Huadian Laizhou power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Huadian Laizhou power station (华电国际莱州发电厂) is an operating power station of at least 4100-megawatts (MW) in Jincheng Town, Laizhou, Yantai, Shandong, China.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Huadian Laizhou power station | Jincheng Town, Laizhou, Yantai, Shandong, China | 37.432222, 120.018056 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Phase I Unit 1, Phase I Unit 2, Phase II Unit 3, Phase II Unit 4: 37.432222, 120.018056
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Phase I Unit 1 | operating | coal: bituminous | 1050 | ultra-supercritical | 2012 |
Phase I Unit 2 | operating | coal: bituminous | 1050 | ultra-supercritical | 2012 |
Phase II Unit 3 | operating | coal: bituminous | 1000 | ultra-supercritical | 2019 |
Phase II Unit 4 | operating | coal: bituminous | 1000 | ultra-supercritical | 2019 |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Phase I Unit 1 | Huadian Laizhou Power Generation Co Ltd [100%] | Huadian Power International Co Ltd [75.0%]; Shandong Development Investment Holding Group Co Ltd [17.5%]; Shandong Guohui Investment Co Ltd [5.0%]; Shandong Caixin Asset Operation Co Ltd [2.5%] |
Phase I Unit 2 | Huadian Laizhou Power Generation Co Ltd [100%] | Huadian Power International Co Ltd [75.0%]; Shandong Development Investment Holding Group Co Ltd [17.5%]; Shandong Guohui Investment Co Ltd [5.0%]; Shandong Caixin Asset Operation Co Ltd [2.5%] |
Phase II Unit 3 | Huadian Laizhou Power Generation Co Ltd [100%] | Huadian Power International Co Ltd [75.0%]; Shandong Development Investment Holding Group Co Ltd [17.5%]; Shandong Guohui Investment Co Ltd [5.0%]; Shandong Caixin Asset Operation Co Ltd [2.5%] |
Phase II Unit 4 | Huadian Laizhou Power Generation Co Ltd [100%] | Huadian Power International Co Ltd [75.0%]; Shandong Development Investment Holding Group Co Ltd [17.5%]; Shandong Guohui Investment Co Ltd [5.0%]; Shandong Caixin Asset Operation Co Ltd [2.5%] |
Background
The first two coal-fired units of Huadian Laizhou power station, totaling 2,100 MW, were brought online in 2012. The plant is majority-owned by China Huadian.[1]
Description of Expansion
Huadian is currently planning to build two additional coal-fired units at this plant, with a total planned capacity of 2,000 MW.[2] The company hopes to have the units approved and under construction by the end of 2014.[3] The two units were permitted in 2015.[4] Construction began in 2016.[5]
Nationwide Restrictions Imposed on Development of Coal-Fired Power Capacity
In January 2017 China's National Energy Administration proposed for suspension over 100 planned and under-construction coal power projects in 13 provinces, including Huadian Laizhou. The NEA proposed the projects included be postponed to the 14th Five Year period (2021-2025).[6]
For details, see China's 2016 Restrictions on Development of Coal-Fired Power Capacity.
Construction ongoing
Based on Planet satellite data from August 2017 to November 2018 construction has continued on the power station. A January 2018 news article confirmed construction was ongoing, with operation planned for 2019.[7] This appears to violate NEA Electricity [2016] 275, which suspended construction that began in 2016 or later in all provinces that have a red light under the traffic light system, which includes Shandong.
Unit 3 was commissioned in August 2019.[8]
Unit 4 was commissioned in November 2019.[9]
Articles and Resources
References
- ↑ "Coal-Fired Plants in China - Shandong - A to M," Industcards, accessed November 2014
- ↑ "华电莱州电厂2×1000MW级机组工程获核准," 2010年02月04日
- ↑ "华电莱州电厂二期计划“十二五”内开工建设," Jiadong.net, March 31, 2014.
- ↑ "华电莱州二期(2×1000MW)清洁高效火电项目获核准," 2015-09-15
- ↑ "诚信在线华电莱州发电有限公司二期2×1000MW超超临界机组工程诚信在线泵及废水回收水泵等设备二次招标," 中国诚信在线处理工程网, 2018-3-28
- ↑ "能源局下发13省市新建火电机组停建清单(附文件)," Polaris, Jan 16, 2017
- ↑ "华电国际打造“智慧电厂”样本 莱州电厂实现废水零排放," 证券日报, 2018年01月24日
- ↑ "华电莱州发电3号1000MW发电机组完成168试运," 北极星电力网新闻中心, 2019/8/27
- ↑ "[中国能源网:华电莱州第四台百万机组顺利投产 - 中国华电集团,"] China Huadian website, Nov 14, 2019