Maspo Ala-2 geothermal power plant is an operating geothermal power plant in Alaşehir, Türkiye.

Project Details

Table 1: Unit-level project details for Maspo Ala-2 geothermal power plant

Status Commissioning year Nameplate capacity Technology Owner
Operating[1] 2019[1] 30 MW[2] Binary cycle[3] Maspo Energy AS [100%][4]

Location

Table 2: Unit-level location details for Maspo Ala-2 geothermal power plant

Location Coordinates (WGS 84)
Alaşehir, Türkiye 38.4222, 28.3892 (exact)

The map below shows the exact location of the geothermal power plant:

Loading map...

Articles and Resources

Additional data

To access additional data, including an interactive map of global geothermal power plants, a downloadable dataset, and summary data, please visit the Global Geothermal Power Tracker on the Global Energy Monitor website.

References

  1. 1.0 1.1 https://web.archive.org/web/20220303221530/https://www.thinkgeoenergy.com/30-mw-maspo-ala-2-geothermal-plant-started-commercial-operation-in-turkey/. Archived from the original on 03 March 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  2. https://web.archive.org/web/20220303220440/https://www.royalcertenerji.com/portfolio/maspo-ala-2-jes/. Archived from the original on 03 March 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)
  3. https://web.archive.org/web/20220630044316/https://www.enprode.com/PROJECTS/Ongoing-Turkey-Maspo-Geothermal-Power-Plant. Archived from the original on 30 June 2022. {{cite web}}: Missing or empty |title= (help)
  4. https://web.archive.org/web/20221108130549/http://thinkgeoenergy.com/map. Archived from the original on 08 November 2022. {{cite web}}: Check date values in: |archive-date= (help); Missing or empty |title= (help)