Kolubara G Coal Mine

From Global Energy Monitor
This article is part of the
Global Coal Mine Tracker, a project of Global Energy Monitor.
Download full dataset
Report an error
Sub-articles:
Related-articles:

Kolubara G Coal Mine is an operating coal mine in Veliki Crjleni, Central Serbia, Serbia.

Location

Table 1: Project-level location details

Mine Name Location Coordinates (WGS 84)
Kolubara G Coal Mine Veliki Crjleni, Central Serbia, Serbia[1] 44.4678357812436, 20.2664008823712 (exact)

The map below shows the exact location of the coal mine:

Loading map...

Project Details

Table 2: Project status

Status Status Detail Opening Year Closing Year
Operating[2][3] 2017[2][3]

Table 3: Operation details

Note: The asterisk (*) signifies that the value is a GEM estimated figure.
Capacity (Mtpa) Production (Mtpa) Year of Production Mine Type Mining Method Mine Size (km2) Mine Depth (m) Workforce Size
5.7[4] 2022[4] Surface Open Pit 100 909*

Table 4: Coal resources and destination

Total Reserves (Mt) Year of Total Reserves Recorded Total Resources (Mt) Coalfield Coal Type Coal Grade Primary Consumer/ Destination
35[5] Kolubara Lignite Thermal Kolubara B Power Station

Table 5: Ownership and parent company

Owner Parent Company Headquarters
Elektroprivreda Srbije Beograd AD[6] Elektroprivreda Srbije Beograd AD [100%] Serbia

Table 6: Historical production (unit: million tonnes per annum)

ROM or Saleable 2017 2018 2019 2020 2021 2022 2023
Saleable 0[7] 4[8] 6[9] 6[10] 5[11] 5[4] 4[12]

Note: The above section was automatically generated and is based on data from the Global Coal Mine Tracker April 2024 release and the September supplement.

Background

The Kolubara Field G coal mine is a surface mine near Veliki Crljeni, Serbia. The Kolubara Field G coal mine is part of Kolubara Mine Complex.

Field G coal mine is located in the western part of the Kolubara coal basin and it started operating in 2017 after the completed exploitation at the Veliki Crljeni mine, as its substitute capacity.[13][14]

As per 2008 EBRD's document, Veliki Crljeni planned mining start in 2009 and should have ceased mining 2016.[15] Technical report by EPS confirm that Veliki Crljeni section ceased to produce in 2016 and Field G started production in 2017.[16]

As per the basin map from 2011 (see below) Veliki Crleni is located in the central part of the basin. However at the time the map did not yet indicate the location of Field G coal mine. As per Euracoal 2019 report, Field G mine extension was opened in 2017 with 36.5 million tonnes of lignite reserves.[14]

A media source from April 2023 reported that the Field G coal mine will be expanded. According to the decision of the Ministry of of Environmental Protection, the expansion of Field G is necessary due to the delay in the procurement of the equipment for Radjlevo coal mine. Extra volumes of coal would last for another year. The total amount of the coal projected for excavation from Field G is 35 million tonnes, that is, 5 million a year.[13]

A map of the pits of the Kolubara mine complex.
  • Owner: Elektroprivreda Srbije Beograd AD (EPS)
  • Parent Company: Government of the Republic of Serbia
  • Status: Operating
  • Location: Veliki Crljeni, Serbia
  • GPS coordinates: 44.46783578, 20.26640088 (exact)
  • Mine status: Operating
  • Production Capacity: 6.5Mt (2020), 5.2Mt (2021),[17][18] 5.7Mt (2022)[19]
  • Mineable reserves: 35 Mt[13]
  • Coal type: Lignite
  • Mine type: Surface
  • Start year: 2017[14]

Articles and Resources

Additional data

To access additional data, including an interactive map of world coal mines, a downloadable dataset, and summary data, please visit the Global Coal Mine Tracker on the Global Energy Monitor website.

References

  1. (PDF) https://web.archive.org/web/20240121033650/https://bankwatch.org/sites/default/files/Kolubara-resettlement.pdf. Archived from the original (PDF) on 21 January 2024. {{cite web}}: Missing or empty |title= (help)
  2. 2.0 2.1 https://web.archive.org/web/20240121023610/https://euracoal.eu/info/country-profiles/serbia/. Archived from the original on 21 January 2024. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 (PDF) https://web.archive.org/web/20240121023556/https://caneurope.org/content/uploads/2021/09/Lazarevac-engl-web-FINAL-web.pdf. Archived from the original (PDF) on 21 January 2024. {{cite web}}: Missing or empty |title= (help)
  4. 4.0 4.1 4.2 (PDF) https://www.eps.rs/eng/Documents/technicalreports/20230421_TEH_Godisnjak2022_web_en_.pdf. {{cite web}}: Missing or empty |title= (help)
  5. https://web.archive.org/web/20240718175024/https://www.ekapija.com/en/news/4171355/beginning-of-coal-exploitation-at-radljevo-mine-to-be-a-year-and. Archived from the original on 18 July 2024. {{cite web}}: Missing or empty |title= (help)
  6. (PDF) https://web.archive.org/web/20240723042403/https://www.eps.rs/eng/Documents/financialreports/JP%2520EPS%2520consolidated%2520report%25202021.pdf. Archived from the original (PDF) on 23 July 2024. {{cite web}}: Missing or empty |title= (help)
  7. (PDF) https://www.eps.rs/eng/Documents/TEH_Godisnjak2017_web_EN_.pdf. {{cite web}}: Missing or empty |title= (help)
  8. (PDF) https://www.eps.rs/eng/Documents/technicalreports/TEH_Godisnjak2018_web_en.pdf. {{cite web}}: Missing or empty |title= (help)
  9. (PDF) https://www.eps.rs/cir/SiteAssets/Pages/tehnicki-izvestaji/TEH_Godisnjak2019_web_s.pdf. {{cite web}}: Missing or empty |title= (help)
  10. (PDF) https://www.eps.rs/cir/SiteAssets/Pages/tehnicki-izvestaji/TEH_Godisnjak2020_web_s_.pdf. {{cite web}}: Missing or empty |title= (help)
  11. (PDF) https://www.eps.rs/eng/Documents/technicalreports/TEH_Godisnjak2021_web_en_Fin.pdf. {{cite web}}: Missing or empty |title= (help)
  12. (PDF) https://www.eps.rs/eng/Documents/technicalreports/TEH_Godisnjak2023_web_en_.pdf. {{cite web}}: Missing or empty |title= (help)
  13. 13.0 13.1 13.2 "Beginning of Coal Exploitation at Radljevo Mine to Be a Year and a Half Late – Field G to Be Expanded for the Purpose of Supplying TENT". https://www.ekapija.com/. April 2023. {{cite web}}: External link in |website= (help)CS1 maint: url-status (link)
  14. 14.0 14.1 14.2 "Euracoal Serbia profile". euracoal.eu/. 2019.{{cite web}}: CS1 maint: url-status (link)
  15. "STRATEGIC ENVIRONMENTAL IMPACT ASSESSMENT OF THE SPATIAL PLAN OF KOLUBARA MINING BASIN AREA" (PDF). www.ebrd.com. December 2008. {{cite web}}: line feed character in |title= at position 24 (help)CS1 maint: url-status (link)
  16. "EPS 2017 Technical report" (PDF). eps.rs. 2018.{{cite web}}: CS1 maint: url-status (link)
  17. "2020 EPS Technical Report" (PDF). https://www.eps.rs. 2021. {{cite web}}: External link in |website= (help)CS1 maint: url-status (link)
  18. "EPS 2021 Technical Report" (PDF). https://www.eps.rs. 2022. {{cite web}}: External link in |website= (help)CS1 maint: url-status (link)
  19. "EPS Technical report 2022" (PDF). www.eps.rs. 2023.{{cite web}}: CS1 maint: url-status (link)