Jaworzno power station

From Global Energy Monitor
(Redirected from Jaworzno Power Station)

Jaworzno power station is an operating power station of at least 2495-megawatts (MW) in Jaworzno, Śląskie, Poland. It is also known as Jaworzno-2 power station (Phase 2 Unit 1, Phase 2 Unit 2, Phase 2 Unit 3), Jaworzno-3 power station (Phase 3 Unit 1, Phase 3 Unit 2, Phase 3 Unit 3, Phase 3 Unit 4, Phase 3 Unit 5, Phase 3 Unit 6, Phase 3 Unit 7).

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Jaworzno power station Jaworzno, Jaworzno, Śląskie, Poland 50.213351, 19.22806 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Phase 2 Unit 1, Phase 2 Unit 2, Phase 2 Unit 3: 50.213351, 19.22806
  • Phase 3 Unit 1, Phase 3 Unit 2, Phase 3 Unit 3, Phase 3 Unit 4, Phase 3 Unit 5, Phase 3 Unit 6: 50.207238, 19.205311
  • Phase 3 Unit 7: 50.20777, 19.20972

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
1R, timepoint 2 Operating[1] bioenergy: wood & other biomass (solids)[1] 50[1] 1953[1]
Phase 2 Unit 1, timepoint 1 Retired[2][3] coal: bituminous[2] 60 subcritical 1998 2013[2]
Phase 2 Unit 1, timepoint 2 Operating[2][3] bioenergy: wood & other biomass (solids)[2] 50[4] 2013[4]
Phase 2 Unit 2 Operating coal: bituminous 70 subcritical 1998 2025 (planned)
Phase 2 Unit 3 Operating coal: bituminous 70 subcritical 1998 2025 (planned)
Phase 3 Unit 1 Operating coal: bituminous 225 subcritical 1977 2025 (planned)
Phase 3 Unit 2 Operating coal: bituminous 225 subcritical 1977 2025 (planned)
Phase 3 Unit 3 Operating coal: bituminous 225 subcritical 1977 2028 (planned)
Phase 3 Unit 4 Operating coal: bituminous 225 subcritical 1977 2025 (planned)
Phase 3 Unit 5 Operating coal: bituminous 220 subcritical 1978 2028 (planned)
Phase 3 Unit 6 Operating coal: bituminous 225 subcritical 1978 2025 (planned)
Phase 3 Unit 7 Operating coal: bituminous 910 supercritical 2020

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
1R, timepoint 2 TAURON Wydobycie SA [100%] TAURON Wydobycie SA [100.0%]
Phase 2 Unit 1, timepoint 1 TAURON Wydobycie SA [100%] TAURON Wydobycie SA [100.0%]
Phase 2 Unit 1, timepoint 2 TAURON Wydobycie SA [100%] TAURON Wydobycie SA [100.0%]
Phase 2 Unit 2 TAURON Wytwarzanie SA [100%] TAURON Polska Energia SA [100.0%]
Phase 2 Unit 3 TAURON Wytwarzanie SA [100%] TAURON Polska Energia SA [100.0%]
Phase 3 Unit 1 TAURON Wytwarzanie SA [100%] TAURON Polska Energia SA [100.0%]
Phase 3 Unit 2 TAURON Wytwarzanie SA [100%] TAURON Polska Energia SA [100.0%]
Phase 3 Unit 3 TAURON Wytwarzanie SA [100%] TAURON Polska Energia SA [100.0%]
Phase 3 Unit 4 TAURON Wytwarzanie SA [100%] TAURON Polska Energia SA [100.0%]
Phase 3 Unit 5 TAURON Wytwarzanie SA [100%] TAURON Polska Energia SA [100.0%]
Phase 3 Unit 6 TAURON Wytwarzanie SA [100%] TAURON Polska Energia SA [100.0%]
Phase 3 Unit 7 TAURON Wytwarzanie SA [100%] TAURON Polska Energia SA [100.0%]

Unit-level fuel conversion details:

Phase 2 Unit 1: Converted from coal to bioenergy in 1953.

Phase 2 Unit 1: Converted from coal to bioenergy in 2013.

Project-level coal details

  • Coal source(s): Tauron's mines

Financing

  • Source of financing: BGK;[5][6][7] PLN 880 million in equity from the Polish Development Fund[8][9]

Ownership

The power station is owned by the Tauron Group (TAURON Polska Energia SA holding).[10]

Jaworzno I and II

The first two generators of Jaworzno I were installed in 1898 with the capacity of 320kW for the purpose of lighting the neighboring coal mines and homes. In 1959, after modernization the power station's capacity reached 157 MW. Construction of the Jaworzno II Power Station started in the 1940s, and by 1953 the first two generating units became operational. In 1956, the Jaworzno Power Station II reached the capacity of 300MW. Jaworzno I was decommissioned in 1998.[11]

Jaworzno II Rebuild

The rebuild of Jaworzno II involved the addition of new CFB boilers, new turbines, and other equipment in 1998. Jaworzno II initially consisted of one 60 MW and two 70 MW units, commissioned in 1998.[11]

In 2013, Unit 1 of Jaworzno II was converted to biomass.[12][13]

Jaworzno III Plant

Construction of the Jaworzno III Power Station started in 1972 and the generating units were commissioned in 1977–1978. In 1995, all three stations were combined into a state-owned company called Elektrownia Jaworzno III. In 2000, the Elektrownia Jaworzno III became part of PKE SA. Jaworzno III has an installed electrical generating capacity of 6 x 225 MW.[10]

Jaworzno III Expansion (Unit 7)

In May 2010 a tender to build a new unit at the Jaworzno Power Plant was announced, originally planned for 2018.[14][15] The station would have a generating capacity of 910 MW and would burn more than 2.7 million tons of coal annually, producing more than 4.7 million tons of CO2.[16][17]

In 2013 the tender was granted to a consortium of Chinese companies (CNEEC/COVEC). Two appeals were filed against Tauron due to alleged irregularities in the tendering procedure: that the new unit does not hold an International Plant Protection Convention (IPPC) permit, nor are there ongoing administrative proceedings concerning permissions for the accompanying infrastructure.[16] In October 2013 contractor Rafako dropped North China Power Engineering (NCPE) and China Power Engineering Consulting Group Corporation (CPECC) from its consortium after the sides failed to agree terms of cooperation.[5]

In November 2013 Polish state development bank BGK signed a letter of intent to provide bank guarantees of PLN 4.4 billion for the project, which was expected to be completed in 2018.[5][6][7] In 2017, the Polish Development Fund committed to investing PLN 880 million in equity in the project.[8][9]

In February 2014 Tauron extended a deadline for signing a construction contract for the 910 MW unit at Jaworzno until April 30 due to problems with the project’s contractors, which have yet to secure bank guarantees for 10% of the contract value.[5]

In April 2014 Tauron signed a contract with a consortium consisting of engineering firm Rafako and construction firm Mostostal Warszawa for construction of the 910 MW unit. Construction was to take 59 months.[18]

In April 2018 it was reported that construction was on schedule, with operation still planned for 2019.[19]

Unit 7 was synchronized in November 2019, and was planned to go online on 31 January 2020.[20]

Damage to the plant's boiler during trial operations led to a further delay in taking the plant online. Tauron said in May 2020 that it was aiming for the plant to start up in November 2020.[21] The plant was reported as operating in November 2020.[22]

The unit was disconnected from the grid in August 2022 due to ongoing boiler defects. Tauron went back and forth with boiler-maker Rafako over the cause of the shut down. While the utility said technological problems with the boiler were to blame, Rafako stated that it was actually low-quality coal that was the issue. The unit was to be back online following repairs from a substitute contractor by September 2.[23]

Fitch Ratings, a financial services firm, noted in an October 2022 briefing that breakdowns at the unit had contributed to the utility's losses. "As the unit's planned generation volumes were sold on the forward market, the missing volumes had to be replaced with purchases on the spot market at significantly higher prices," the firm noted.[24]

In January 2023, Tauron demanded 1.3 billion zloty ($299 million USD) in damages and penalty fees from Rafako surrounding the troubled unit. The utility stated that Rafako had failed to rectify the unit's defects and had 30 days to pay.[25]

Articles and Resources

References

  1. 1.0 1.1 1.2 1.3 https://web.archive.org/web/20230426042936/https://www.tauron-wytwarzanie.pl/oddzialy/oddzial-jaworzno. Archived from the original on 26 April 2023. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 2.2 2.3 2.4 (PDF) https://web.archive.org/web/20240125124408/https://www.jaworzno.pl/wp-content/uploads/2023/02/Pkt_8_-_w_sprawie_przyjecia_Aktualizacji_zalozen_do_planu_zaopatrzenia_w_cieplo_energie_elektryczna_i_paliwa_gazowe_na_obszarze_miasta_Jaworzna.pdf. Archived from the original (PDF) on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 https://web.archive.org/web/20240125124447/https://www.eib.org/en/projects/pipelines/all/20100270. Archived from the original on 25 January 2024. {{cite web}}: Missing or empty |title= (help)
  4. 4.0 4.1 https://www.power-technology.com/data-insights/power-plant-profile-jaworzno-biomass-power-plant-poland/. {{cite web}}: Missing or empty |title= (help)
  5. 5.0 5.1 5.2 5.3 "Power in Europe," Platts report, Issue 675, April 28, 2014 (subscription only).
  6. 6.0 6.1 "BGK: Bliżej gwarancji na Jaworzno i Opole". forsal.pl (in polski). 2013-11-28. Retrieved 2020-12-01.
  7. 7.0 7.1 "RAFAKO: Przystąpienie przez Bank Gospodarstwa Krajowego do listu intencyjnego dot. Projektu Jaworzno". Bankier.pl (in polski). 2013-11-27. Retrieved 2020-12-01.
  8. 8.0 8.1 www.fitchratings.com https://www.fitchratings.com/research/corporate-finance/fitch-affirms-poland-tauron-at-bbb-rates-new-hybrids-bb-17-04-2019. Retrieved 2020-12-01. {{cite web}}: Missing or empty |title= (help)
  9. 9.0 9.1 "PFR invests in a new unit of the Jaworzno power plant". June 6, 2017.{{cite web}}: CS1 maint: url-status (link)
  10. 10.0 10.1 "History: We build modernity based on 100-year-long tradition," Tauron website, accessed Sep. 2012.
  11. 11.0 11.1 BANKTRACK: Jaworzno coal power plant, Poland
  12. "Aktualizacja założeń do planu zaopatrzenia w ciepło, energię elektryczną i paliwa gazowe na obszarze miasta Jaworzna (aktualizacja 2022 r.)," Energoekspert sp. z o.o. energia I ekologia, November 2022
  13. "Construction of biomass boiler improves Poland’s energy security," European Commission, December 16, 2014
  14. "New unit of Jaworzno Power Plant (nowy blok elektrowni Jaworzno)," BankTrack, accessed March 2013.
  15. "Power group Tauron again puts off deadline for EUR 1.1bn Jaworzno unit," GoWarsaw.eu, August 13, 2012.
  16. 16.0 16.1 "New unit of Jaworzno Power Plant (nowy blok elektrowni Jaworzno)," BankTrack, updated Mar 24, 2014.
  17. "Siemens Receives Order For Steam Power Plant Equipment From Poland," Power Online, June 13, 2014
  18. "Polish energy giant signs 910 MW power unit deal," China.org.cn, Apr 18, 2014
  19. "Elektrownia Jaworzno: Budowa bloku energetycznego. Jet olbrzymi. ZOBACZ ZDJĘCIA I WIDEO z budowy," Strefa Biznesu, 12.04.2018
  20. "Synchronizacja bloku 910 MW w Elektrowni Jaworzno III jeszcze w listopadzie," WNP, 19-11-2019
  21. "Tauron delays its 910 MW coal-fired power unit at Jaworzno III (Poland)," Enerdata, May 6, 2020
  22. "Nowy blok Elektrowni Jaworzno został oddany do eksploatacji". BiznesAlert.pl. 2020-11-14. Retrieved 2020-12-17.
  23. "Polish utility Tauron trades blows with boiler maker Rafako over cause of plant shutdown," Reuters, 30-08-2022
  24. Fitch Ratings, "Fitch Affirms Poland's Tauron at 'BBB-'; Outlook Stable", Fitch Ratings, October 12, 2022.
  25. "Tauron demands 1.3 bln zloty in damages over power unit it says is faulty," Reuters, January 11, 2023

Additional data

To access additional data, including interactive maps of the power stations, downloadable datasets, and summary data, please visit the Global Bioenergy Power Tracker and the Global Coal Plant Tracker on the Global Energy Monitor website.