Jiangsu Guoxin Shazhou power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Jiangsu Guoxin Shazhou power station (江苏国信沙洲发电项目) is a power station under construction in Zhangjiagang, Suzhou, Jiangsu, China.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Jiangsu Guoxin Shazhou power station | Zhangjiagang, Suzhou, Jiangsu, China | 31.985654, 120.684419 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2: 31.985654, 120.684419
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Unit 1 | construction | coal: unknown | 1000 | ultra-supercritical | 2025 (planned) |
Unit 2 | construction | coal: unknown | 1000 | ultra-supercritical | 2025 (planned) |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Unit 1 | Jiangsu Guoxin Shazhou Power Generation Co Ltd [100%] | Jiangsu Guoxin Corp Ltd [51.0%]; Wintime ENERGY Group Co Ltd [15.0%]; Zhangjiagang State Owned Capital Investment Group Co Ltd [15.0%]; Suzhou Urban Construction Investment Development Co Ltd [13.8%]; other [5.2%] |
Unit 2 | Jiangsu Guoxin Shazhou Power Generation Co Ltd [100%] | Jiangsu Guoxin Corp Ltd [51.0%]; Wintime ENERGY Group Co Ltd [15.0%]; Zhangjiagang State Owned Capital Investment Group Co Ltd [15.0%]; Suzhou Urban Construction Investment Development Co Ltd [13.8%]; other [5.2%] |
Background
This 2 x 1,000 MW ultra-supercritical coal-fired power plant is one of the three "establish first and then reform" projects to provide a clean, efficient and supportive power supply to Jiangsu province.[1]
The power station would be on the southwest side of Zhangjiagang Shazhou power station.
Permission to build was granted on 28 October 2022 by Jiangsu Provincial Development and Reform Commission (苏发改能源发〔2022〕1250号, portal update timestamp: 2023/01/16).[2] It was reported the construction for this plant may have begun on November 25, 2022 but concrete was poured into the foundation of the main structure at the end of June 2023, which indicates construction officially began.[3][4]
As of May 2023, EPC information for Jiangsu Guoxin Shazhou power station was available. The project was slated for operation in 2025.[5]
Articles and Resources
References
- ↑ "国信沙洲2×100万千瓦煤电项目最新进展!江苏国信拟设立合资公司!". 北极星火力发电网. 2022-10-09. Retrieved 2023-02-06.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "苏发改能源发〔2022〕1250号". 江苏省发展和改革委员会行政许可和行政处罚信息公示专栏. 2023/01/16. Retrieved 2023-08-15.
{{cite web}}
: Check date values in:|date=
(help)CS1 maint: url-status (link) - ↑ "中国能建江苏院设计的国信沙洲支撑性电源项目开工". 中国能建网站. 2022-12-01. Retrieved 2023-02-06.
{{cite web}}
: CS1 maint: url-status (link) - ↑ "国信沙洲2×1000MW机组扩建项目主体工程首砼浇筑!". 北极星电力网. 2023-06-29. Retrieved 2023-8-15.
{{cite web}}
: Check date values in:|access-date=
(help)CS1 maint: url-status (link) - ↑ 拟在建电厂项目推荐(05月10日), mp.weixin.qq.com, 2023-05-09
Additional data