Kalteng-1 Pulang Pisau power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Kalteng-1 Pulang Pisau power station is an operating power station of at least 120-megawatts (MW) in Buntoi, Kahayan Hilir, Pulang Pisau, Central Kalimantan, Indonesia.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Kalteng-1 Pulang Pisau power station Buntoi, Kahayan Hilir, Pulang Pisau, Central Kalimantan, Indonesia -2.822646, 114.208831 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2: -2.822646, 114.208831

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year Retired year
Unit 1 operating coal - unknown 60 subcritical 2015
Unit 2 operating coal - unknown 60 subcritical 2015

Table 3: Unit-level ownership and operator details

Unit name Owner
Unit 1 PT PLN (Persero) [100.0%]
Unit 2 PT PLN (Persero) [100.0%]

Background

The 120 MW Pulang Pisau power station in Central Kalimantan Province is operated by PLN.[1] The construction contract was awarded back in January 2008, to a consortium consisting of China National Heavy Machinery Corporation, Shandong Electric Power Group (a subsidiary of Shandong Energy), and Mega Power Mandiri.[2]

As of October 2014, construction was 83% complete. The plant was scheduled to be completed in May 2015.[3][4]

Although the plant is almost complete, land claims for the site were apparently still in dispute.[3]

In June 2015, workers from the plant were in training for plant operations, and startup appeared to be imminent.[5]

Unit 1 began commercial operations in August 2016.[6] Unit 2 began operating sometime later, most likely in early 2017, although there were no announcements when the unit came online.[7] Both units were operating in October 2018, when they were forced offline by a lightning strike on electrical transmission lines.[8]

In February 2024, PLN opened a tender for woody biomass procurement to supply Kalteng-1 Pulang Pisau power station.[9]

Articles and Resources

References

  1. “PLN Long Term Electricity Plan (2013-2023),” presentation by Moch. Sofyan, Head of New & Renewable Division of PT PLN (Persero), 06 March 2014, page 14
  2. Konsorsium China Menangkan Tender PLTU Kalteng Rp1,1 Triliun, Antara News, 6 Jan. 2008.
  3. 3.0 3.1 Alex Gunawan. Pembangunan PLTU Pulang Pisau Sudah 83 Persen. KabarIndonesia, 12 Oct. 2014.
  4. Mei, PLTU Pulang Pisau Beroperasi, Kalteng Post, 9 Jan. 2015.
  5. "The first On-Site Training Of Indonesian Central Kalimantan Project," O&M Power, 22 June 2015
  6. PLN: PLTU Pulang Pisau Mulai Beroperasi, Republika, Aug. 23, 2016
  7. PLTU Pulang Pisau Perkuat Listrik Kalteng-Kalsel, Antara News, Dec. 5, 2016
  8. Sofyar Redhani, PLTU Pulangpisau Segera Beroperasi Lagi, Tribun Kalteng, Oct. 8, 2018
  9. PENGUMUMAN TENDER TERBUKA PENGADAAN BAHAN BAKAR BIOMASSA (WOODCHIP), PT PLN (Persero), February 2, 2024

Additional data

To access additional data, including an interactive map of coal-fired power stations, a downloadable dataset, and summary data, please visit the Global Coal Plant Tracker on the Global Energy Monitor website.