Kaltim FTP2 power station

From Global Energy Monitor
Part of the
Global Coal Plant Tracker,
a Global Energy Monitor project.
Download full dataset
Report an error
Related coal trackers:

Kaltim FTP2 power station is an operating power station of at least 200-megawatts (MW) in East Kutai, East Kalimantan, Indonesia. It is also known as 印尼卡帝姆2期电站.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Kaltim FTP2 power station East Kutai, East Kalimantan, Indonesia 0.0551785, 117.4945887 (exact)

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Unit 1, Unit 2: 0.0551785, 117.4945887

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology Start year
Unit 1 operating coal: unknown 100 subcritical 2019
Unit 2 operating coal: unknown 100 subcritical 2020

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Unit 1 PT PLN (Persero) [100%] PT PLN (Persero) [100.0%]
Unit 2 PT PLN (Persero) [100%] PT PLN (Persero) [100.0%]

Financing

  • Source of financing: Loan from Bank of China

Background

This project is mentioned on Table 13 of the 2015-2024 PT PLN long range supply plan, scheduled for 2018 and 2019.[1] The project comprises two units of 100 MW each. It is located in East Kalimantan near the Sangatta mines operated by Kaltim Prima Coal.[2]

In the 2017-2026 long-range plan, the project is rescheduled to 2026 and is described as an independent power project (IPP).[3] In the 2019-2028 long-range plan the project is rescheduled 2020/2021.[4]

Funding for the Kaltim FTP2 power station was provided by Bank of China. The exact loan amount was not released publicly. The power station was constructed under a Build, Own, Operate, Transfer (BOOT) model, with China Chengda Engineering Co., Ltd. awarded the BOOT contract.[5][6]

Unit 1 was commissioned in October 2019, setting a record for fastest construction of a power plant on Kalimantan.[7] Unit 2 began commercial operations in January 2020.[8]

Environmental impact

People who live near the plant have complained that their catch of fish and harvesting of seaweed from Kadere Bay has diminished since the plant began operating. As of November 2020 the plant had not been used to electrify Lok Tunggul, a neighborhood adjacent to the plant.[9]

Articles and Resources

References

  1. "Executive Summary: Electricity Supply Business Plan PT PLN (Persero) 2015-2024"
  2. "Tantangan Dan Upanya Menuju Kedaulatan Energi Di Provinsi Kalimantan Timur," slide presentation by Dr. H. Awang Faroek Ishak, governor of Kalimantan Timur, April 6, 2016
  3. Rencana Usaha Penyediaan Tenaga Listrik (RUPTL) 2017-2026, PT PLN Persero, p. VI-58
  4. Rencana Usaha Penyediaan Tenaga Listrik (RUPTL) 2019-2028, PT PLN Persero, V-53
  5. 中国成达工程投资建设的印尼KALTIM-2 2x125MW 燃煤电站项目成功并网发电, Sohu, Oct. 9, 2019
  6. 中国成达工程与中国银行四川省分行签署印尼KALTIM-2电站项目贷款协议, BHI, May 11, 2018
  7. prokal.co. "Operasikan Pembangkit Baru, PLTU Kaltim 2 Perkuat Sistem Kelistrikan | ProkalNews". news.prokal.co (in Indonesian). Retrieved 2020-01-13.{{cite web}}: CS1 maint: unrecognized language (link)
  8. Completion of Kaltim-2 2x125MW Coal-Fired Power Plant Project, China Chengda Engineering Co., Ltd., Jan. 13, 2020