Henan Yongcheng power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Henan Yongcheng power station (河南永城发电厂, 中煤·河南永城“两个联营”暨综合能源基地项目) is an operating power station of at least 630-megawatts (MW) in Yongcheng, Shangqiu, Henan, China with multiple units, some of which are not currently operating. It is also known as 中煤商丘(永城)2x1000MW高效超超临界机组 (New Unit 1 & 2), 永煤集团裕东发电厂 (Unit 1 & 2).
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Henan Yongcheng power station | Yongcheng, Shangqiu, Henan, China | 33.95412, 116.415988 (approximate) |
The map below shows the approximate location of the power station.
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
New Unit 1 | Construction | coal: unknown | 1000 | ultra-supercritical | – |
New Unit 2 | Construction | coal: unknown | 1000 | ultra-supercritical | – |
Unit 1 | Operating | coal: anthracite | 315 | subcritical | 2005 |
Unit 2 | Operating | coal: anthracite | 315 | subcritical | 2005 |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
New Unit 1 | China Coal Power Co Ltd [100%] | China National Coal Group [100.0%] |
New Unit 2 | China Coal Power Co Ltd [100%] | China National Coal Group [100.0%] |
Unit 1 | Shangqiu Yudong Power Generation Co Ltd [100%] | Henan Province Energy Chemical Group Co Ltd [100.0%] |
Unit 2 | Shangqiu Yudong Power Generation Co Ltd [100%] | Henan Province Energy Chemical Group Co Ltd [100.0%] |
Project-level coal details
- Permit(s): 豫发改审批〔2022〕588号[1]
Background
Yongcheng power station is a two-unit coal-fired power plant with a total capacity of 630 MW.[2] The plant was completed in 2005, and is owned by Yongcheng Mine Group.[3][4] An additional 2,000 MW of coal capacity is under development.
New Project
A new project was listed in Yongcheng City's 14th Five-Year plan.[5][6]
The project was permitted November 3, 2022.[7] Construction reportedly began December 29, 2022.[8]
The project was so rushed that based on available information, it was hard to tell if it was being built at the same site or if the project was a relocation. There is a possibility the older 2 x 315 MW could be shut down to make room for the new one.[9]
Articles and Resources
References
- ↑ https://news.bjx.com.cn/html/20221204/1273882.shtml.
{{cite web}}
: Missing or empty|title=
(help) - ↑ "裕东电厂--永城市人民政府网站". www.ycs.gov.cn. 2017-03-07.
{{cite web}}
: CS1 maint: url-status (link) - ↑ Yongcheng Powerplant, Enipedia, accessed Sept. 2015.
- ↑ "河南永城电厂2号30万千瓦机组投产," Sina, Jan 5, 2005
- ↑ "河南永城:建设中煤永城2×1000MW高效超超临界机组工程项目," BJX, 2022-10-09
- ↑ "YCS," Archive, accessed October 2023
- ↑ "中煤永城2×1000MW高效超超临界机组工程获得核准," BJX, 2022-12-04
- ↑ "中煤·商丘(永城)2×1000MW高效超超临界机组工程开工," BJX, 2023-01-13
- ↑ See, e.g., "总投资约70亿,中煤永城2×1000MW高效超超临界机组工程项目新进展," Tou Tiao, 2022-08-07
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.