Kalteng-1 Pulang Pisau power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Kalteng-1 Pulang Pisau power station is an operating power station of at least 120-megawatts (MW) in Buntoi, Kahayan Hilir, Pulang Pisau, Central Kalimantan, Indonesia.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Kalteng-1 Pulang Pisau power station | Buntoi, Kahayan Hilir, Pulang Pisau, Central Kalimantan, Indonesia | -2.822646, 114.208831 (exact) |
The map below shows the exact location of the power station.
Unit-level coordinates (WGS 84):
- Unit 1, Unit 2: -2.822646, 114.208831
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology | Start year |
---|---|---|---|---|---|
Unit 1 | operating | coal: unknown | 60 | subcritical | 2015 |
Unit 2 | operating | coal: unknown | 60 | subcritical | 2015 |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Unit 1 | PT PLN (Persero) [100%] | PT PLN (Persero) [100.0%] |
Unit 2 | PT PLN (Persero) [100%] | PT PLN (Persero) [100.0%] |
Background
The 120 MW Pulang Pisau power station in Central Kalimantan Province is operated by PLN.[1] The construction contract was awarded back in January 2008, to a consortium consisting of China National Heavy Machinery Corporation, Shandong Electric Power Group (a subsidiary of Shandong Energy), and Mega Power Mandiri.[2]
As of October 2014, construction was 83% complete. The plant was scheduled to be completed in May 2015.[3][4]
Although the plant is almost complete, land claims for the site were apparently still in dispute.[3]
In June 2015, workers from the plant were in training for plant operations, and startup appeared to be imminent.[5]
Unit 1 began commercial operations in August 2016.[6] Unit 2 began operating sometime later, most likely in early 2017, although there were no announcements when the unit came online.[7] Both units were operating in October 2018, when they were forced offline by a lightning strike on electrical transmission lines.[8]
In February 2024, PLN opened a tender for woody biomass procurement to supply Kalteng-1 Pulang Pisau power station.[9]
Articles and Resources
References
- ↑ “PLN Long Term Electricity Plan (2013-2023),” presentation by Moch. Sofyan, Head of New & Renewable Division of PT PLN (Persero), 06 March 2014, page 14
- ↑ Konsorsium China Menangkan Tender PLTU Kalteng Rp1,1 Triliun, Antara News, 6 Jan. 2008.
- ↑ 3.0 3.1 Alex Gunawan. Pembangunan PLTU Pulang Pisau Sudah 83 Persen. KabarIndonesia, 12 Oct. 2014.
- ↑ Mei, PLTU Pulang Pisau Beroperasi, Kalteng Post, 9 Jan. 2015.
- ↑ "The first On-Site Training Of Indonesian Central Kalimantan Project," O&M Power, 22 June 2015
- ↑ PLN: PLTU Pulang Pisau Mulai Beroperasi, Republika, Aug. 23, 2016
- ↑ PLTU Pulang Pisau Perkuat Listrik Kalteng-Kalsel, Antara News, Dec. 5, 2016
- ↑ Sofyar Redhani, PLTU Pulangpisau Segera Beroperasi Lagi, Tribun Kalteng, Oct. 8, 2018
- ↑ PENGUMUMAN TENDER TERBUKA PENGADAAN BAHAN BAKAR BIOMASSA (WOODCHIP), PT PLN (Persero), February 2, 2024
Additional data
To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.