Jayapura-3 power station is a cancelled power station in Papua, Indonesia.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Jayapura-3 power station Papua, Indonesia -2.60839, 140.807479 (approximate)

The map below shows the approximate location of the power station.

Loading map...


Project Details

Table 2: Unit-level details

Status Fuel(s) Capacity (MW) Technology Start year
cancelled coal: unknown 50 unknown 2028

Table 3: Unit-level ownership and operator details

Owner Parent
PT PLN (Persero) [100%] PT PLN (Persero) [100.0%]

Background

In the 2019-2028 long-range plan, the project was listed as 50-MW and was scheduled for 2028.[1]

In October 2021, the plant was shelved under the government's long-range plan for 2021-2030.[2]

In October 2023, with no apparent news since the project was shelved, Jayapura-3 power station was presumed to be cancelled.