Kukurda power station
Part of the Global Coal Plant Tracker, a Global Energy Monitor project. |
Related coal trackers: |
Kukurda power station is a cancelled power station in Kukurda, Korba, Chhattisgarh, India. It is also known as Raigar JSW.
Location
Table 1: Project-level location details
Plant name | Location | Coordinates (WGS 84) |
---|---|---|
Kukurda power station | Kukurda, Korba, Chhattisgarh, India | 21.8475, 83.54 (approximate) |
The map below shows the approximate location of the power station.
Project Details
Table 2: Unit-level details
Unit name | Status | Fuel(s) | Capacity (MW) | Technology |
---|---|---|---|---|
Unit 1 | cancelled | coal: unknown | 660 | supercritical |
Unit 2 | cancelled | coal: unknown | 660 | supercritical |
Table 3: Unit-level ownership and operator details
Unit name | Owner | Parent |
---|---|---|
Unit 1 | JSW Energy Ltd [100%] | JSW Energy Ltd [100.0%] |
Unit 2 | JSW Energy Ltd [100%] | JSW Energy Ltd [100.0%] |
Project-level coal details
- Coal source(s): Indonesia until domestic coal available
Financing
Source of financing:
Background
The station is to be built near Kukurda, Nawapara, Dumarpalli, Chhuhipali, and Salheona villages of Raigarh Tehsil, Raigarh District Chhattisgarh, India.[1] JSW refers to a 1320MW project being proposed near Raipur, which is approximately 200 kilometres south west of Raigarh as well as another 100MW project at an unspecified location in Chhattisgarh.[2]
In a January 2012 presentation to investors, JSW Energy stated that the project, comprising two 660MW supercritical plants, was proposed to be based on domestic coal. However, the company states that at present it has an 11% interest in coal block jointly allocated but that it has applied for "additional coal linkage" to ensure adequate supplies for the plant. JSW also states that it has been allocated 35 million cubic metres of water a year from the Mahanadi River. However, as yet the company does not have clearance for the project from the Ministry of Environment and Forests. The company states that "The company states that land acquisition for the project is in "progress satisfactorily" and that it has entered into a power purchase agreement with the Government of Chhattisgarh for 35% of the power from the plant.[3]
The project's March 7, 2012 Environmental clearance permit states that the power station will use imported coal from Indonesia until domestic coal sources are available.[4]
The project is listed in a 2014 JSW Director's report, but does not give a timeline for completion. The plant is only described as permitted.[5]
As of September 2016 there are no reports the project has begun construction, and plans appear to be deferred or abandoned.
Articles and Resources
References
- ↑ Centre for Science and Environment , "Analysis of the Rapid EIA report prepared for JSW ENERGY LTD’S (JSWEL) 2x660 MW coal based thermal power plant at Kukurda, Nawapara, Dumarpalli, Chhuhipali and Salhona villages of Raigarh Tehsil, Raigarh District, Chhattisgarh", Centre for Science and Environment website, accessed February 2012.
- ↑ "Projects Under Development" JSW Energy Ltd., accessed January 31, 2012.
- ↑ JSW Energy, "Energising India", Investor presentation, January 2012, page 20. (Pdf)
- ↑ Environmental clearance, India MoEF, March 7, 2012
- ↑ "Director's Report," JSW Energy, Apr 30, 2014