Luoding power station (粤电广东罗定发电厂, 云浮罗定天然气热电联产项目, 云浮罗定电厂天然气热电联产机组二期项目) is an operating power station of at least 270-megawatts (MW) in Shuangdong District, Luoding, Yunfu, Guangdong, China with multiple units, some of which are not currently operating. It is also known as 云浮罗定电厂燃煤热电联产机组二期项目.

Location

Table 1: Project-level location details

Plant name Location Coordinates (WGS 84)
Luoding power station Shuangdong District, Luoding, Yunfu, Guangdong, China 22.8044935, 111.6182819 (exact)[1]

The map below shows the exact location of the power station.

Loading map...


Unit-level coordinates (WGS 84):

  • Phase II CHP 1, Phase II CHP 2, Phase II Unit 3, Phase II Unit 4, Unit 1, Unit 2: 22.8044935, 111.6182819

Project Details

Table 2: Unit-level details

Unit name Status Fuel(s) Capacity (MW) Technology CHP Start year
Phase II CHP 1 Announced[2] fossil gas: natural gas[3][4] 460[3] combined cycle[3] yes[4]
Phase II CHP 2 Announced[2] fossil gas: natural gas[3][4] 460[3] combined cycle[3] yes[4]
Phase II Unit 3 Announced coal: unknown 660[1] ultra-supercritical 2026 (planned)[1]
Phase II Unit 4 Announced coal: unknown 660[1] ultra-supercritical 2026 (planned)[1]
Unit 1 Operating coal: anthracite 135 subcritical 2004
Unit 2 Operating coal: anthracite 135 subcritical 2004

CHP is an abbreviation for Combined Heat and Power. It is a technology that produces electricity and thermal energy at high efficiencies. Coal units track this information in the Captive Use section when known.

Table 3: Unit-level ownership and operator details

Unit name Owner Parent
Phase II CHP 1 Guangdong Yuelong Power Generation Co Ltd [100%] Guangdong Hengjian Investment Holding Co Ltd [61.6%]; China Huaneng Group Co Ltd [19.4%]; Guangdong Electric Power Development Co Ltd [9.0%]; Luoding Yida Investment Development Co Ltd [8.0%]; Luoding Yixin Investment Development Co Ltd [1.6%]; Foshan Dongping Asset Management Co Ltd [0.2%]; Yunfu Yunsheng Investment Development Co Ltd [0.1%]; Yunfu Infrastructure Construction Investment Group Co Ltd [0.1%]; Guangdong Yunfu Land Property Co [0.0%]; unknown [0.0%]
Phase II CHP 2 Guangdong Yuelong Power Generation Co Ltd [100%] Guangdong Hengjian Investment Holding Co Ltd [61.6%]; China Huaneng Group Co Ltd [19.4%]; Guangdong Electric Power Development Co Ltd [9.0%]; Luoding Yida Investment Development Co Ltd [8.0%]; Luoding Yixin Investment Development Co Ltd [1.6%]; Foshan Dongping Asset Management Co Ltd [0.2%]; Yunfu Yunsheng Investment Development Co Ltd [0.1%]; Yunfu Infrastructure Construction Investment Group Co Ltd [0.1%]; Guangdong Yunfu Land Property Co [0.0%]; unknown [0.0%]
Phase II Unit 3 Guangdong Yuelong Power Generation Co Ltd [100%] Guangdong Hengjian Investment Holding Co Ltd [61.6%]; China Huaneng Group Co Ltd [19.4%]; Guangdong Electric Power Development Co Ltd [9.0%]; Luoding Yida Investment Development Co Ltd [8.0%]; Luoding Yixin Investment Development Co Ltd [1.6%]; Foshan Dongping Asset Management Co Ltd [0.2%]; Yunfu Yunsheng Investment Development Co Ltd [0.1%]; Yunfu Infrastructure Construction Investment Group Co Ltd [0.1%]; Guangdong Yunfu Land Property Co [0.0%]; unknown [0.0%]
Phase II Unit 4 Guangdong Yuelong Power Generation Co Ltd [100%] Guangdong Hengjian Investment Holding Co Ltd [61.6%]; China Huaneng Group Co Ltd [19.4%]; Guangdong Electric Power Development Co Ltd [9.0%]; Luoding Yida Investment Development Co Ltd [8.0%]; Luoding Yixin Investment Development Co Ltd [1.6%]; Foshan Dongping Asset Management Co Ltd [0.2%]; Yunfu Yunsheng Investment Development Co Ltd [0.1%]; Yunfu Infrastructure Construction Investment Group Co Ltd [0.1%]; Guangdong Yunfu Land Property Co [0.0%]; unknown [0.0%]
Unit 1 Guangdong Yuelong Power Generation Co Ltd [100%] Guangdong Hengjian Investment Holding Co Ltd [61.6%]; China Huaneng Group Co Ltd [19.4%]; Guangdong Electric Power Development Co Ltd [9.0%]; Luoding Yida Investment Development Co Ltd [8.0%]; Luoding Yixin Investment Development Co Ltd [1.6%]; Foshan Dongping Asset Management Co Ltd [0.2%]; Yunfu Yunsheng Investment Development Co Ltd [0.1%]; Yunfu Infrastructure Construction Investment Group Co Ltd [0.1%]; Guangdong Yunfu Land Property Co [0.0%]; unknown [0.0%]
Unit 2 Guangdong Yuelong Power Generation Co Ltd [100%] Guangdong Hengjian Investment Holding Co Ltd [61.6%]; China Huaneng Group Co Ltd [19.4%]; Guangdong Electric Power Development Co Ltd [9.0%]; Luoding Yida Investment Development Co Ltd [8.0%]; Luoding Yixin Investment Development Co Ltd [1.6%]; Foshan Dongping Asset Management Co Ltd [0.2%]; Yunfu Yunsheng Investment Development Co Ltd [0.1%]; Yunfu Infrastructure Construction Investment Group Co Ltd [0.1%]; Guangdong Yunfu Land Property Co [0.0%]; unknown [0.0%]

Background

Luoding power station is a two-unit coal-fired power plant with a total capacity of 270 MW. The plant was completed in 2004, and is owned by Guangdong Yudean Group. It is a CHP power plant, supplying heat and steam to Shuangdong Industrial Zone where it is located, besides power generation. [5]

Articles and Resources

References

  1. 1.0 1.1 1.2 1.3 1.4 "粤泷发电公司"云浮罗定电厂燃煤热电联产机组二期项目"社会稳定风险评估公示-罗定市人民政府门户网站". www.luoding.gov.cn. 2023-11-02. Archived from the original on 2024-02-12. Retrieved 2024-01-05.
  2. 2.0 2.1 https://www.yunfu.gov.cn/yfsrmzf/jcxxgk/zcfg/zfwj/content/post_1596677.html. {{cite web}}: Missing or empty |title= (help)
  3. 3.0 3.1 3.2 3.3 3.4 3.5 (PDF) https://www.yunfu.gov.cn/attachment/0/68/68719/1688294.pdf. {{cite web}}: Missing or empty |title= (help)
  4. 4.0 4.1 4.2 4.3 (PDF) https://www.yunfu.gov.cn/attachment/0/96/96785/1852227.pdf. {{cite web}}: Missing or empty |title= (help)
  5. "广东省粤泷发电有限责任公司"Guangdong Yudean Group, 2016-5-27