

Articles and Resources

References

  1. "裕东电厂--永城市人民政府网站". www.ycs.gov.cn. 2017-03-07.{{cite web}}: CS1 maint: url-status (link)
  2. Yongcheng Powerplant, Enipedia, accessed Sept. 2015.
  3. "河南永城电厂2号30万千瓦机组投产," Sina, Jan 5, 2005
  4. "河南永城:建设中煤永城2×1000MW高效超超临界机组工程项目," BJX, 2022-10-09
  5. "YCS," Archive, accessed October 2023
  6. "中煤永城2×1000MW高效超超临界机组工程获得核准," BJX, 2022-12-04
  7. "中煤·商丘(永城)2×1000MW高效超超临界机组工程开工," BJX, 2023-01-13
  8. See, e.g., "总投资约70亿,中煤永城2×1000MW高效超超临界机组工程项目新进展," Tou Tiao, 2022-08-07